Engineering & Digital Technology Park, University of Chichester
Bognor Regis
Project Details
Client
University of Chichester
Project Manager
AECOM
Architect
Stride Treglown
Contractor
Galliford Try
Value
£21.3m
Contract Period
85 weeks
Procurement Type
Two-Stage
Form of Contract
NEC3 Option A
Size
6,340sqm
Apprentices
700 weeks
Project Summary
The Engineering and Digital Technology Park provides a purpose built facility for the Engineering & Design and Creative & Digital Technologies departments. A landmark STEM building that was officially opened by the Duke and Duchess of Sussex.
In addition to providing a range of research and practical spaces for these two departments, the new building includes the creation of a Research Centre for Sustainable Operations and Departments of Data Science and Advanced Engineering & Design.
The building is available for use by the industry and provides a large multipurpose engineering laboratory incorporating workshop, cleanroom and wet area, facilities to teach electronics and Computer Aided Design (CAD), a fabrication laboratory, prototype manufacturing facilities and collaborative co-working spaces.
The Creative & Digital Technologies Department includes 2no. sound stages, digital editing studios as well as a TV production studio, green room, social learning spaces and ancillary facilities.
The site is located within a flood zone 3 area, which posed a significant challenge for the design and construction, involving Galliford Try and the design team undertaking significant flood risk assessment modelling to ensure the design was deliverable.
This important project for the area was opened by the Duke and Duchess of Sussex in October 2018 and achieved BREEAM Excellent.
“The university’s engineering and digital technology park will produce the engineering and scientific skills that the UK economy needs, particularly at a time when Brexit gives an even greater emphasis on the need for our economy to be internationally and industrially competitive.”
Project Takeaways
Value Added
- BREEAM Excellent
- Social Added Value: £275,705
KPI’s & Statistics
Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
---|---|---|---|
Cost | £32m | £21.3m (included scope reduction) | -33.60% |
Time | 77 weeks | 85 weeks | 10.70% |
- Average CCS Score: 41