• SCF Client Portal
Logo
  • Support
    • Working with SCF
    • Meet the team
  • Our Frameworks
    • SCF Construct
      • Partnering Contractors
    • SCF Intermediate
      • Intermediate contractors
    • SCF Consult
      • Consultant Partners
  • Our Projects
    • Case Studies
    • Video Testimonials
    • SCF Social Value
  • Resources
    • Market Intelligence
    • Sustainability
    • Contractor and Suppliers Support
    • SCF Documents
    • SCF Passport Training
    • Building Safety Act 2022
  • SCF6 Procurement
  • News
  • Contact
  • Click to open the search input field Click to open the search input field Search
  • Menu Menu

The Castle School

  • Client

    South Gloucestershire Council 

  • Contractor

  • Value

    £11m 

  • Completion Date

    June 2024 

The Challenge

The Castle School project in Thornbury required a significant expansion to support its growing Sixth Form cohort, requiring a new three‑storey extension for Maths and Science teaching. The project also required a link bridge connecting the new block to the existing secondary school building, ensuring a seamless campus layout. 

However, delivering this scheme posed several key challenges largely around disruption to the school; this included: 

Working within a live school environment: Works were undertaken while the school remained open, meaning student safety, staff access, and uninterrupted learning had to be protected at all times. 

Complex ground conditions: Beneath the preserved tarmac areas lay Type 1 build-up and shallow hard rock, meaning foundation and drainage works required drilling operations that risked generating prolonged noise. 

Tight exam‑based restrictions: Noisy or disruptive works could not clash with GCSE and A‑Level exam periods, narrowing the available working windows. 

Sensitive neighbouring receptors: Surrounding residential streets—Park Road, Regents Close, Alexandra Way—and a nearby care home required careful environmental management around noise and dust. 

Busy school‑day traffic movements: With hundreds of daily drop‑offs and pick‑ups, deliveries needed strict control to avoid congestion and maintain site safety 

The Solution

The project team implemented a comprehensive package of operational controls, programming adjustments, and environmental protections to deliver the new block safely and efficiently.  

Disruptive works such as rockbreaking and drilling tasks were scheduled outside exam periods, with the majority delivered during the summer holidays to avoid noise during teaching hours. 

The team kept as much of the existing roadway and hardstanding in place which reduced unnecessary ground disturbance, improved site cleanliness, and prevented mud tracking onto public routes

Timed delivery restrictions were introduced to avoid conflict with school traffic. 

The Results

Through meticulous planning and a proactive approach to environmental and stakeholder management, the project was delivered with: 

Minimal disruption to school life, including zero clashes with exams despite significant drilling and groundworks. 

Enhanced safety for students, staff, visitors, and construction personnel due to carefully managed vehicle movements and clear site logistics. 

Excellent environmental performance, with noise and dust impacts effectively controlled and monitored in real time. 

A modern, connected Sixth Form facility offering high quality Maths and Science teaching spaces, improving the school’s capacity and creating a more cohesive campus layout. 

A successfully delivered project that demonstrates how thoughtful planning enables significant construction activity within challenging live school environments. 

 Amid the challenges faced, the project was delivered one week ahead of programme. 

10

Number of apprentices

69.4%

SME Spend

£53,700

Added Value

9/10

Client Satisfaction

Client Testimonials

“The thought of a huge construction project was daunting, I’ve never had any experience in that area – It could have been really chaotic! But to be honest, most of the time I wouldn’t have even known that the work was going on. I got regular updates; I was allowed on site to see progress and all of that reassured me. It never felt like we were unsafe, because of the relationship between Morgan Sindall and the school”.  

Jessica LobbettHeadteacher, The Castle School, Thornbury
Previous Previous Previous Next Next Next

Contractor Performance | Commitments

Sustainability

100% waste diverted from landfill 

43T of CO2e saved  

100% timber responsibly sourced 

Safe

Zero RIDDORs 

CCS Score 45/45 

 

Aftercare

Soft landings for handover and Dedicated Morgan Sindall point of contact 

On-line portal for notifying any defects with 3 priority categories for response times 

Fair

100% payment within 30 days terms

Legacy

87.1% No of SMEs, 15 jobs created, 12 Work Experience (11 – in Education/ 1 – not in education)

546 training weeks on site (Apprenticeships, Traineeships, Technical/Higher Level Qualifications)

£1.3k donations to charity/material donations, 28 volunteer hours, £6.5m social value created

SCF Logo White

Two Stage Open Book Procurement delivered by the public sector, for the public sector.

  • Cookie Policy
SCF is a member of NACF, a national collective of regional frameworks which shares best practice expertise and experience.
© 2026 - Website by Blaze Concepts
Link to: Stanhope Primary School Link to: Stanhope Primary School Stanhope Primary School Link to: Oakmoor Secondary School Exapansion Link to: Oakmoor Secondary School Exapansion Oakmoor Secondary School Exapansion Scroll to top Scroll to top Scroll to top