Bristol Humanities Hub
The new state-of-the-art Humanities Building is in the Arts Complex surrounded by a series of handsome of Victorian villas with Woodland Road nearby.
The new state-of-the-art Humanities Building is in the Arts Complex surrounded by a series of handsome of Victorian villas with Woodland Road nearby.
Project Details
Procurement Type:
Two Stage
Form of Contract:
NEC version 4
Contract Period: 86 weeks
Size: 29,375 sq ft
Restricted footprint – The dimensions of the site were 30 x 70m in a complex urban live environment adjacent to occupied Grade II listed properties.
Demolition in a confined live environment – The confined nature of the site required sensitive demolition.
Impact on adjacent Grade II Listed buildings – The original site comprised of an existing single storey building and external courtyard space, located behind the two main Grade ΙΙ listed villas.
Basement design – A key project driver was the basement solution confirmed as this was vital to achieving the budget and programme.
Design of the retaining structure – With budget and programme constraints to consider, a hybrid solution was developed, which moved away from the simplest option of using contiguous piling in all three areas.
Ventilation solution and occupancy level assumptions – We reduced occupancy levels, which enabled natural ventilation to be considered. This supported the aspiration in line with BREEAM Excellent.
Restricted footprint – Due to the confines of the site, we could not use mobile cranes as these would have required lorries to support the mobile cranes, increasing congestion of local roads to an impractical level for our neighbours. As an alternative, we used a tower crane which occupied less room occupying only 5 x 5m and preventing unnecessary disturbance to the local community.
Demolition in a confined live environment – Demolition was planned to have minimum impact on students, faculty and adjacent privately owned student accommodation during holiday periods starting in July 2018. In collaboration with the client’s facilities management team, we isolated fire alarms and ensured there was a temporary fire strategy for retained buildings following demolition of existing structures.
Impact on adjacent Grade II Listed buildings – Adjacency to existing buildings was immediately identified during the pre-construction phase as a key area of design risk. Early works involved re-evaluating the basement perimeter, to increase the area between existing buildings and the boundary, whilst maximising the footprint to accommodate a lecture theatre, cinema, and plant room.
Basement design – The original basement depth and proximity to existing structures (party wall) and retained teaching facilities presented a risk to construction. During the design phase we relocated the basement, minimising the risk to programme, cost, and buildability. Our design team reviewed spatial planning and reconfigured internal layouts which were agreed in collaboration with the client’s project manager and client stakeholders. Our solution used off-site manufactured pre-cast basement walls which reduced programme time. This demonstrated a six-week saving to the original programme.
Design of the retaining structure – Retaining structure solutions:
Ventilation solution and occupancy level assumption – We introduced natural ventilation on the first floor. Using thermal modelling we reassessed and rationalised the mechanical to natural ventilation. This aligned the scheme with the client’s aspiration to have natural ventilation wherever possible. This allowed reduction in the requirements of ventilation. We reduced large ducts within and on the side of the building creating additional floor space. We removed the need for large risers allowing us to provide extra cupboards and increased floor plan space.
100% payment within 30-day terms
100% waste diverted from landfill.
BREEAM Excellent
Green roof, photovoltaics, natural ventilation
Zero RIDDORs
CCS Score 42/50
4 Open Doors sessions
34 attendees to a Women in Property site visit
WOWEX (World of Work Experience) – 18 attendees with 5 accepted onto ISG’s apprenticeship programme
10 school and college visits engaging 400 young people
15 community events
10 jobs created
Handover & Aftercare Contractor Promise
Email: kingsley.clarke@devon.gov.uk
Phone: 07805760622