Exeter
The main challenges relating to this project were optimising the design to meet budget and making sure the design of the custody cells were Ministry of Justice compliant.
Early appointment formed an ‘integrated team’ newly formed with common agreed objectives were able to de-risk prior to any works commencing on site. This aided and protected final account predictability which contributed to completing on time and on budget.
Built to Ministry of Justice standards using the Yellow book design guide providing first-class accommodation for solicitors and partners has been incorporated in the design, including interview rooms and medical suites. The custody centre will use modern technology to monitor the health of vulnerable detainees and offers a virtual courts system. The linked-hub buildings provide modern office and meeting space for all operational police functions.
Completed on time and on budget. Willmott Dixon worked collaboratively with their Works Partner of the Year, Stephenson Group, to reduce the in-situ concrete frame programme by 12 weeks Exeter Police Station met all the requirements for Time, Cost and Quality achievements: defect free, on budget and handed over on time after being completed two weeks early. The project used 67% Mandated Suppliers and 82% Cat A suppliers, proving that building closer relationships builds trust and improves quality and service BREEAM Excellent certification accredited to design stage and is in UK’s top 10% sustainable buildings.
99% of regular payments and payment periods did not exceed 30 days
The facility uses 22% less energy than a traditional building of the same size, generates 68kwh of electricity a year from solar panels and carbon generated from its construction has been offset
Zero RIDDORs
Held 100 school children visits
1,600 students engaged at career events and workshops
2 ex-military personnel joined the construction industry
Zero defects at handover & aftercare
Client
Somerset County Council
Project Manager
Somerset County Council
Architect
NVB Architects
Contractor
Midas Construction Ltd
Value
£2.9m
Contract Period
47 weeks
Procurement Type
Competitive tender – 2 stage
Form of Contract
NEC3 Option A
Size
830m²
Apprentices
6
Tor School is a Pupil Referral Unit (PRU) in Glastonbury, one of the first fully integrated PRUs in the UK, which brings together three streams of Somerset County Council’s educational facilities. The school offers alternative educational provision for vulnerable young people who struggle in a mainstream school environment and provides facilities for Key Stages 2, 3 and 4. The PRU includes a Learning Enhancement Centre with facilities for outreach staff. Designed with the needs of the young people in mind, the building’s layout enables direct access from each classroom to dedicated external spaces. The different year groups share specialist spaces, including a breakout room with low-level lighting.
Midas constructed this single-storey, 12 classroom educational building on a design and build contract. This well-insulated building features blockwork render on all elevations with a truss timber roof and robust internal fittings designed to accommodate the specialist needs of the pupils. Midas completed groundworks including drainage and service connections, with internal works including first fix M&E, dry lining, plastering and decorations.
The client scored the project 100% in the customer satisfaction survey at practical completion and the site received a CCS Bronze 2018 National Site Award.
Community Engagement
Career Opportunities
Key Challenges
The client had a restricted budget with which to meet their project requirements
This constrained site contained a party wall and was bounded by commercial and residential properties, including a live ambulance station to the south and an adjacent Learning Difficulties Day Centre that remained open throughout the project.
The site contained hazardous underground and overhead live services including a high voltage (HV) cable that served half of Glastonbury. The project also included creation of a substation requiring rerouting of existing services and removal of redundant services.
