Project Details
Procurement Type: Two stage
Form of Contract: JCT Design and Build Contract 2016
Contract Period: 42 weeks
Size: 1,329m2
Provision of much-needed grow out space for maturing STEMM (science, technology, engineering, maths and medical) businesses at Exeter Science Park.
Constructed to net zero carbon standards, the ‘BREEAM Excellent’ building is configured to provide 3 floors comprising bespoke laboratory and office accommodation, now known as The George Parker Bidder Building.
The building is the latest in a rolling series of developments in which ESP has demonstrated an approach of Continuous Improvement in its built estate, particularly relating to the environmental performance of buildings.
The project was externally funded. However, the funding cost and time envelopes were extremely challenging, necessitating a completion within 18 months of funding award. Morgan Sindall was formally appointed as Design and Build contractor in November 2021, leaving less than 14 months to take develop the RIBA 2 design price the project, agree the price and contract, and deliver the scheme.
Additionally, sustainability and climate change imperatives were at the heart of the project. This project’s Net Zero Carbon in Use is a steppingstone to the client’s ultimate aim of developing carbon negative buildings that generate more power than they use, creating a carbon “payback” within the lifetime of the building.
Working to develop the design “at risk” through the main contractor selection process, allowed the early appointment of key subcontractors, which was required to meet the challenging programme. Furthermore, the client supported Morgan Sindall’s procurement strategy through early instruction of programme-critical structural steelwork order.
The building was designed and delivered to meet the Green Building Councils definition of Nett Zero carbon in use. Our team employed a “Fabric First” strategy to achieve the required sustainability and climate change imperatives.
An Integrative, collaborative approach characterised all aspects of the project conception, design development and delivery.
The results of this approach are:
Furthermore, in achieving the required environment targets:
Soft landings for handover
Dedicated Morgan Sindall point of contact
On-line portal for notifying any defects with 3 priority categories for response times
100% payment within 30 days terms
Zero RIDDORs
CCS Score 40/45
The building was designed and delivered to meet the Green Building Councils definition of Nett Zero carbon in use. Our team employed a “Fabric First” strategy to achieve the required sustainability and climate change imperatives.
Zero carbon in use
BREEAM Excellent
“Fabric First” strategy, including U values of 0.17 (Wall), 0.1 (Floor) and 0.12 (roof), and air tightness of 3m3/h.m2K
The predicted in use Energy Use Intensity is 92.09 kWhrs/m2/a.
100% waste diverted from landfill
100% timber responsibly sourced
71 Tonnes of carbon Saved
32 No of SMEs
27 beneficiaries
32 SME’s
9 jobs created
160 trainee weeks
Schools engagement: 81 students
25 volunteer hours
83% social value created