• SCF Client Portal
Logo
  • Support
    • Working with SCF
    • Meet the team
  • Our Frameworks
    • SCF Construct
      • Partnering Contractors
    • SCF Intermediate
      • Intermediate contractors
    • SCF Consult
      • Consultant Partners
  • Our Projects
    • Case Studies
    • Video Testimonials
    • SCF Contractor Apprenticeships
  • Resources
    • Market Intelligence
    • Sustainability
    • Contractor and Suppliers Support
    • SCF Documents
    • SCF Passport Training
    • Building Safety Act 2022
  • SCF6 Procurement
  • News
  • Contact
  • Click to open the search input field Click to open the search input field Search
  • Menu Menu

Archives

You are here: Home1 / Matthew Elliott Contact details2 / Case Studies

Dartmouth Street London No 21

September 15, 2022/in Civic and Community Refurbishment/by Andrew Real

Dartmouth Street London No 21

  • Client

    Confidential Government Client

  • Contractor

  • Value

    £21m

  • Completion Date

    April 2022

Project details

Form of Contract: NEC3 Engineering and Construction Contract April 2013

Procurement Type: 2 Stage

Contract Period:  97 weeks

Size: 55,000 sqft

The project comprised of the refurbishment and upgrade of the client’s estate under their ‘Restoration and Renewal Programme’. The project endeavored to deliver maximum flexibility and usability for a design life of 15 years, achieving BREEAM Excellent.

The project included CAT B fit out of offices, a new reception, new meeting rooms and collaboration spaces. The scope of works also included structural alterations, window replacements and external works and security enhancements of 55,000 sq ft over 9 floors including roof and terraces in a 1920’s building.

The Challenge

Multiple stakeholder engagement
The scope included the decant of large numbers of staff to allow 750 new staff to occupy their new space.

Engaging with government recommended contractors
ISG had to liaise with government recommended subcontractors with their own works packages within the building.

Delivering in a Global Pandemic
The PCSA and part of the construction period spanned the unprecedented Covid-19 Global Pandemic.

Challenging logistics
The project was located in central London, with the building located on a busy road. The building was occupied for the duration of the works.

Base build fit out
It became clear the CAT A wasn’t fit for purpose; extensive reparations were required before the CAT B could begin.

The Solution

Multiple stakeholder engagement
ISG engaged early in the preconstruction phase with incoming government departments to build a move-in calendar for each department. They also held coordination workshops with the client’s in-house design team, data teams, security and maintenance teams, and catering teams.

Engaging with government recommended contractors
ISG engaged at tender stage with government recommended subcontractors and incorporated their specialist programmes into their master programme to calibrate and synchronise their works.

Delivering in a Global Pandemic
ISG’s industry leading Covid-19 safety measures ensured minimal disruption to the project despite lockdowns and social distancing measures, in the challenging conditions of an unprecedented global pandemic.

Challenging logistics
The logistics of the site was very tight. The scope included the removal and replacement of the lift motor room. ISG agreed the use of a full height hoist to the front elevation for movement of materials and operatives into the building. Neighbouring businesses and residents were kept informed of progress and the team received zero complaints of disruption.

Base build fit out
After notifying the client of the issues with the base build, ISG removed infrastructure back to risers and validated all CAT A base-build plant, effectively providing the client with a turnkey solution.

The Results

Early engagement with government subcontractors enabled the programme to progress efficiently and smoothly

The ISG and client team remained safe, proactive, focused and driven to achieve all key sign offs and milestones throughout the project lifecycle

The occupants of the space moved into their new offices on time, with support of the ISG team

Neighbouring business and residents were satisfied with the logistics approach, resulting in zero complaints

Effectively delivered a turn-key solution for the client

Contractor Performance | Commitments


Fair

100% payment within 30 days


Sustainability

Achieved BREEAM Excellent


Safe

Zero RIDDORs


Aftercare

Handover & Aftercare Contractor Promise


Legacy

ISG maintains ongoing community engagement with three organisations:

The Passage – refurbishment of their entrance / circulation / break out zones

One Westminster – welfare facilities refurbishment

St Mungo’s – PPE donations

SCF Framework Manager

Alex Nelhams

Email: alex.nelhams@hants.gov.uk

Phone: 07717 003869

Contractor Framework Manager

Matt Glass

Email: matt.glass@isgltd.com

Phone: 07929755500

https://southernconstructionframework.gov.uk/wp-content/uploads/2022/08/21-DS-external-image-scaled.jpg 1537 2048 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2022-09-15 11:22:092024-01-25 09:52:51Dartmouth Street London No 21

Victoria Street London 64

August 25, 2022/in Civic and Community Block, Business, Office/by Andrew Real

Victoria Street London 64

  • Client

    Confidential Client

  • Contractor

  • Value

    £17.3m

  • Completion Date

    May 2021

Project Information

Form of Contract: NEC3 Engineering and construction contract April 2013

Procurement type: Two Stage

Contract period:  57 weeks

Size: 9290m2

As part of their ‘Restoration and Renewal Programme’ the client needed to move lots of staff members from their existing accommodation.

The refurbishment of this new space was to allow over 1000 member their staff to relocate there. The existing building occupied Levels 11 and 20 with Levels 1 to 10 offered as high standard Cat A. This 10 floor Design and Build Cat B office fit out comprised primarily of a new office, collaboration and ancillary spaces on Levels 3 to 10 with catering and meeting areas situated on Levels 1 and 2.


The Challenge

Integrating client instructed variations
ISG integrated upwards of 100 client instructed variations into the project.

Working in occupation
Works were carried out whilst the upper floors were in occupation.

