Woodmansterne Secondary School

Streatham, Lambeth

Project Details

Client
Lambeth London Borough Council

Project Manager
Faithful and Gould

Architect
Peter Taylor Associates Limited

Contractor
Willmott Dixon

Value
£21.3 million

Contract Period
48 weeks

Procurement Type
Two Stage Open Book Design and Build

Form of Contract
Jct 2011 Minor Works

Apprentices Engaged
5

BIM
Level 2 Construct

New 5 full education secondary school with 150 pupil sixth form. Works to be undertaken within the demolition area and consist of an RC Frame / Gebrik Cladding system and Glazing to the envelope, associated MUGA Pitches and external works and include the installation and removal of temporary classrooms.

Urban Beach Programme for Inner City Schools

Due to the temporary loss of access to the schools’ ecological area, the site team have developed an Urban Beach Programme to bring the coast to city pupils, raising their awareness of the coastal environment and the need to protect it. Woodmansterne school is the pilot for the Urban Beach Programme, and is partnered with the Marine Conservation Society, with Willmott Dixon fully funding the pilot programme by providing resources, staff and funding the coach trip to the Grain Coastal Park.

It is based on the Wildbeach programme developed by the wildlife Trusts and has been fully adapted to be delivered in inner city schools with the aim to get the children to the beach by the end of the programme. A new topic is introduced each week covering areas such as species ID, tides, human impact, food webs, marine processes and more.

The programme began with two year 3 classes of 30 and ran for 6 weeks, culminating in a field trip to the beach. The majority of the sessions are delivered in the school field to promote outdoor learning.

Local volunteers were sought through the Marine Conservation Society, providing an opportunity for anyone looking for a career in marine education.

The programme will continue with one of the volunteers taking over the project to deliver to the next year group selected by the school. The Marine Conservation Society is also looking out for the right candidate so this can be rolled out to other schools.

ContractGateway 2 PlanningGateway 3 Contract AgreementVariation
Cost£2,5532,4122 (£141.00)
Time48 weeks48 weeks0

KPI Graphs

Apprentices 5

Average AIR NIL

Average CCS score 47(out of 50)

Waste diverted from landfill 99%

Cost/m2 £3,1K/m2