Project Takeaways
Our Successes
Our Learnings
Added Value
KPI’s & Statistics
| Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
| Cost | £2,949,492 | £2,901,181 | -£48,311 (-0.3%) |
| Time | 34 weeks | 38 weeks | 4 weeks (11.8%) |
KPI Graphs
Apprentices 6
Graduates 1
Average AIR 0
Average CCS score 40.5
Waste diverted from landfill 92.1%
Cost/m2 £3,502m²
Cost/m2 excl abnormals £2,347m²
Client
South Somerset District Council
Project Manager
NPS South West Limited
Architect
NPS South West Limited
Contractor
Midas Construction Ltd
Value
£1.5m
Contract Period
40 weeks
Procurement Type
Competitive tender – 2 stage
Form of Contract
NEC3 Option A
Size
1,044m²
The Yeovil Innovation Centre is an evolving business community designed for small businesses and entrepreneurs that require high quality, low-cost and flexible work spaces with room for growth. Supported by funding from the Heart of the South West Local Enterprise Partnership, Midas constructed this two-storey extension for client South Somerset District Council to expand the capacity and update resources at this multi-office facility.Located on Lufton Trading Estate to the east of Yeovil’s town centre, the Innovation Centre provides reception and meeting areas for tenants and entrepreneurs looking for the flexibility of short term leases. This extension offers over 1,000m² office accommodation across two floors. The structure is strip footing foundations supporting a portal steel frame, with a block and beam ground floor and precast first floor and roof, and raised access flooring installed to both floors. It benefits from brise soleil solar shading, with internal plasterboard finish that allows for future reconfiguration of the ground floor to meet the changing needs of tenants. Midas’ works included a lift, shell and core finish to the first floor, a single ply roof and landscaping. The project received a score of 96% in the customer satisfaction survey at practical completion.
Career Development
Meeting the client’s design expectations within their budget
Budget: Early in the programme Midas’ market intelligence and cost benchmarking works identified a challenge, with the client’s design requirements exceeding their budget allowance. Midas’ commercial team worked closely with the client’s designers and our supply chain partners to deliver £550,000 of value engineering – including changing the structural frame, amending the window and natural ventilation configuration, amending hollow clay pot and lintel solution, and rationalising roof and gutter design – to make the project viable whilst achieving the client’s vision.
The Innovation Centre remained open and occupied throughout the works
Occupied building: Prior to commencement, Midas established a secure construction site perimeter to segregate live works from the Centre, and erected full perimeter Heras fencing with solid hoarding to the front elevation and post and rail fencing to pedestrian routes. Midas liaised with the client in advance of works and completed noisy works at agreed times. The team implemented acoustic protection measures including forming two baffle bunds from soils excavated on site. The team restricted and segregated noisy works, managed the movement of plant, and situated cement mixers on the opposite side of the site from neighbours. The team held regular consultation meetings to update neighbours on the project; allowing one to one discussions and providing advance notice of noisy works to Centre staff. The team monitored noise, dust and vibration levels through the works and across the site. Contractors completed cutting works in designated areas and made sparing use of damping down to manage dust whilst restricting the site’s water use.
The project involved connection of the extension to an operational building with live services
Live services: The project included demolition works to form a link opening to the existing structure, and service and utilities connections between the original building and the extension. Midas engaged early with the Centre’s management team and planned works in consultation with them. Thanks to the good relations with the client, the site team developed a mutually agreed programme. This ensured Midas could complete demolition, connection and security works during daylight hours, allowing time to address any potential issues. Midas installed a lockable partition early in the programme to segregate works and mitigate disturbance from noise or dust. The team then installed temporary works prior to commencing demolition to support the structural integrity of the façade whilst forming the structural opening. Midas brought new services to the edge of the extension and existing services to the connection point in the original building, before completing service connections overnight. This simplified the connection process, ensured services were not in use during works and prevented disturbance of the Centre staff.
Project Takeaways
KPI’s & Statistics
| Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
| Cost | £2,117,646 | £1,474,292 | -£545,854 (-30.4%) |
| Time | 42 weeks | 36 weeks | -6 weeks (-14.3%) |
Apprentices: 8
Average AIR: 0
Average CCS score: 41
Waste diverted from landfill: 99.2%
Cost/m2: £1,574m²
Cost/m2: excl abnormals £1,453m²
Cost/m2: Industry average £ m
Client
Devon County Council
Project Manager
NPS South West Limited
Architect
NPS South West Limited
Contractor
Midas Construction Ltd
Value £2.4m
Contract Period
37 weeks
Procurement Type
Competitive tender – 2 stage
Form of Contract
NEC3 Option A
Size 890m²
Apprentices
3
Situated in rural village surroundings, Loddiswell Primary School provides a welcoming and inclusive learning environment. The school is a 150-place, one form-entry single storey building with capacity to expand as the school grows. The school provides four classrooms, complete with interactive whiteboards and modern ICT equipment, a library, school hall and extensive outside space including a multi-use games area and playgrounds.
