Archives

Vandyke Upper School

  • Client

    Vandyke Upper School

  • Contractor

  • Value

    £10.6m

  • Completion Date

    September 2020

Project Background

Three storey modular teaching block boasts new science labs and general classrooms relocating 6th form study areas, associated external works and two separate refurbishment areas offering more general teaching space and expands the school’s kitchen and dining area.

The Project Manager, James Wood, went on to win Construction Manager of the Year and showcased the project at the awards ceremony.


The Challenge

A site-specific risk assessment should be in place prior to commencing work accounting for the local environment in which the work is undertaken.  This highlighted the area beneath the cycle shelter is heavily populated with services feeding the school including LV, HV and Gas. Upon completing several trial holes in accordance with the services plan it was discovered the services were laid shallow in the ground with some having less than 500mm cover.


The Solution

As a result of the incoming services feeding a live school, lowering the services was not a feasible option due to an extended shutdown requirement whilst the works were ongoing. Therefore, a propriety protection board was proposed as a solution to protect the services. The cable protection was specified to be 230mm wide concrete tiles with marker tape to be installed above as a standard requirement. In order to install the protection board, the services needed to be fully exposed and the safest and most efficient method of ground clearance was Vacuum Excavation.

The Results

A site-specific risk assessment was in place prior to commencing work accounting for the local environment in which the work is undertaken.

Vacuum excavation avoided using mechanical means to dig near live services as well as significantly reducing the risk of service strike.  It also meant there was no need to disrupt existing services feeding a live school thus the school was able to remain operational throughout the entire process avoiding any disruption.

Working with Eco Modular, the project team utilised off-site manufacturing to minimise disruption, create cost and time efficiencies and enhance the building’s sustainability performance.  This created a high Pre-Manufactured Value (PMV) which meant the design could be strictly coordinated and managed with regular inspections, including stringent quality checks, via weekly factory visits. The project also had a high percentage of PMV MEP installation including containment, first fix, plant room design and structured cabling architecture.

The high percentage of PMV on the building produced a better-quality product with less rework and remaining onsite activities were predictable, plannable and labour loading was simpler.

When Covid struck part-way through, it seemed the project may be in trouble but it was delivered on time and to budget in time for the school’s new academic year..

4


Apprentices

60%


SME Spend

£457,373k


Added Value

9/10


Client Satisfaction

Client Testimonials

We are thrilled at what has been achieved. It will make such a difference to the experience of the students and staff. So to everybody who has worked on the project and made this possible – from me, a heart-felt thank you.  The completion of the project in just 33 weeks was a remarkable achievement and thanks go to James who worked so closely with us and to our partners at Morgan Sindall.”

”Morgan Sindall Construction is passionate about delivering outstanding education facilities for the next generation and we’re pleased to have successfully completed works to expand and remodel Vandyke Upper School – creating a contemporary, future-fit learning environment which will benefit young people living locally and bolster the region’s educational offering.”

Contractor Performance | Commitments


Safe

Zero RIDDORs

CCS Score 44/45

Any site specific initiatives


Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times

Any site specific process/initiatives


Fair

100% payment within 30 days terms


Legacy

A celebratory capsule burying ceremony marked the completion milestone for the students, teachers and project team who worked steadily throughout the peak of the COVID-19 pandemic to ensure the project was safely delivered on time

18 SMEs, 19 beneficiaries, 4 jobs created and 112 trainee weeks

350 students Engaged, £600 donations to charity and 61 volunteer hours


Sustainability

82% of the building by volume was constructed using offsite manufacturing providing a programme saving of 16 weeks over traditional methods

Water tightness was achieved within 2 weeks of modules being delivered speeding up the construction programme

97% waste diverted from landfill

100% timber responsibly sourced

Bristol Operations Centre

  • Client

    Bristol City Council

  • Contractor

  • Value

    £7.28

  • Completion Date

    October 2017

–
Project Background

Following the successful completion of Phase 1, Phase 2 refurbishment of Bristol City Council’s headquarters at Temple Street, Bristol including the creation of a new Operations Centre on one floor which provides the central hub for all CCTV cameras in the city.  The room also acts as the control centre for major incidents and thus has a higher level of security than the rest of the building.


The Challenge

Provision of high security to one floor and fit out to the rest of the building whilst remaining a live operational building.

The Solution

Specialist and security systems included the installation of a video wall system which feature images from CCTV cameras that operators can play numerous images on enabling them to split the screen or zoom in.

