• SCF Client Portal
Logo
  • Support
    • Working with SCF
    • Meet the team
  • Our Frameworks
    • SCF Construct
      • Partnering Contractors
    • SCF Intermediate
      • Intermediate contractors
    • SCF Consult
      • Consultant Partners
  • Our Projects
    • Case Studies
    • Video Testimonials
    • SCF Social Value
  • Resources
    • Market Intelligence
    • Sustainability
    • Contractor and Suppliers Support
    • SCF Documents
    • SCF Passport Training
    • Building Safety Act 2022
  • SCF6 Procurement
  • News
  • Contact
  • Click to open the search input field Click to open the search input field Search
  • Menu Menu

Abbey View Primary Academy

  • Client

    Buckingham County Council 

  • Contractor

  • Value

    £6.8m 

  • Completion Date

    August 2019 

The Challenge

The design was carried out in two volumes – developing the design for the school and for future extension.  The project had a BIM Level 2 requirement with a verification point cloud survey to be carried out prior to handing over the asset information model. 

The biggest challenge was the Building Control review of the high performance fast-track SIPS construction and associated structural elements (supporting steelwork and precast concrete first floor and stairs). 

The Solution

Morgan Sindall took the project from RIBA Stage 2 and developed the design to Stage 5.  A BIM model was produced which incorporated the architectural, structural, civil, MEPH and specialist sprinkler designs.  The FF&E and catering subcontractor models were developed alter and incorporated in the Project Information Model. 

The school was built using Structural Insulated Panels (SIPs) structural frame with a series of panels manufactured off-site and assembled on-site.  To make best use of the clash detection process, the SIPSs subcontractor Innovare began work alongside the design consultants at Stage 3.  The MEPH subcontractor also began work early during the design period allowing access zones around the plan equipment to be added to the BIM Execution Plan as a modelling item.  Once the SIPs frame was installed, it was laser scanned.  The scan output could then be used to compare the built asset against the digital model. 

The Results

The use of a Project Information Manager was invaluable to the design team meeting COBie requirements.  This resulted in the last validation reporting showing Stage 4 data was on target and met the Information Exchange requirements.  The design team continued to develop the model with a final update carried out after the point cloud information was issued to form an accurate Asset Information Model. 

The off-site manufacture approach created a bespoke solution which provide cost efficiencies through a standardisation of the process and increases sustainability through a fabric-first approach.  The SIPs were manufactured under factory controlled conditions resulting in a system that was extremely quick to install, strong, energy-efficient and cost and time effective. 

6

Apprentices

91%

SME Spend

£600k

Added Value

8/10

Client Satisfaction

Contractor Performance | Commitments

Legacy

29 No of SMEs  – 22 beneficiaries – 5 jobs created – 155 trainee weeks 

Schools engagement: 30 students – 86% social value created 

£300 donations to charity  – 30 volunteer hours 

Sustainability

97% waste diverted from landfill 

100% timber responsibly sourced 

Order placed with Community Wood Recycling and a wood recycling bay for regular collections was set up.  This resulted in 14.3 tonnes collected with a saving of £492.06 and the majority being high-grade reuse. 

Aftercare

Soft landings for handover 

Dedicated Morgan Sindall point of contact 

On-line portal for notifying any defects with 3 priority categories for response times 

Safe

Zero RIDDORS

CCS Score 43/45 

Fair

100% payment within 30 days terms

Client Testimonials

“Felt as though the team went beyond just delivery a project.” 

Adrian CouchCapital Projects Performance Manager, Buckinghamshire County Council
Previous Previous Previous Next Next Next

SCF Logo White

Two Stage Open Book Procurement delivered by the public sector, for the public sector.

  • Cookie Policy
SCF is a member of NACF, a national collective of regional frameworks which shares best practice expertise and experience.
© 2026 - Website by Blaze Concepts
Link to: Silverwood SEND School Link to: Silverwood SEND School Silverwood SEND School Link to: Philip Southcote School Link to: Philip Southcote School Philip Southcote School Scroll to top Scroll to top Scroll to top