Tufnell Park Primary School

Tufnell Park Primary School

Islington, London


Project Details



Client

London Borough of Islington

Project Manager

Baily Garner

Architect

Haverstock

Contractor

Morgan Sindall

Value

£14.2 million

Contract Period

81 weeks

Procurement Type

 Design & Build

Form of Contract

JCT 2011 D&B

Size

3,252 sqm

Project Summary

A new 3FE modular primary school and associated landscaping with new MUGA (Multi-Use Games Area) to replace an existing 1.5FE school. The pupils from the existing school were housed in temporary classrooms while the old school was demolished to make way for the new school. Demolition took place in two phases with one building remaining operational throughout the build and was demolished once the school had decanted into the new building.

The new school is a modular construction by Eco Modular.



“Our project team is extremely experienced and adept at delivering high-quality education projects, often working in logistically challenging urban environments across London, and on live sites. We will bring this knowledge to bear on this development, doing our utmost to minimise disruption, engage both school users and the local community and manage the project to a high standard to ensure the journey to completion is a positive one for all stakeholders.”

Key Challenges

A substantial cut and fill was carried out on the site to level it out and a retaining wall was constructed on three sides.

The site was landlocked by neighbouring properties on three sides and the site was very tight, making access to it very challenging.  In the planning stages, permission for the retaining wall of a listed building was sought, but it wasn’t communicated properly how much working space was needed, which resulted in very limited space on each side of the building.

The modular build was proposed by Morgan Sindall as a solution to the tight site and limited access. Eco modular, who provided the building, also carried out the fit-out meaning there was only one contractor to manage for the whole of the building.

There was very little storage on the tight site, so “just in time” deliveries were scheduled to avoid having to store materials on site. All materials had to be craned in or hand-balled over a bridge and entered the building on the first floor.

Working in a live school environment with school children in very close proximity to the site and having to maintain services to the remaining school building.

A road closure was put in place for five weeks whilst the modular building was being delivered and craned into place. During this time, access still needed to be maintained for a special needs school opposite the site, so the road was only closed between the entrance and exit to the school.

The site team worked with the school to get the site set up initially. A good relationship with the school and local community was maintained throughout the course of the project, with regular site visits by the school’s headteacher and office manager as well as letter drops to neighbours.

The site team worked with the school to get the site set up initially. A good relationship with the school and local community was maintained throughout the course of the project, with regular site visits by the school’s headteacher and office manager as well as letter drops to neighbours.

Yeovil Innovation Centre

Yeovil Innovation Centre

Yeovil, Somerset

Project Details



Client
South Somerset District Council

Project Manager
NPS South West Limited

Architect
NPS South West Limited

Contractor
Midas Construction Ltd

Value
£1.5m

Contract Period
40 weeks

Procurement Type
Competitive tender – 2 stage

Form of Contract
NEC3 Option A

Size
1,044m²

Project summary

The Yeovil Innovation Centre is an evolving business community designed for small businesses and entrepreneurs that require high quality, low-cost and flexible work spaces with room for growth. Supported by funding from the Heart of the South West Local Enterprise Partnership, Midas constructed this two-storey extension for client South Somerset District Council to expand the capacity and update resources at this multi-office facility.Located on Lufton Trading Estate to the east of Yeovil’s town centre, the Innovation Centre provides reception and meeting areas for tenants and entrepreneurs looking for the flexibility of short term leases. This extension offers over 1,000m² office accommodation across two floors. The structure is strip footing foundations supporting a portal steel frame, with a block and beam ground floor and precast first floor and roof, and raised access flooring installed to both floors. It benefits from brise soleil solar shading, with internal plasterboard finish that allows for future reconfiguration of the ground floor to meet the changing needs of tenants. Midas’ works included a lift, shell and core finish to the first floor, a single ply roof and landscaping. The project received a score of 96% in the customer satisfaction survey at practical completion.



“The perfect location to nurture and grow your business.”

Community Engagement


Career Development

  • 8 Apprentices through the project

Key Challenges


Budget: Early in the programme Midas’ market intelligence and cost benchmarking works identified a challenge, with the client’s design requirements exceeding their budget allowance. Midas’ commercial team worked closely with the client’s designers and our supply chain partners to deliver £550,000 of value engineering – including changing the structural frame, amending the window and natural ventilation configuration, amending hollow clay pot and lintel solution, and rationalising roof and gutter design – to make the project viable whilst achieving the client’s vision.

Occupied building: Prior to commencement, Midas established a secure construction site perimeter to segregate live works from the Centre, and erected full perimeter Heras fencing with solid hoarding to the front elevation and post and rail fencing to pedestrian routes. Midas liaised with the client in advance of works and completed noisy works at agreed times. The team implemented acoustic protection measures including forming two baffle bunds from soils excavated on site. The team restricted and segregated noisy works, managed the movement of plant, and situated cement mixers on the opposite side of the site from neighbours. The team held regular consultation meetings to update neighbours on the project; allowing one to one discussions and providing advance notice of noisy works to Centre staff. The team monitored noise, dust and vibration levels through the works and across the site. Contractors completed cutting works in designated areas and made sparing use of damping down to manage dust whilst restricting the site’s water use.

Live services: The project included demolition works to form a link opening to the existing structure, and service and utilities connections between the original building and the extension. Midas engaged early with the Centre’s management team and planned works in consultation with them. Thanks to the good relations with the client, the site team developed a mutually agreed programme. This ensured Midas could complete demolition, connection and security works during daylight hours, allowing time to address any potential issues. Midas installed a lockable partition early in the programme to segregate works and mitigate disturbance from noise or dust. The team then installed temporary works prior to commencing demolition to support the structural integrity of the façade whilst forming the structural opening. Midas brought new services to the edge of the extension and existing services to the connection point in the original building, before completing service connections overnight. This simplified the connection process, ensured services were not in use during works and prevented disturbance of the Centre staff.

Project Takeaways