The refurbishment also included CAT 6 data wiring, installation of a new generator, UPS and air conditioning.  The new switch panel was installed over 3 weekends as the building remained occupied.

Fit out to the first floor for the Department of Work and Pensions were phased to keep staff entrances live throughout with minimal disruption.  Deliveries were planned carefully.  Any drilling was not undertaken after 8.30am


The Results

Building handed over on time and within budget whilst remaining operational throughout the works.

4


Apprentices

92.3%


SME Spend

8/10


Client Satisfaction

Client Testimonials

It’s the way you set up your sites, down to bags and PPE.  It’s really impressive.  People always talk about it.  You stand out because of your site set up.

Contractor Performance | Commitments


Fair

100% payment within 30 days terms


Sustainability

100% timber responsibly sourced


Safe

Zero RIDDORs


Legacy

23 No of SMEs

22 Beneficiaries

2 Work experience placements and 16 jobs created

3 curriculum support activities


Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times

East Anton Primary School

Andover, Hampshire

  • Client

    Hampshire County Council

  • Contractor

  • Value

    £13m

  • Completion Date

    October 2018


The Challenge

To minimise energy consumption and maximise occupant comfort, our team focused on the careful design of the building form and selection of materials. In particular, the layout of the proposed building features south facing classrooms with north facing clerestory glazing. This arrangement offers good opportunities for providing generous natural daylight with natural cross ventilation and effective shading from excessive solar gain.

The Solution

Willmott Dixon’s team of education experts have created a new 420 place primary school in Andover. The school provides places for students aged from 4-11 years old and is likely to expand in the future with elements already in place to accommodate this.

This arrangement offers good opportunities for providing generous natural daylight with natural cross ventilation and effective shading from excessive solar gain. The school is highly sustainable with photovoltaics on the roof which provide 10% of the building’s energy use.


The Results

The Primary school provided 420 places for students aged from 4-11 years old and is likely to expand in the future with elements already in place to accommodate this. Set within the East Anton Major Development Area (MDA) the school is being built alongside 2,850 new homes with developer Taylor Wimpey.

1


Apprentices

91.25%


SME Spend

20.5%


Added Value

10


Client Satisfaction

Client Testimonials

“We are delighted to have created this new sustainable school in Andover, creating much needed school places for the local community.”

Contractor Performance | Commitments


Fair

100% of payments were made promptly and within 30 days


Sustainability

98% diverted from landfill


Legacy

Created 9 new jobs through the project
Career guidance events
Provided over 186 weeks of training onsite


Safe

Zero harm


Aftercare

SCF handover and aftercare process carried out

Police Investigation Centre, Portsmouth

  • Client

    Police and Crime Commissioner for Hampshire and the Isle of Wight

  • Contractor

  • Value

    £23m

  • Completion Date

    April 2019

The Challenge

Building on the success of the Basingstoke PIC [link], the challenge was set by OPCC to develop an identical facility for the Portsmouth site but deliver it quicker and cheaper. Whilst this excluded site abnormals, the focus was on seeking efficiencies in the design by adopting an off-site manufacture / kit of parts approach.


The Solution

Using the BIM model to carefully interrogate the design the focus was on which elements of the design could be premanufactured and delivered to site, taking the benefits of quicker delivery. The building cores were one focus area, rather than a concrete cast in-situ approach, these were revised to a twin-wall solution. The MEP installation was another focus area, with plant modules being manufactured off-site alongside horizontal services modules for distribution across each floor.

—

The Results

The programme benefits delivered through the adoption of premanufacture achieved an approximate 3 week saving and consequential cost saving. The wider benefits included quality checked products, reduced site labour and associated health and safety impacts such as periods spent working at height together with a reduced waste.

6


Apprentices

£19.3m


SME Spend

£1.4m


Added Value

10


Client Satisfaction

Client Testimonials

“This is such a huge deal operationally, and for the hundreds of officers and staff who are really excited about being here. I know that it will make a vast difference to them, to the effectiveness of what they do, and to their productivity and how they feel.”  

Contractor Performance | Commitments


Fair

Client and sub-contractor payments made within 28 days of certification date.


Sustainability

The installation of PV’s supported the buildings achievement of BREEAM.


Safe

Zero RIDDORs


Legacy

Programme of engagement with UTC Portsmouth to support curriculum activities.