High level of security
There were secure areas on every floor with CTC clearance requirements which meant ISG had to meet stringent SR requirements.

Working in a global Pandemic
Works were carried out in the midst of the Covid-19 global pandemic.

Fast track programme
The construction programme ran to a duration of just 24 weeks

The Solution

Integrating client instructed variations
ISG collaborated early BDP which was essential to allow alternative compliant design options and opportunities with increased budget certainty. ISG hosted workshops with the client and project team to incorporate instructed changes without negatively impacting the programme.

Working in occupation
Early engagement with incoming government departments was key; ISG held coordination workshops with the client’s in-house design team, data teams, security and maintenance teams, and catering teams. The phased programme was determined by incoming client direct contractors, and included early access and handover of the IT server and hub comms rooms 2 weeks before handover. To mitigate disruption to the existing building users, Westminster City Council, ISG held regular meetings to ensure minimal impact caused by their presence. ISG controlled more than 200 operatives using labour histograms and short interval controls with floor by floor close out programmes as part of our soft landings phasing strategy.

High level of security
For information security and due to the secure nature of the client and works, ISG integrated two document controllers into the team to manage the handling of the three doc-hosting systems; Aconex downstream to our supply chain, Business Collaborator, the client’s doc-hosting system and Conject for the NEC Contract management. Level 7 was highly secure, so ISG engaged with CPNI standards to achieve SR3 levels. ISG implemented early action of CTC clearance to ensure workers were security compliant for delivery. The team engaged at tender stage with government recommended subcontractors and incorporated their specialist programmes into our master programme.

Working in a global Pandemic
ISG followed strict Covid-19 protocols, complying with CLC and SOP guidelines. We enacted safety measures on site such as temperature testing, and 2 metre social distancing ensure the safety of the team, client and stakeholders.

Fast track programme
Production of a tender event schedule alongside programme enabled critical path analysis covering design release, labour and plan resource requirements, material procurement and security screening.  This ensured timely procurement and us the opportunity to plan resources to meet the programme. Long lead items were prioritised, we held workshops with our supply chain and the professional team to agree these elements of the designs quicker allowing early orders to be placed to assure on time delivery. In the last 8 weeks of the programme, the team optimised outputs using evenings and weekends to complete on time.

The Results

– ISG’s flexibility ensured client instructed changes were made without delay to the programme

– Working in occupation we received zero complaints from building occupants caused by our presence

– ISG met the client’s stringent security measures, and ensured our supply chain did the same

– ISG’s industry leading Covid-19 strategy ensured the works were completed on time, in a safe manner

– Fast track programme was successfully delivered with stringent programme analysis and evening and weekend works


Client Testimonials

‘A challenging project at times especially given the red tape, delivered very well by a committed team’

Ian Jones Senior Project Leader for the Strategic Estates Team
Previous Previous Previous Next Next Next

Contractor Performance | Commitments


Fair

100% payment within 30-day terms


Sustainability

BREEAM ‘Excellent’


Safe

Zero Riddors

Safe delivery of works in a global pandemic

CCS Score: 40/50


Legacy

Created a new school kitchen for a school in the community


Aftercare

Handover & Aftercare Contractor Promise

SCF Framework Manager

James Wright

Email: james.wright@hants.gov.uk

Phone: 07761 330560

Contractor Framework Manager

Matt Glass

Email: matt.glass@isgltd.com

Phone: 07929755500

https://southernconstructionframework.gov.uk/wp-content/uploads/2022/08/64-VS-external.jpg 936 1137 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2022-08-25 14:11:592024-01-25 10:07:32Victoria Street London 64

Fareham Innovation Centre – Phase 2 Extension, HMS Daedalus

August 25, 2022/in Civic and Community, Innovations Industrial/by Gabby Stevens

Fareham Innovation Centre Phase 2 Extension

  • Client

    Fareham Borough Council

  • Contractor

  • Value

    £7m

  • Completion Date

    March 2018

Daedalus Enterprise Zone was designated as one of 11 initial enterprise zones around the country by the central Government. The Homes and Communities Agency (HCA) owned most of the land and ran a programme for the regeneration of Daedalus along with the Solent Local Enterprise Partnership (LEP) and Partnership for Urban South Hampshire (PUSH). Fareham Borough Council took ownership from the HCA that rest within the district of FBC.

In 2014/15 Fareham Borough Council constructed an Innovation Centre for new businesses, with Oxford Innovation assistance to provide business support services, enabling nurture and development. Due to the success of that building, a business case supported the construction of a Phase 2 extension.

The new extension consists of the construction of a two and three storey steel frame with associated external hard and soft landscaping, providing a range of office and workshop spaces for local businesses as well as additional space within the Enterprise Zone.

The Challenge

  1. Works had to be completed by end March 2018 to facilitate discounted business rates.
  2. Ensuring the running of the current centre was not affected and “business as usual” is maintained throughout the works.
  3. To match existing centre and not be seen as “an extension” with all spaces designed to be agile – flexible and adaptable.


The Solution

  1. A preconstruction and construction programme was developed with a completion date of 19 March 2018.
  2. Chaired collaborative planning, programming and risk sessions throughout the precon and construction periods with client, end users and Morgan Sindall team in attendance.
  3. Developed an open and regular communication process with Phase 1 business users ensuring we achieved the “business as usual” deliverable.

–

The Results

  1. Actual completion was achieved 2 weeks early on 26 February 2018.
  2. The existing centre remained open throughout the build without any disruptions to existing operations.
  3. Phase 2 now provides a seamless extension to the first block with composite panels and glazing to match the existing building.