The building is timber frame with Structural Insulated Panels with a sectional roof, supported by glulam beams. The finished building features a 14kw PV array, larch weatherboarding and rubble stone walling, with an access road and car parking.Externally, Midas completed landscaping works and created a swale planted with wetland wildflowers as part of the Sustainable Urban Drainage Strategy, to help manage drainage, prevent flooding or run off, increase biodiversity and provide a source of natural interest for the pupils.The project scored 88% in the customer satisfaction survey at practical completion and received a CCS 2019 Bronze National Site Award.
Community Engagement
Career Opportunities
Key Challenges
The village of Loddiswell is off the gas grid, meaning the building could not benefit from low carbon gas grids and hydrogen solutions, and had no direct access to the cheapest heating options
To address the power supply Midas installed air-source heat pumps, with a 14kw PV array on the roof. The building includes wind-catchers to increase natural ventilation, designed through the Building Physics strategy to meet requirements for natural ventilation, solar shading and natural daylight.
The building needed to be made watertight as early in the programme as possible, to ensure the client-design timber frame retained its integrity
Midas implemented Structural Insulated Panel (SIPS) construction. This off site construction method is then fitted at the premises, enabling the team to make the building watertight sooner and resulting in a positive impact on the programme whilst also reducing waste, noise, dust and air pollution on site.
The site was in proximity to new houses, with a large population of children, with access only available via narrow roads through the existing housing estate
To manage the constrained access Midas restricted delivery vehicle size and scheduled deliveries to avoid rush hour and early mornings, directing site traffic to circumvent the village, and closely managed vehicle movements and timing to avoid disruption. The team reduced site movements by completing a cut and fill exercise, retaining 1,100m³ of excavated materials for the sports pitch and landscaping. The site team monitored the cleanliness of the access road, preempting the need for a road sweeper where necessary, and formed a tarmac car park within the site at the start of the project. Contractors used on-site parking to keep the residential roads clear and the vehicle controller monitored contractor parking to mitigate disturbance to the neighbours.
Project Takeaways
Our Success
Our Learnings
Value Added
KPI’s & Statistics
| Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
| Cost | £2,238,653 | £2,420,067 | -£40,300 (8.1%) |
| Time | 37 weeks | 37 weeks | 0 weeks |
KPI Graphs
Apprentices 3
Average AIR 0
Average CCS score 41
Waste diverted from landfill 41%
Cost/m2 £2,793m²
Cost/m2 excl abnormals £1,948m²
Cost/m2 Industry average £ m
Contact: Email:
A new-build 2FE school to provide a permanent new home for Ashmole Primary School. The school created 420 places for pupils aged four to 11 and provides teaching space for KS1 and KS2 along with offices, a sports hall, a community room and a canteen.
The school was built on a land-filled site with debris built up from previous excavations in the local area. The ground was found to contain asbestos and obstructions. The risk was quantified and a management strategy was put in place to remove the asbestos and obstructions from the site. This put significant pressure on the project programme.
The use of SIPs achieved a 10 week programme saving during the pre-construction phase and a five week programme saving during the construction phase of the project. This has led to SIPs being used on subsequent SCF and Morgan Sindall projects. The frame, including the roof, floor and walls, was installed in 13 weeks, which is a significant saving compared to traditional construction methods.
The use of SIPs achieved a 10 week programme saving during the pre-construction phase and a five week programme saving during the construction phase of the project. This has led to SIPs being used on subsequent SCF and Morgan Sindall projects. The frame, including the roof, floor and walls, was installed in 13 weeks, which is a significant saving compared to traditional construction methods.
100% payment within 30 days terms
98% waste diverted from landfill
100% timber responsibly sourced
Zero RIDDORs
CCS Score 39/45
7 work experience placements
94 apprenticeship weeks
£5k charitable donations
23 SMEs
Soft landings for handover
Dedicated Morgan Sindall point of contact
On-line portal for notifying any defects with 3 priority categories for response times
Somerset
Project Team
Project Manager
Aecom
Architect
AWW
Civil Engineer
Services Design Solution
A challenging site that had to battle flooding after a string of winter storms, the team involved have overcome numerous obstacles to deliver the school successfully to Somerset County Council.