Aftercare

Mace supported the early occupation and operation of the building through maintaining our MEP and Construction Managers on site for the first 2 months to ensure smooth operation and running of the building.

Barnet Waste Transfer

London

  • Client

    London Borough of Barnet

  • Contractor

    Willmott Dixon logo

  • Value

    £11.9m

  • Completion Date

    July 2017

Architects: Capita

Electrical: Capita

MEP: Capita


Project Background

The project was a design and build development of Oakleigh Road South Vehicle Depot to create a Barnet Council vehicle depot and a base for their fleet of 46 household recyclable waste collection vehicles.

The Challenge

There were several challenges faced throughout this project. There was restricted access on a long and narrow site which caused difficulties when trying to overcome other challenges such as dealing with the below ground water, removing underground drainage structures and the buried hazardous waste.

The Solution

To overcome the narrow site, the Willmott Dixon team worked in a ‘patchwork’ fashion, sectioning off the works and moving operations around to keep the access road fully open throughout the build.

Willmott Dixon found existing sewers and then got permission from Thames Water to use them instead for the below ground water. They found a solution using a land drain pump to drain the ground water which was causing surface water.


The Results

Now built, the depot will allow Barnet Council to operate its vehicle maintenance and recycling collection fleet from single coordinated site, ensuring the most efficient service for residents across the borough. The construction also consisted of a tractor barn and car parking, together with associated ancillary facilities, a recycling waste transfer building and bulking facility, a two storey office and welfare building.

2


Apprentices

88%


SME Spend

£1.2m


Added Value

9/10


Client Satisfaction

Contractor Performance | Commitments


Sustainability

Early contractor engagement realised that by raising finished floor levels by introducing an engineered ground geotextile design produced a saving of c£720k, helping significantly reduce excavated materials resulting in programme saving £110k.

Added surveys resulting in reduced risk on hazardous waste, saving £205k


Fair

Regular payments and payment periods did not exceed 30 days


Safe

Zero RIDDORs


Legacy

2 starter apprentices who went on to gain full time graduate employment


Aftercare

SCF handover and aftercare promised carried out

Middlemoor Criminal Justice Centre

Exeter

  • Client

    Devon & Cornwall Police

  • Contractor

  • Value

    £25.2m

  • Completion Date

    February 2020

The Challenge

The main challenges relating to this project were optimising the design to meet budget and making sure the design of the custody cells were Ministry of Justice compliant.


The Solution

Early appointment formed an ‘integrated team’ newly formed with common agreed objectives were able to de-risk prior to any works commencing on site. This aided and protected final account predictability which contributed to completing on time and on budget.

Built to Ministry of Justice standards using the Yellow book design guide providing first-class accommodation for solicitors and partners has been incorporated in the design, including interview rooms and medical suites. The custody centre will use modern technology to monitor the health of vulnerable detainees and offers a virtual courts system. The linked-hub buildings provide modern office and meeting space for all operational police functions.


The Results

Completed on time and on budget. Willmott Dixon worked collaboratively with their Works Partner of the Year, Stephenson Group, to reduce the in-situ concrete frame programme by 12 weeks Exeter Police Station met all the requirements for Time, Cost and Quality achievements: defect free, on budget and handed over on time after being completed two weeks early. The project used 67% Mandated Suppliers and 82% Cat A suppliers, proving that building closer relationships builds trust and improves quality and service BREEAM Excellent certification accredited to design stage and is in UK’s top 10% sustainable buildings.

exterior shot of middlemoor

6


Apprentices and ex-defenders

78%


SME Spend

£6.3m


Added Value

10


Client Satisfaction

Client Testimonials

“In a crisis our police force has demonstrated an ability to be extraordinarily agile, and the early opening of the station is an example of that”

“There has been a huge amount of work going on behind the scenes to make this happen – mostly around IT systems, and I’d like to thank those who have put in a Herculean effort to make this happen as one part of our response to this serious public health crisis.”

Contractor Performance | Commitments

Fair

99% of regular payments and payment periods did not exceed 30 days

Sustainability

The facility uses 22% less energy than a traditional building of the same size, generates 68kwh of electricity a year from solar panels and carbon generated from its construction has been offset

Safe

Zero RIDDORs

Legacy

Held 100 school children visits

1,600 students engaged at career events and workshops

2 ex-military personnel joined the construction industry

Aftercare

Zero defects at handover & aftercare

Ashmole Primary School

Ashmole Primary School

  • Client

    ESFA

  • Contractor

  • Value

    £7.5m

  • Completion Date

    November 2018

Project Background

A new-build 2FE school to provide a permanent new home for Ashmole Primary School. The school  created 420 places for pupils aged four to 11 and provides teaching space for KS1 and KS2 along with offices, a sports hall, a community room and a canteen.