9


Apprentices

£736,000


Added Value

9/10


Client Satisfaction

Client Testimonials

‘Fareham County Council enjoyed an excellent relationship with Morgan Sindall on this project, which was completed on budget and ahead of what was an already challenging programme. Thanks to Mike and his team for the tremendous effort put into the project and with minimal disruption to Phase 1’.

Colin Mitchell Fareham Borough Council

‘The overall performance of Morgan Sindall was excellent in terms of communication, organisation, site management and consideration of other site users’.

Paul Bannon Baqus (Client Project Manager)
Previous Previous Previous Next Next Next

Contractor Performance | Commitments


Fair

100% payment within 30 days terms


Sustainability

100% timber responsibly sourced


Safe

Zero RIDDORs


Legacy

18 beneficiaries


Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times

Any site specific process/initiatives

SCF Framework Manager

James Wright

Email: james.wright@hants.gov.yk

Phone: 07761 330560

Contractor Framework Manager

Alan Smedley

Email: alan.smedley@morgansindall.com

Phone: 07967 686066

https://southernconstructionframework.gov.uk/wp-content/uploads/2021/02/72V1124_M120-1500x430-1.jpg 430 1500 Gabby Stevens https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Gabby Stevens2022-08-25 11:11:162022-08-31 15:40:03Fareham Innovation Centre – Phase 2 Extension, HMS Daedalus

North Devon Enterprise Centre (Node) Expansion

August 19, 2022/in Civic and Community/by Andrew Real

North Devon Enterprise Centre (Node) Expansion

The second phase expansion will bring an extra 564sq metres of flexible office space to support the growth of the hub

  • Client

    Devon County Council

  • Contractor

  • Value

    £2,009,000

  • Completion Date

    March 2023


PROJECT ON SITE



Based upon successful delivery of the North Devon Enterprise Centre (Node) at One Enterprise Road in Barnstaple which was completed in 2021, ISG were selected to deliver the NODE Expansion project which started on site in June 2022.

Within the first year of operating, Node had already let 64% of its 37 offices after just eight months. The second phase expansion will bring an extra 564 sq. metres of flexible office space across the ground and first floor and additional parking provision to create an extra 48 carparking spaces.

Design and build of the RIBA Stage 4 onwards project involves both advance site-wide infrastructure works and the build-out of the Enterprise Centre and associated plot works.

Designed to look identical to the existing building, Devon County Council requested that ISG design and construct the extension in spirit of the BREEAM Excellent standard of the original building.

Whilst undertaking the original Node project, ISG held collaborative design workshops with the architect to gain an in-depth understanding of how the business park would develop. With the development of RIBA stage 3 design to provide a RIBA stage 4 solution for a future proofed development, ISG incorporated technical design features to allow easy expansion/extension of the Node building’s structure and infrastructure.

https://southernconstructionframework.gov.uk/wp-content/uploads/2022/08/NODE-1-scaled.jpg 1043 2048 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2022-08-19 11:05:172022-08-19 11:05:17North Devon Enterprise Centre (Node) Expansion

University of Chichester

August 11, 2022/in Education: Further / Higher University/by Andrew Real

University of Chichester

  • Client

    University of Chichester

  • Contractor

  • Value

    £21m

  • Completion Date

    August 2018

This new state-of-the-art Tech Park provides new engineering and digital creative technology facilities to support 500 new science, technology, engineering, and maths undergraduate and postgraduate student places per year. The facilities provide a TV production studio, a green room and a “create, design, implement and operate” (CDIO) engineering space. Also included are a machine shop, welding area and fabricating laboratory (fab lab). In addition, an Institute for Sustainable Enterprise, and a Centre for Digital Technology, located in a new signature building, and will enable the creation of a Research Centre for Sustainable Operations and Departments of Data Science and Advanced Engineering & Design.

Passivhaus design principals were applied resulting in running costs efficiencies. Sustainability was key and several added value benefits were achieved, for example by protecting and increasing biodiversity levels in the stream which runs separates the buildings from the carpark during the construction works and inclusion of a swale.

BREEAM Excellent was achieved with exemplar levels of Responsible Construction Practices six weeks post completion.

The Grand Opening was attended by the Duke and Duchess of Sussex.

—


The Challenge

As the site was in a flood zone 3, this required the design teams to collaborate with us and our supply chain partners to finalise the design and construction methodologies as early as possible. We collaborated with the novated design team to fully understand the flood risks and several modelling assessments were undertaken to ensure that design was right first time.

The Solution

Together, the teams engaged with the Environmental Agency early and designed both compliant temporary and permanent flood mitigation strategies, which included diverting the stream to enable the installation of a temporary bailey bridge over a storm ditch that traversed the site, giving way for plant and vehicle access during the enabling works. Whilst the enabling works were progressing, the teams concluded the permanent bridge design which featured concrete balustrade and culvert and tarmac. The bridge was designed to withstand the weight of HGVs and emergency vehicles.


—


The Results

The completed installation was in keeping with the design features important to the client, practical and in full agreement of the Environmental Agency.


26


Apprentices

£15m


SME Spend

£2.5m


Added Value

Excellent


BREEAM

Client Testimonials

“The Technology Park will help us to deliver our vision of making our region a place where businesses, large and small, can thrive, create jobs, and where people can access the very best education and training opportunities.”

Professor Longmore, Vice Chancellor University of Chichester
Previous Previous Previous Next Next Next

Contractor Performance | Commitments


Safe

Tower crane rescue courses were offered to subcontractors.


After Care

The site team remained on site 6 weeks post completion. Our Galliford Try Facilities Management team will be attendance for 3 years, 24 hours, 7 days a week making it easy for defects to be reported and resolved quickly.


