• SCF Client Portal
Logo
  • Support
    • Working with SCF
    • Meet the team
  • Our Frameworks
    • SCF Construct
      • Partnering Contractors
    • SCF Intermediate
      • Intermediate contractors
    • SCF Consult
      • Consultant Partners
  • Our Projects
    • Case Studies
    • Video Testimonials
    • SCF Social Value
  • Resources
    • Market Intelligence
    • Sustainability
    • Contractor and Suppliers Support
    • SCF Documents
    • SCF Passport Training
    • Building Safety Act 2022
  • SCF6 Procurement
  • News
  • Contact
  • Click to open the search input field Click to open the search input field Search
  • Menu Menu

North Devon Enterprise Centre (Node) Expansion

The second phase expansion will bring an extra 564sq metres of flexible office space to support the growth of the hub

  • Client

    Devon County Council

  • Contractor

  • Value

    £2,009,000

  • Completion Date

    March 2023

PROJECT ON SITE

Based upon successful delivery of the North Devon Enterprise Centre (Node) at One Enterprise Road in Barnstaple which was completed in 2021, ISG were selected to deliver the NODE Expansion project which started on site in June 2022.

Within the first year of operating, Node had already let 64% of its 37 offices after just eight months. The second phase expansion will bring an extra 564 sq. metres of flexible office space across the ground and first floor and additional parking provision to create an extra 48 carparking spaces.

Design and build of the RIBA Stage 4 onwards project involves both advance site-wide infrastructure works and the build-out of the Enterprise Centre and associated plot works.

Designed to look identical to the existing building, Devon County Council requested that ISG design and construct the extension in spirit of the BREEAM Excellent standard of the original building.

Whilst undertaking the original Node project, ISG held collaborative design workshops with the architect to gain an in-depth understanding of how the business park would develop. With the development of RIBA stage 3 design to provide a RIBA stage 4 solution for a future proofed development, ISG incorporated technical design features to allow easy expansion/extension of the Node building’s structure and infrastructure.

SCF Logo White

Two Stage Open Book Procurement delivered by the public sector, for the public sector.

  • Cookie Policy
SCF is a member of NACF, a national collective of regional frameworks which shares best practice expertise and experience.
© 2026 - Website by Blaze Concepts
Link to: University of Chichester Link to: University of Chichester University of Chichester Link to: Fareham Innovation Centre – Phase 2 Extension, HMS Daedalus Link to: Fareham Innovation Centre – Phase 2 Extension, HMS Daedalus Fareham Innovation Centre – Phase 2 Extension, HMS Daedalus Scroll to top Scroll to top Scroll to top