The Challenge

The school was built on a land-filled site with debris built up from previous excavations in the local area. The ground was found to contain asbestos and obstructions. The risk was quantified and a management strategy was put in place to remove the asbestos and obstructions from the site. This put significant pressure on the project programme.

The Solution

The use of SIPs achieved a 10 week programme saving during the pre-construction phase and a five week programme saving during the construction phase of the project. This has led to SIPs being used on subsequent SCF and Morgan Sindall projects. The frame, including the roof, floor and walls, was installed in 13 weeks, which is a significant saving compared to traditional construction methods.


The Results

The use of SIPs achieved a 10 week programme saving during the pre-construction phase and a five week programme saving during the construction phase of the project. This has led to SIPs being used on subsequent SCF and Morgan Sindall projects. The frame, including the roof, floor and walls, was installed in 13 weeks, which is a significant saving compared to traditional construction methods.

91.5%


SME Spend

£252k


Added Value

9/10


Client Satisfaction

Client Testimonials

“The on-site management team’s highly professional and collaborative approach enabled the new building to be completed on a demanding programme to a high standard of quality ready for the school to occupy”

Contractor Performance | Commitments


Fair

100% payment within 30 days terms


Sustainability

98% waste diverted from landfill

100% timber responsibly sourced


Safe

Zero RIDDORs

CCS Score 39/45


Legacy

7 work experience placements

94 apprenticeship weeks

£5k charitable donations

23 SMEs


Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times

Polden Bower School

Polden Bower School

Somerset

  • Client

    Somerset County Council

  • Contractor

  • Value

    £16m

  • Completion Date

    May 2021

Project Manager
Aecom

Architect
AWW

Civil Engineer
Services Design Solution

The Challenge

A challenging site that had to battle flooding after a string of winter storms, the team involved have overcome numerous obstacles to deliver the school successfully to Somerset County Council.

The team had to undertake a major value engineering process, which led to a substantial redesign to bring the project in to budget, as well as building on a site with significant drainage issues.

The team designed a bund to provide acoustic protection for the school from the neighbouring motorway (M5), all while maintaining strong and collaborative working relationships between all parties.

However, Willmott Dixon are experts in navigating complex and challenging builds, finding solutions and making sure the works carried out meet expected requirements, so we were able to successfully deliver the project to a high standard.

The Solution

Construction of a new 160 Place All-Through Special Educational Needs School (SEN) with administration facilities, hydrotherapy pool, sensory areas, carparking and other required facilitating and external works on greenfield land. Also include the construction of a spine road to facilitate access to the new school.


The Results

Willmott Dixon’s team of education specialists have constructed a state of the art, new two-storey SEN School in Bridgwater creating 160 school places, bringing pupils from two existing sites under one roof.

The new all-age school includes accessible classrooms, dining hall, sports hall, sensory and therapy rooms and a hydrotherapy pool. Outside a sensory garden, multi-use games area and adventure playground will provide lots of spaces to support the pupils’ physical and sensory needs.

5


Apprentices

95.7% were local


SME Spend

£3.8m


Added Value

9/10


Client Satisfaction

Client Testimonials

“ These are the next steps in ensuring we have the right provision in the right places for Somerset’s children.  We always do all we can to support children with SEND to attend mainstream school where this is appropriate and also make sure that those with the highest level of need have the right provision. These projects will ensure that children with all levels of need can be educated close to home in their own communities.”

Contractor Performance | Commitments


Legacy

20 work experience placements, 12 local jobs created, 19 construction careers information, advice and guidance events and 4396 hours spent dedicated to construction support and  mentoring and training for both under 24s and over 24s.