Fair

In keeping with our payment method and agreement, all payment periods did not exceed 30 days


Sustainability

Low carbon design was included like passive design analysis, free cooling and future provisions for CHP. During the enabling phase, we acknowledged that the existing site had diverse habitat and preserved the wildlife by maintaining the wildflowers and grass for as long as possible. A dedicated foot traffic path was created through the field. Grass cuts were reused to protect the soil in the path and doubled up as safe passage during winter and wet months.


Legacy

700 trainee weeks, 10no supported employment, 12no new recruits, 4no work placements including 16no graduates and 8 activities to support students, such as careers fairs and talks and site visits. In addition, we renovated the local cricket pavilion and our trainee site manager supervised the club showers and toilet replacement works.  

“We are totally indebted to all involved who have saved our club after the fire and would welcome them all to join us on match days in the new facility that the council have provided for us and the local community.” Ian Guppy, from Aldwick Cricket Club, said the new building was a site to be proud of.

Paul Broggi, Property, Estates and Facilities Manager at Arun District Council said “I have been involved since inception and it has been an honour to work with all involved. It has been a bit of a labour of love and has taken a lot of time to resolve but I am extremely proud of the result.”

Further local community engagement projects included;  Acoustic barriers and fencing utilised during the construction phase was donated to the Coast Guard, Created a new local allotment entrance and donated site fencing, Donated defibrillator to local scout group, Bognor beach clean, Planting and clearing of weeks of Hotham Park.

SCF Framework Manager

James Wright

Email: James.wright@hants.gov.uk

Phone: 07761 330560

Contractor Framework Manager

Angela Purse

Email: angela.purse@gallifordtry.co.uk

Phone: 07593 561 855

https://southernconstructionframework.gov.uk/wp-content/uploads/2022/08/Bognor-External-Piazza-1.jpg 628 1184 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2022-08-11 11:03:202022-08-11 11:09:42University of Chichester

Rosalind Franklin Institute, Science and Technology Facilities Council

August 8, 2022/in /by Andrew Real

Rosalind Franklin Institute, Science and Technology Facilities Council (STFC)

  • Client

    Science and Technology Facilities Council

  • Contractor

  • Value

    £35m

  • Completion Date

    January 2021

About Rosalind Franklin Institute

The Rosalind Franklin Institute (RFI) is a life sciences facility named after one of the UKs pioneering female scientists. The building is dedicated to bringing academic and industry researchers from across the UK together to develop disruptive new technologies. These technologies are designed to tackle major challenges in health and life sciences and accelerate the discovery of new treatments for chronic diseases, affecting millions of people around the world, such as dementia.

The Challenge

The ground floor of the building had to be designed to accommodate sensitive scientific instruments which could not be subjected to vibration or electromagnetic interference.

The Solution

The foundations of the ground floor were designed to be separated from the rest of the building to shield it from vibration. To prevent electromagnetic interference, stainless steel reinforcement was used in the structure, and nonferrous materials used in the fabric, finishes, and MEP.

The Results

The design created a close to perfect, stable environment to test the limits of specialist technologies such as four large, state of the art electron microscopy suites and mass spectrometry facilities. The building now houses all core and support staff for the Institute, plus 150 researchers from industry and academia.


605


Apprentices

£29,900,000.


SME Spend

£4,990,000.


Added Value

9


Client Satisfaction

Client Testimonial

“Mace are currently delivering three projects across the live Harwell Campus site. Their attention to detail in health and safety and campus liaison has helped maintain business as usual for everyone.”

Clive NorkettScience and Technology Facilities Council
Previous Previous Previous Next Next Next

Contractor Performance | Commitments

Fair

Client and sub-contractor payments made within 21 days and 30 days respectively of certification/valuation date.

Sustainability

Building achieved BREEAM Very Good.

Safe

Zero RIDDORs

Legacy

75 trainee weeks

94 graduate trainee weeks

Aftercare

Building handed over January 2021 with zero defects. Two Mace managers remained on site for period afterwards to manage soft landings.

SCF Framework Manager

Adam Sanford

Email: adam.sanford@hants.gov.uk

Phone: 03707790304

Contractor Framework Manager

David Chambers

Email: david.chambers@macegroup.com

Phone: 07789 514895

https://southernconstructionframework.gov.uk/wp-content/uploads/2022/08/Outside-shot.jpg 637 956 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2022-08-08 14:20:432022-08-08 14:46:47Rosalind Franklin Institute, Science and Technology Facilities Council

Brixton House Theatre and Workspace, Somerleyton Road

July 29, 2022/in Civic and Community, Social Legacy/by Andrew Real

Brixton House Theatre and Workspace, Somerleyton Road

Brixton House is the new location for Ovalhouse, one of the most important centres for pioneer fringe theatre groups, previously located in Kennington. The Grand Opening was attended by the Duke and Duchess of Cambridge.

  • Client

    London Borough of Lambeth            

  • Contractor

  • Value

     £37m

  • Completion Date

    March 2022


Galliford Try has recently completed the construction of Brixton House – a modern, purpose-built arts and community destination in South London. Part of the Somerleyton Road Development Project in partnership with the London Borough of Lambeth, the new building houses two fully accessible theatres (120 and 200 seating capacity), seven flexible rehearsal rooms and a creative hub with large public café, while the neighbouring Victorian Carlton building, Carlton Mansions, has been refurbished to create two floors of creative workspace.