The team had to undertake a major value engineering process, which led to a substantial redesign to bring the project in to budget, as well as building on a site with significant drainage issues.
The team designed a bund to provide acoustic protection for the school from the neighbouring motorway (M5), all while maintaining strong and collaborative working relationships between all parties.
However, Willmott Dixon are experts in navigating complex and challenging builds, finding solutions and making sure the works carried out meet expected requirements, so we were able to successfully deliver the project to a high standard.
Construction of a new 160 Place All-Through Special Educational Needs School (SEN) with administration facilities, hydrotherapy pool, sensory areas, carparking and other required facilitating and external works on greenfield land. Also include the construction of a spine road to facilitate access to the new school.
Willmott Dixon’s team of education specialists have constructed a state of the art, new two-storey SEN School in Bridgwater creating 160 school places, bringing pupils from two existing sites under one roof.
The new all-age school includes accessible classrooms, dining hall, sports hall, sensory and therapy rooms and a hydrotherapy pool. Outside a sensory garden, multi-use games area and adventure playground will provide lots of spaces to support the pupils’ physical and sensory needs.
20 work experience placements, 12 local jobs created, 19 construction careers information, advice and guidance events and 4396 hours spent dedicated to construction support and mentoring and training for both under 24s and over 24s.
Apprentices spending 585 training weeks on site, 30 construction qualifications gained, 21 hours in school doing H&S assemblies and site visits and 658 hours spent on other initiatives across the community (legacy projects, support with qualifications, community engagement)
99% prompt and fair payments
Zero Harm
97% waste diverted from landfill
Handover & Aftercare Contractor Promise
The school, previously known as Bordon Secondary School needed to meet the requirements of 900 school places and relocate from the eastern side of town to a more central location for children in both Bordon and neighbouring Whitehill. In 2015, Bordon and Whitehill were selected by the NHS’s Healthy New Towns scheme in hopes to develop a healthier environment, a strong sense of community and better care services within the local area. It was therefore imperative that the new school included facilities that would boost the children’s well-being.
Due to constricting budget restraints, it was crucial that Kier worked closely with Hampshire County Council’s team and maintained consistent communication throughout the project to help bring their dream school to life.
In order to create a modern and cohesive learning environment that satisfies the councils’ design, a proposal was approved for a collegiate style campus with four separate buildings connected by a central courtyard. This courtyard was intended to be a social and teaching hub, therefore encouraging a positive and well-connected community.
As part of the town’s Healthy Living Masterplan, extensive consultation with Sport England was carried out to devise a diverse range of facilities that could be used by the children all year round, therefore encouraging activity. The school was built in an area easily accessible for residents of Bordon and Whitehill, acting as a gateway to intertwine the communities.
To prioritise sustainability, the project adopted a low-energy, fabric-first strategy by making the most of the surrounding and historical Woolmer Forest. This resulted in the school possessing beautiful views of nature, boosting student and faculty morale. Additionally, a large expanse of PV panels on the southern teaching wing’s roof provides 10% of the school’s energy requirements.
The new Oakmoor School is a modern building with two-storey teaching wings spanning from the central courtyard, with school halls and sports halls at either end. The covered courtyard effectively reduces internal floor area and prevents the corridors from becoming overcrowded. Additionally, entrances to teaching wings are defined by staircases, once again minimising the volume of students within corridors. Passing through the courtyard promotes a healthier lifestyle as students and teachers will get a breath of fresh air while traveling easily between classes.
10% energy requirements from green energy
Zero RIDDORs
900 academy places
Handover & Aftercare Contractor Promise
Surrey County Council
Project Team
Architect
HGP Architects
Civil Engineer
Lyons O’Neill
As part of its global expansion, L3 commissioned a new £40m training and production facility on a site owned by Surrey County Council just a few miles from Gatwick Airport. The Nexus Training and Production Facility is critical for the UK’s aviation industry, as it will attract huge amounts of inward investment.
Engineering solutions were required due to the ground contamination and temporary works were needed on the existing retaining wall which made meeting the programme end date a challenge.
