Project details
Form of Contract: NEC3 Engineering and Construction Contract April 2013
Procurement Type: 2 Stage
Contract Period: 97 weeks
Size: 55,000 sqft
The project comprised of the refurbishment and upgrade of our client’s estate under their ‘Restoration and Renewal Programme’. The project endeavoured to deliver maximum flexibility and usability for a design life of 15 years, achieving BREEAM Excellent.
The project included CAT B fit out of offices, a new reception, new meeting rooms and collaboration spaces. Our scope of works also included structural alterations, window replacements and external works and security enhancements of 55,000 sq ft over 9 floors including roof and terraces in a 1920’s building.
Multiple stakeholder engagement
The scope included the decant of large numbers of staff to allow 750 new staff to occupy their new space.
Engaging with government recommended contractors
We had to liaise with government recommended subcontractors with their own works packages within the building.
Delivering in a Global Pandemic
The PCSA and part of the construction period spanned the unprecedented Covid-19 Global Pandemic.
Challenging logistics
The project was located in central London, with the building located on a busy road. The building was occupied for the duration of the works.
Base build fit out
It became clear the CAT A wasn’t fit for purpose; extensive reparations were required before the CAT B could begin.
Multiple stakeholder engagement
ISG engaged early in the preconstruction phase with incoming government departments to build a move-in calendar for each department. We also held coordination workshops with the client’s in-house design team, data teams, security and maintenance teams, and catering teams.
Engaging with government recommended contractors
We engaged at tender stage with government recommended subcontractors and incorporated their specialist programmes into our master programme to calibrate and synchronise our works.
Delivering in a Global Pandemic
Our industry leading Covid-19 safety measures ensured minimal disruption to the project despite lockdowns and social distancing measures, in the challenging conditions of an unprecedented global pandemic.
Challenging logistics
The logistics of the site was very tight. The scope included the removal and replacement of the lift motor room. We agreed the use of a full height hoist to the front elevation for movement of materials and operatives into the building. Neighbouring businesses and residents were kept informed of our progress and we received zero complaints of disruption.
Base build fit out
After notifying the client of the issues with the base build, we removed infrastructure back to risers and validated all CAT A base-build plant, effectively providing the client with a turnkey solution.
Early engagement with government subcontractors enabled the programme to progress efficiently and smoothly
The ISG and client team remained safe, proactive, focused and driven to achieve all key sign offs and milestones throughout the project lifecycle
The occupants of the space moved into their new offices on time, with support of the ISG team
Neighbouring business and residents were satisfied with our logistics approach, we received zero complaints
Effectively delivered a turn-key solution for the client
100% payment within 30 days
Achieved BREEAM Excellent
Zero RIDDORs
Handover & Aftercare Contractor Promise
ISG maintains ongoing community engagement with three organisations:
The Passage – refurbishment of their entrance / circulation / break out zones
One Westminster – welfare facilities refurbishment
St Mungo’s – PPE donations
Email: alex.nelhams@hants.gov.uk
Phone: 07717 003869
Email: matt.glass@isgltd.com
Phone: 07929755500