Copyright: Hufton+Crow

The Challenge

Surrounded by busy residential streets and a railway line, all while sitting atop London Underground tunnels, it’s no surprise this project required extensive collaboration, negotiation of intricate party-wall and land ownership issues and complex construction logistics. In addition, much of the project coincided with the Covid19 pandemic and the resulting lockdowns, requiring active management of resource and material difficulties.

A scaffold was needed to repair the existing Victorian façade at Carlton Mansions – the challenge was it needed to be erected just one metre away from the railway line. One of south London’s busiest passenger lines and a primary freight line, it is in constant use throughout the day and night.

The Solution

Following extensive engagement with Network Rail and our scaffold supply chain partner, Trad Scaffold, we had a daily 45-minute window to erect, and eventually dismantle, the scaffolding.


Copyright: Hufton+Crow

The Results

Scaffolding was installed and dismantled within programme and highest safety standards.

‘H&S procedures were well followed, and good behaviours were demonstrated by the site team and the operatives. The response to Covid was excellent.’

Bruce McRobie, London Borough of Lambeth

In addition, whilst resolving a key buildability challenge we presented the opportunity for London Borough of Lambeth to generate increased revenue across the lifetime of the project. Requiring construction over a London Underground tunnel, we developed a displacement foundation solution as an alternative to a piled solution. We then proposed utilising the void created for lettable space as recording studios.


Copyright: Hufton+Crow

14


Apprentices

£21.9m


SME Spend

£5.7m


Added Value

9/10


Client Satisfaction

Client Testimonials

“Actively collaborated and formed a one-team ethic with the client team. Open-book approach consistently and enthusiastically applied across all disciplines.”

Bruce McRobieLondon Borough of Lambeth

“The Brixton House team wish to pass on our sincere gratitude for assisting us in our last performance at the old building. Bringing a poignant end to over 55 years of theatre at Kennington Oval. Whilst the occasion was emotional for all involved, the support your staff gave, and continue to give is providing our team and our stakeholders with hope and enthusiasm for the future, where it is much needed. Furthermore, adapting our new home at this late stage to cope with COVID19 is a real credit to your dedicated team. A sincere thank you.”

Gary Johnson Brixton House

“The support your staff gave and continue to give is providing our team and our stakeholders with hope and enthusiasm for the future. Furthermore, adapting our new home at this late stage to cope with COVD-19 is a real credit to your dedicated team. A sincere thank you.”

Gary JohnsonBrixton House
Previous Previous Previous Next Next Next

Contractor Performance | Commitments


Safe

The project achieved zero RIDDOR, had an average CCS score of 42 and was able to continue to operate safely during Covid with no major outbreaks. During the construction phase, numerous safety stand downs were carried out, two in particular during Covid when social distancing was in place and with circa 140 operatives on site was no mean feat. During these stand downs, the site team utilised the basement area of the site, setup individual stalls manned by a different member of the team, and we had groups of six operatives work their way down each stall to discuss various Health and Safety topics including lifting operations, dust control, work at height and also mental health.


Legacy

Restoration of mural of local importance: Painted on the side of Carlton Mansions, the Nuclear Dawn mural was given a new lease of life. Created in the 1980s when Britain was in the clutches of the Cold War, it has been fully restored by local artist, Morganico, and muralists Paul Butler and Linda Jane James. Brian Barnes MBE, one of the original creators of the mural, has been a regular visitor throughout.

Local artwork: Rising up from the ground floor is a pink cantilevered staircase and greeting visitors and users of the theatre at each floor level is a mural from local artist Damilola Odusote. Known for his eclectic, intricate, illustrative work, Damilola was given free reign by London Borough of Lambeth.

Social value: Over 340 training weeks, 14 apprentices, 6 jobs created for local people and 85% employed local labour. We volunteered monthly from January 2017 until December 2021 at The Ace of Clubs in Clapham, offering support to vulnerable homeless people. This included preparing and serving lunch.


Fair

Payments were paid on time and this continued even when the site was closed during Covid. We helped pay some of our supply chain’s material order during Covid to ensure work continuity and agreed many final accounts ahead of project completion.


Sustainability

This project achieved BREEAM Very Good, EPC of A rating, and air permeability of 3m3/hr/m2. Other sustainable features include photovoltaics, sustainable drainage systems and both blue and green roofs.


Aftercare

Galliford Try Facilities Management will be on site for five years, aiding 24 hours a day, 7 days a week. Our Project Director continued to stay on site 10 weeks post completion to make sure that everything was working as it should be and resolve defects promptly.

SCF Framework Manager

Alex Nelhams

Email: alex.nelhams@hants.gov.uk

Phone: 07717 003869

Contractor Framework Manager

Priya Parthi / Angela Purse

Email: Priya.parthi@gallifordtry.co.uk / Angela.purse@gallifordtry.co.uk

Phone: 07484037015 / 07593 561 855

https://southernconstructionframework.gov.uk/wp-content/uploads/2022/07/Foster-Wilson-Size_Brixton-House_©HuftonCrow_006.jpg 1200 1175 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2022-07-29 16:40:452022-07-29 16:44:01Brixton House Theatre and Workspace, Somerleyton Road

Kingsbrook View Primary Academy, Aylesbury

July 29, 2022/in Education: Primary School/by Andrew Real

Kingsbrook View Primary Academy, Aylesbury

The state-of-the-art school consists of a new build two-storey SIP construction teaching block and main hall, a sports pitch and associated external soft and hard landscaping providing 420 places and 52 nursery places.

