New 2FE (420 place) primary school plus 60-place nursery school provision on greenfield site in Larkhill, Wiltshire. This project was part of the Army Rebasing Programme for the relocation of troops from Germany with 917 homes constructed by Morgan Sindall Group sister company, Lovell.
Challenging site access
The installation of the planned approach road to site (not undertaken by Morgan Sindall) was delayed and not in place for the start of works.
Complex topography and formation of terraced hard landscaping
The topography of the site involved a 15m gradient across the site.
Bringing the project to budget
A VE exercise was undertaken during the second stage to identify opportunities and suggest alternative products or rationalisation of the design, to bring the project to budget.
Challenging site access
We had to utilise an alternative 2.5 mile redundant off-road ‘tank’ track. Prior to being able to use this route, appropriate UXO and archaeology certificates had to be obtained.
Complex topography and formation of terraced hard landscaping
The school building itself was positioned at the lowest part of the slope, with the courtyard and break-out areas to the rear on the same elevation. The first terrace was formed using a stone gabion retaining structure, leading to soft landscaping. The next level was formed with a timber crib local wall providing the Multi-Use Games Area (MUGA). The following terrace created a wild flower meadow, and finally the top level provided the sports pitches.
Bringing the project to budget
The VE exercise identified the following:
A Siniat Weather Defence Board was identified as an alternative product which reduces reliance on workmanship, providing a consistent quality finish and reducing the need for third-party quality checks, saving costs.
Omission of Brise Solei and adjustment to floor finishes, provided a £20k saving to the school’s life cycle costs.
Thickness of the ground floor slab was reduced from 200mm all over, to 150mm to all areas, except the plant room and main hall, saving £20k.
Composite windows were changed to aluminium, saving £50k. Aluminium windows offer the same BREEAM rating, achieve the same U value and are a more robust product.
We identified over £436k of savings through the VE exercise up to Gateway 3, an additional £10k to incorporate cycle storage, and a further £220k incorporated during the project (signed off at Gateway 4). We also successfully delivered the project to a delighted client who gave us a recommended score of 9/10.
100% payment within 30 days terms
Soft landings for handover
Dedicated Morgan Sindall point of contact
On-line portal for notifying any defects with 3 priority categories for response times
100% timber responsibly sourced
Zero RIDDORs
29 beneficiaries