Ashmole Primary School

  • Client

    ESFA

  • Contractor

  • Value

    £7.5m

  • Completion Date

    November 2018

A new-build 2FE school to provide a permanent new home for Ashmole Primary School. The school  created 420 places for pupils aged four to 11 and provides teaching space for KS1 and KS2 along with offices, a sports hall, a community room and a canteen.

The Challenge

The school was built on a land-filled site with debris built up from previous excavations in the local area. The ground was found to contain asbestos and obstructions. The risk was quantified and a management strategy was put in place to remove the asbestos and obstructions from the site. This put significant pressure on the project programme.

The Solution

The use of SIPs achieved a 10 week programme saving during the pre-construction phase and a five week programme saving during the construction phase of the project. This has led to SIPs being used on subsequent SCF and Morgan Sindall projects. The frame, including the roof, floor and walls, was installed in 13 weeks, which is a significant saving compared to traditional construction methods.

The Results

The use of SIPs achieved a 10 week programme saving during the pre-construction phase and a five week programme saving during the construction phase of the project. This has led to SIPs being used on subsequent SCF and Morgan Sindall projects. The frame, including the roof, floor and walls, was installed in 13 weeks, which is a significant saving compared to traditional construction methods.

91.5%

SME Spend

£252k

Added Value

9/10

Client Satisfaction

Client Testimonials

The on-site management team’s highly professional and collaborative approach enabled the new building to be completed on a demanding programme to a high standard of quality ready for the school to occupy

Contractor Performance | Commitments

Fair

100% payment within 30 days terms

Sustainability

98% waste diverted from landfill

100% timber responsibly sourced

Safe

Zero RIDDORs

CCS Score 39/45

Legacy

7 work experience placements

94 apprenticeship weeks

£5k charitable donations

23 SMEs

Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times

SCF Framework Manager

James Wright

Email: james.wright@hants.gov.uk

Phone: : 07761 330560

Contractor Framework Manager

Alan Smedley

Email: alan.smedley@morgansindall.com

Phone: 07967 686066