  • Client

    Buckinghamshire Council

  • Contractor

  • Value

    £10.95m

  • Completion Date

    July 2021

Project Information

Procurement Type: Two stage

Form of Contract: JCT 2016 D&B

Contract Period: 48 weeks

Size: 2,515 m

The Challenge

  1. The need to undertake a complete redesign of the school at the start of the PCSA period due to adverse comments from the Local Planning Authority on the RIBA Stage 2 design.
  2. Ensuring our developed red line boundary aligned with both the council position and the developer’s team.
  3. Designing to budget
  4. Speed, safety and cost of construction

The Solution

  1. The complete redesign of the school building and landscape was completed at the outset of RIBA Stage 3, and the overall PCSA design programme was still met.
  2. Early in the process we worked closely with the developer’s team to engage on incoming service locations, drainage connections and tie-ins to local S278 highways. In order to ensure tie in positions were suitably coordinated Morgan Sindall ran a separate combined model which was shared with the developer’s design team so an external ‘clash’ process could be used. Once fully coordinated, Morgan Sindall supported the council on key deliverable dates which formed a key part of the land transfer legal documentation
  3. The design was market tested during RIBA Stage 3.  We managed the design and budget throughout the PCSA using our supply chain early to market test packages and set a realistic and achievable cost plan from the outset achieving the contract sum below the agreed PCSA cost plan. We performed a sanity check on the Pick Everard stage 2 cost plan.

4. SIP construction is much faster than traditional building. At Kingsbrook, using SIP construction allowed the programme to be significantly reduced whilst still producing a quality building.

The Results

  1. Planning approval was achieved with no pre-commencement conditions.
  2. Once the land transfer was signed, no delays were parted onto the project as a result of developer delays. Once the contractual side had been finalised, we worked alongside the developer to produce a combined traffic management plan which ensured interfaces on deliveries and loading zones were fully coordinated to avoid any disruption to the local residence in the vicinity of the school.
  3. No VE was required at CP stage. The client, Morgan Sindall and the design team worked very well together, taking a ‘one team’ collaborative approach where design matters were discussed openly and always in a constructive and objective way. The design was delivered within the client budget which was agreed very early on in the PCSA. This cost plan was updated with package fees as they came in and shared with the Client PM on commercial catch-up calls scheduled weekly creating an open-book collaborative working relationship from the outset.

4. The SIP installation was 12 weeks allowing following trades and internal works to progress. Additionally, due to the nature of SIP construction all internal walls had been installed and therefore this removed the 1st fix process of drylining, reducing installation time and in turn associated costs. The site establishment was required for less time and therefore overhead costs of accommodation, site setup and management costs are minimised.

Due to SIP construction consisting mostly of offsite production this significantly reduced risk on site, the panels were produced in a controlled factory environment away from the construction site, leaving minimal works to take place on site.


14


Apprentices

80%


SME Spend

£394k


Added Value

9/10


Client Satisfaction

Client Testimonials

“This is a truly wonderful building. The facilities are second to none and will provide a great learning environment for the current and future pupils. The building has sustainable credentials such as solar panels on the roof and the building fabric is designed to ensure it is thermally efficient thereby reducing the carbon emissions which will help the Council meet its Carbon reduction targets. I hope the pupils, teachers, staff and local community enjoy the new facilities for many years to come.”

Councillor Anita CranmerCabinet Member for Education, Buckinghamshire Council
Previous Previous Previous Next Next Next

Contractor Performance | Commitments


Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times


Safe

Zero RIDDORs

CCS Score 43/45


Fair

100% payment within 30 days terms


Sustainability

The high-quality, energy efficient building is designed to enhance the character of the local area and provide a positive contribution to the public realm and includes a number of landscaping features to help complement its surrounds including planting choices to maximise benefits for wildlife.

Air tightness achieved required performance of 4m3/(h.m2) at 50 pascals, 98% waste diverted from landfill, 100% timber responsibly sourced, Solar panels on roof, Thermally efficient reducing carbon emissions helping LA meet its carbon reduction targets, Electric charging points installed; cycle and scooter storage, Wildlife area and forest school


Legacy

25 beneficiaries (36% aged 16-25)

8 jobs created

266 trainee weeks

Schools engagement: 120 students

£5,000 donations to charity

112 volunteer hours

89% social value created

SCF Framework Manager

James Wright 

Email: james.wright@hants.gov.uk

Phone: 07761 330560

Contractor Framework Manager

Alan Smedley

Email: alan.smedly@morgansindall.com

Phone: 07967 686066

https://southernconstructionframework.gov.uk/wp-content/uploads/2022/07/53Y002_M50-scaled.jpg 1365 2048 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2022-07-29 12:48:362022-08-12 11:39:38Kingsbrook View Primary Academy, Aylesbury

The Bottle Yard Studios

May 27, 2022/in Civic and Community/by Andrew Real

The Bottle Yard 2 Studios

    Project Details

    Procurement Type:
    Two stage Design & Build

    Form of Contract:
    NEC 4

    Contract Period:  34weeks

    Size: 82,000 sq ft

    The Challenge

    Bristol City Council (BCC) contracted ISG to convert the industrial property at Hawkfield Business Park, less than half a mile from the main Bottle Yard site, into three new state-of-the-art studios in South Bristol (The Bottle Yard 2).

    BCC was heavily focused on increasing the sustainable performance of the studios as well as delivering a social value target of £230,500.

    During the Preconstruction Service Agreement (PCSA) period ISG’s team worked alongside AHR, Method and CMB to develop the mechanical ventilation strategy after an initial survey indicated that the original natural ventilation strategy would not be sufficient to service the volumetric needs of the studio spaces required to meet regulatory requirements. The new mechanical ventilation systems had to be carefully designed to integrate the acoustic requirements of the sound stages.

    The new system had to be designed to provide flexibility at height to accommodate the lighting, staging and sound rigs within the studio areas.