Apprentices spending 585 training weeks on site, 30 construction qualifications gained, 21 hours in school doing H&S assemblies and site visits and 658 hours spent on other initiatives across the community (legacy projects, support with qualifications, community engagement)


Fair

99% prompt and fair payments


Safe

Zero Harm


Sustainability

97% waste diverted from landfill


Aftercare

Handover & Aftercare Contractor Promise

Front view of Mill Chase Academy

Oakmoor School Secondary School Expansion

Oakmoor Secondary School Expansion

  • Client

    Hampshire County Council

  • Contractor

  • Value

    £23m

  • Completion Date

    November 2019

The Challenge

The school, previously known as Bordon Secondary School needed to meet the requirements of 900 school places and relocate from the eastern side of town to a more central location for children in both Bordon and neighbouring Whitehill. In 2015, Bordon and Whitehill were selected by the NHS’s Healthy New Towns scheme in hopes to develop a healthier environment, a strong sense of community and better care services within the local area. It was therefore imperative that the new school included facilities that would boost the children’s well-being.

Due to constricting budget restraints, it was crucial that Kier worked closely with Hampshire County Council’s team and maintained consistent communication throughout the project to help bring their dream school to life.

The Solution

In order to create a modern and cohesive learning environment that satisfies the councils’ design, a proposal was approved for a collegiate style campus with four separate buildings connected by a central courtyard. This courtyard was intended to be a social and teaching hub, therefore encouraging a positive and well-connected community.

As part of the town’s Healthy Living Masterplan, extensive consultation with Sport England was carried out to devise a diverse range of facilities that could be used by the children all year round, therefore encouraging activity. The school was built in an area easily accessible for residents of Bordon and Whitehill, acting as a gateway to intertwine the communities.

To prioritise sustainability, the project adopted a low-energy, fabric-first strategy by making the most of the surrounding and historical Woolmer Forest. This resulted in the school possessing beautiful views of nature, boosting student and faculty morale. Additionally, a large expanse of PV panels on the southern teaching wing’s roof provides 10% of the school’s energy requirements.

The Results

The new Oakmoor School is a modern building with two-storey teaching wings spanning from the central courtyard, with school halls and sports halls at either end. The covered courtyard effectively reduces internal floor area and prevents the corridors from becoming overcrowded. Additionally, entrances to teaching wings are defined by staircases, once again minimising the volume of students within corridors. Passing through the courtyard promotes a healthier lifestyle as students and teachers will get a breath of fresh air while traveling easily between classes.


86.4%


SME Spend

£362,000


Added Value

8.6


Client Satisfaction

Contractor Performance | Commitments


Fair


Sustainability

10% energy requirements from green energy


Safe

Zero RIDDORs


Legacy

900 academy places


Aftercare

Handover & Aftercare Contractor Promise

Nexus

Nexus Training and Production

Nexus Training and Production

Surrey County Council

  • Client

    Surrey County Council

  • Contractor

  • Value

    £40m

  • Completion Date

    February 2019

Architect
HGP Architects

Civil Engineer
Lyons O’Neill

The Challenge

As part of its global expansion, L3 commissioned a new £40m training and production facility on a site owned by Surrey County Council just a few miles from Gatwick Airport. The Nexus Training and Production Facility is critical for the UK’s aviation industry, as it will attract huge amounts of inward investment.

Engineering solutions were required due to the ground contamination and temporary works were needed on the existing retaining wall which made meeting the programme end date a challenge.

The Solution

Willmott Dixon deployed a team of commercial building specialists to create the exact conditions needed for the fixed-based simulators as well as briefing rooms, classrooms, meeting rooms and a restaurant.

To meet the challenge of having a fully operational facility by summer 2019 an experienced management team were on hand to ensure any requests for changes were accommodated and fitted into a complex building schedule, making sure the 60,000 square foot facility came in on schedule.


The Results

The project involves creating two rather special buildings. The first is a global centre for excellence in airline training and houses eight flight simulators, each costing £12m. It also includes a number of fixed-based simulators plus briefing rooms, classrooms, meeting rooms and a restaurant.

The second building, opposite, is a similarly sized facility to manufacture 30 simulators a year and be a base for more than 300 employees.


6


Apprentices

96.8


SME Spend

£5.6m


Added Value

9/10


Client Satisfaction

Client Testimonials

“We’re proud of our legacy  in Sussex with completing Nexus on time and on budget helping L3 realise its growth in the Gatwick area, as well as provide opportunities to help attract and retain the next generation of workers in the county.”

Contractor Performance | Commitments


Fair

99%


Sustainability

Waste diverted from landfill: 99%

Solar power was used to power temporary site accommodation


Safe

Zero Harm


Legacy

Shortlisted for LABC awards 2020

Safety tours undertaken on for local school children


Aftercare

Handover and aftercare process followed