Willmott Dixon deployed a team of commercial building specialists to create the exact conditions needed for the fixed-based simulators as well as briefing rooms, classrooms, meeting rooms and a restaurant.
To meet the challenge of having a fully operational facility by summer 2019 an experienced management team were on hand to ensure any requests for changes were accommodated and fitted into a complex building schedule, making sure the 60,000 square foot facility came in on schedule.
The project involves creating two rather special buildings. The first is a global centre for excellence in airline training and houses eight flight simulators, each costing £12m. It also includes a number of fixed-based simulators plus briefing rooms, classrooms, meeting rooms and a restaurant.
The second building, opposite, is a similarly sized facility to manufacture 30 simulators a year and be a base for more than 300 employees.
99%
Waste diverted from landfill: 99%
Solar power was used to power temporary site accommodation
Zero Harm
Shortlisted for LABC awards 2020
Safety tours undertaken on for local school children
Handover and aftercare process followed
Project Team
Civil Engineer: Enginuiti
Architect: GT3
Project Manager: Gleeds
The new multi-level site was designed to transform the western side of Central Parade in New Addington, Croydon to provide community spaces, state of the art sports facilities and eight new family homes running parallel with the swimming pool, separated only by a considered designed structural wall.
Local businesses needed to maintain ‘business as usual’ so Willmott Dixon undertook and deployed a extremely detailed logics phased plan.
Overall, the project helped create over 75 jobs for local Croydon residents and was where Willmott Dixon held their first Building Lives Academy. This was an initiative to upskill young people in Croydon and provide them with valuable construction experience and gain qualifications within the industry.
The development has provided high quality leisure and community facilities which is a significant improvement on the previous facilities in the area.
The project won the RICS Social Impact 2020 award in recognition of the positive impact Building Lives has made on the community.
The team also helped facilitate the Christmas lights switch on in New Addington, not only donating funds to the charity but helped create their own Santa’s Grotto in the local community.
RICS Social Impact 2020 award won in recognition of the positive impact Building Lives has made on the community.
Helped facilitate the Christmas lights switch on in New Addington. The team not only donated funds to the charity but helped create their own Santa’s Grotto in the local community.
Regular payments and have payment periods not exceeding 30 days
99% of waste diverted
CCS Score 40
Handover & Aftercare Contractor Promise
Winchester, Hampshire
Awards
RIBA Awards 2022
Shortlisted
AJ Architecture Awards 2021
School category – Shortlisted
SPACES Awards 2021
Highly Commended
Civic Trust Awards 2022
Due to the 2,000 new homes being built as part of the Kings Barton development, there was a requirement for additional school places for the local area.
The project presented a challenging cost plan and was a very intricate, detailed and customer led design.
Unfortunately the project was put on hold for 12 months due to the housing developer not being as advanced as first anticipated, which meant the school placements weren’t needed as early as first though. With the project being pushed back a year, the planning had expired by the time the project was up and running again.
By aligning with the school’s high standards for environmental sustainability and quality, Willmott Dixon were able to create an environment where children will learn and flourish which is aspirational, inclusive and joyful.
The School’s design is based on sustainable, low energy, fabric-first principles achieving BREEAM Excellent rating with: wild flower green roof; PV’s, natural ventilation; surface water drainage managed on site with porous surfaces; bio-diverse landscape areas in courtyards; and rainwater recycling for flushing wc’s and landscape irrigation.
The design also incorporated future planning and infrastructure for a future 1FE expansion and a Teacher Development Facility.
The architecturally striking school, designed by Hampshire County Council’s award-winning Property Services Team, features a main hall, holistic music and drama studio, ‘discovery point’ library, staff room and workspace, administration offices, and classrooms offering a high quality learning environment.
The school is one of the most sustainable schools in Hampshire and it has created over 400 new school places.
A key part of the success of this project was the customer welcoming early supply chain input and engaging in collaborative working practices.
Regular payments and have payment periods not exceeding 30 days
99% of target waste diverted
Zero RIDDORs
CCS Score 41
4 Apprenticeships
140 Apprenticeship weeks
Handover & Aftercare Contractor Promise