    The Solution

    Due to the internal scale of the rooms, standard building regulations and compliance had to be carefully considered to deliver compliant low energy mechanised ventilation system with heat-recovery and fan coil units delivering hot/ cold air into internal spaces. ISG worked with Method and CMB to develop a series of thermal models to define how the studio space would perform through each season. Their mechanised ventilation system features ceiling mounted textile baffles which align with the customer’s need for highly specified acoustic performance and minimal suspended services which could interfere with the staging rigs. The system’s benefits include:

    • Superior acoustic control
    • Meets user requirement for minimal roof-based services
    • Better user environmental control
    • Reduced in operation carbon

    Designed to provide enhanced sustainable and operational performance, The Bottle Yard 2 (TBY2) adds three new sound stages measuring: 20,000 sq. ft, 16,000 sq. ft and 7,000 sq. ft to the existing Bottle Yard facility, accompanied by ancillary spaces including production offices, prop stores, costume/ make-up and break-out areas totalling 82,000 sq. ft.

    ISG worked with Bristol City Council who were committed to following a performance and evidence based approach to social value, based on National Themes, Outcomes and Measures (TOMS) developed by Social Value Portal. ISG worked in partnership with BCC, Social Value Portal and their supply chain to develop a bespoke social value plan.

    The Results

    The new studios are one of the first Studios to be awarded BAFTA albert’s inaugural Studio Sustainability Standard. It was the second highest scoring studio out of the 12 participating in this first cohort. The project also won a 2023 Global Production Award in the Sustainable initiative category at Canne Film Festival.

    Since its completion in November 2022, the expansion to The Bottle Yard, from eight to 11 stages, has ensured the continuing growth of this already established facility and secured Bristol’s status as a UNESCO City of Film, allowing growth via clients such as BBC and Amazon.

    Overall, the investment in the current Bottle Yard Studios site and additional studio provision at the new TBY2 facility located at Hawkfield Business Park is expected to create 135 jobs during the refurbishment process, with a further 863 jobs created over the next 10 years through an accompanying Workforce Development Programme focused on high-end TV skills and targeting development of new talent in South Bristol.

    The project has created a legacy in South Bristol. It has generated £3,153,615.37 of social value at completion versus a target of £230,589.44. Outperforming the target by 1,367.63%. The collaboration between BCC, ISG and members of the TBY2’s integrated delivery team played a critical part the project’s success in promoting investment in the local economy and surrounding community.


    72


    Apprenticeship weeks

    £3,060,172


    SME Spend

    88%


    Client Satisfaction

    Improved performance in operation and end-user wellbeing due to improved thermal & acoustic strategy



    Added Value

    Client Testimonials

    “It is great to see the expansion work starting at The Bottle Yard Studios. Our £1.6m investment in the current site, coupled with the additional capacity at the Hawkfield site, once developed, will bring confidence to the city’s film and TV production sector and harness growth as the demand for on-screen content grows worldwide. The expansion will also create jobs, skills, and training opportunities, support the local supply-chain and be a major boost to our wider regeneration plans for south Bristol, bringing growth and opportunity into the area.”

    Marvin ReesMayor of Bristol

    The expansion of The Bottle Yard studios sends a strong message that our amazing creative sector here in the West-of-England is thriving. So many talented people are helping put our region on the national and international map as a go-to location for the film and TV industry. Three new stages will mean even more of our favourite shows like The Outlaws, Poldark and Showtrial can be filmed here. This vote of confidence in the West-of-England will create a thousand high skilled jobs and should help us to attract even more production companies. I look forward to watching lots of new shows hit our screens, and I’ll enjoy them even more knowing they are made in the West-of-England”

    Dan NorrisMayor of the West-of-England.
    Previous Previous Previous Next Next Next

    Contractor Performance | Commitments


    Fair

    100% payment within 30-day terms


    Sustainability

    Up to 70% off annual running costs


    Safe

    Zero RIDDORs

    CCS score: 44/45

    26/27 CLOCS Audit Score


    Aftercare

    Handover & Aftercare Contractor Promise


    Legacy

    Support local community projects:
    Heart of BS13 – Volunteer day to help set up the new sustainable flower farm
    Wild Goose Charity – Volunteer day to refurbish and paint worn cafe furniture

    Inclusion for disabled and neuro diverse colleagues’ training for 3 staff members

    11 community events

    5 jobs created

    SCF Framework Manager

    Kingsley Clarke

    Email: kingsley.clarke@devon.gov.uk

    Phone: 07805760622

    Contractor Framework Manager

    Matt Glass

    Email: Matt.Glass@isgltd.com

    Phone: 07929755500

    https://southernconstructionframework.gov.uk/wp-content/uploads/2022/05/0X0A5766d-scaled.jpg 1366 2048 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2022-05-27 12:43:492024-04-26 09:19:38The Bottle Yard Studios

    Bristol Humanities Hub

    May 26, 2022/in Civic and Community/by Andrew Real

    Bristol Humanities Hub

    The new state-of-the-art Humanities Building is in the Arts Complex surrounded by a series of handsome of Victorian villas with Woodland Road nearby.

    • Client

      University of Bristol

      University of Bristol

    • Contractor

      ISG

    • Value

      £9.8m

      £9.8m

    • Completion Date

      January 2020

      January 2020

    Project Details

    Procurement Type:
    Two Stage

    Form of Contract:
    NEC version 4

    Contract Period: 86 weeks

    Size: 29,375 sq ft

    The Challenge

    Restricted footprint – The dimensions of the site were 30 x 70m in a complex urban live environment adjacent to occupied Grade II listed properties.

    Demolition in a confined live environment – The confined nature of the site required sensitive demolition.

    Impact on adjacent Grade II Listed buildings – The original site comprised of an existing single storey building and external courtyard space, located behind the two main Grade ΙΙ listed villas.

    Basement design – A key project driver was the basement solution confirmed as this was vital to achieving the budget and programme.

    Design of the retaining structure – With budget and programme constraints to consider, a hybrid solution was developed, which moved away from the simplest option of using contiguous piling in all three areas.

    Ventilation solution and occupancy level assumptions – We reduced occupancy levels, which enabled natural ventilation to be considered. This supported the aspiration in line with BREEAM Excellent.

    The Solution

    Restricted footprint – Due to the confines of the site, we could not use mobile cranes as these would have required lorries to support the mobile cranes, increasing congestion of local roads to an impractical level for our neighbours. As an alternative, we used a tower crane which occupied less room occupying only 5 x 5m and preventing unnecessary disturbance to the local community.

    Demolition in a confined live environment – Demolition was planned to have minimum impact on students, faculty and adjacent privately owned student accommodation during holiday periods starting in July 2018. In collaboration with the client’s facilities management team, we isolated fire alarms and ensured there was a temporary fire strategy for retained buildings following demolition of existing structures.

    Impact on adjacent Grade II Listed buildings – Adjacency to existing buildings was immediately identified during the pre-construction phase as a key area of design risk. Early works involved re-evaluating the basement perimeter, to increase the area between existing buildings and the boundary, whilst maximising the footprint to accommodate a lecture theatre, cinema, and plant room.

    Basement design – The original basement depth and proximity to existing structures (party wall) and retained teaching facilities presented a risk to construction. During the design phase we relocated the basement, minimising the risk to programme, cost, and buildability. Our design team reviewed spatial planning and reconfigured internal layouts which were agreed in collaboration with the client’s project manager and client stakeholders. Our solution used off-site manufactured pre-cast basement walls which reduced programme time. This demonstrated a six-week saving to the original programme.

    Design of the retaining structure – Retaining structure solutions:

    • Contiguous pile wall to part of the perimeter as a retaining system for two sides of the lecture theatre on the Northeast of the site, this is pinned with free standing cantilevers
    • Slope batters at 2.1m for remaining basement wall structure
    • Waterproofed contiguous pile wall with masonry face, incorporating drainage gulley
    • Precast wall favoured for remaining walls, with integrated damp proof membrane and stone backfill placed between the building’s steel frame structure

    Ventilation solution and occupancy level assumption – We introduced natural ventilation on the first floor. Using thermal modelling we reassessed and rationalised the mechanical to natural ventilation. This aligned the scheme with the client’s aspiration to have natural ventilation wherever possible. This allowed reduction in the requirements of ventilation. We reduced large ducts within and on the side of the building creating additional floor space. We removed the need for large risers allowing us to provide extra cupboards and increased floor plan space.

    The Results

    • To overcome the restricted footprint, ISG worked closely with Bristol City Council Highways Department to create a traffic-controlled loading lane on the busy Tyndalls Road. This enabled the efficient offload of materials via the site tower crane
    • By sequencing the demolition, we prevented possible uncontrolled collapse. This was achieved by the buildings being munched down to ground rather than dropped
    • Vibration monitoring ensured piling works for both the adjoining wall and the basement floor, from which the steel frame is mounted, did not impact on adjacent properties
    • The priority was to re-design the basement perimeter, with the requirement to both minimise risk to adjacent properties and enable sufficient space to construct the retaining walls. By re-positioning, the plant room, and subsequent risers, whilst maintaining the position of the lecture theatre, adequate space was created
    • ISG aligned the scheme with the client’s aspiration to have natural ventilation.

    6


    Apprentices

    79%


    SME Spend

    £760k


    Added Value

    84%


    Client Satisfaction

    Client Testimonials

    “I have much pleasure in welcoming you to the School of Humanities, a leading centre for teaching, learning and research the humanities located in the dynamic port city of Bristol.”

    Martyn PowellHead of School
    Previous Previous Previous Next Next Next

    Contractor Performance | Commitments

    Fair

    100% payment within 30-day terms

    Sustainability

    100% waste diverted from landfill.

    BREEAM Excellent

    Green roof, photovoltaics, natural ventilation

    Safe

    Zero RIDDORs

    CCS Score 42/50

    Legacy

    4 Open Doors sessions

    34 attendees to a Women in Property site visit

    WOWEX (World of Work Experience) – 18 attendees with 5 accepted onto ISG’s apprenticeship programme

    10 school and college visits engaging 400 young people

    15 community events

    10 jobs created

    Aftercare

    Handover & Aftercare Contractor Promise

    SCF Framework Manager

    Kingsley Clarke

    Email: kingsley.clarke@devon.gov.uk

    Phone: 07805760622

    Contractor Framework Manager

    Matt Glass

    Email:  Matt.Glass@isgltd.com

    Phone: : 07929755500

    https://southernconstructionframework.gov.uk/wp-content/uploads/2022/05/Bristol-Humanities-Hub_Image-1-scaled.jpg 1365 2048 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2022-05-26 16:17:582022-10-25 16:51:40Bristol Humanities Hub
    Page 5 of 14«‹34567›»
    SCF Logo White

    Two Stage Open Book Procurement delivered by the public sector, for the public sector.

    • Cookie Policy
    SCF is a member of NACF, a national collective of regional frameworks which shares best practice expertise and experience.
    © 2026 - Website by Blaze Concepts
    Scroll to top Scroll to top Scroll to top