Islington, London
London Screen Academy was a design & build project which involved the partial demolition of part of the central and southern section of the existing 4 storey plus basement building. The logistics of building within a building was the most challenging aspect of the project
One of the biggest refurbishment challenges to the non-studio part of the project was the sagging and heavily deflected floors that were in the existing building. The beam-and-pot floor construction had been filled with terracotta void formers but over time this has sagged by up to 60mm across the full extent of the floor.
While the structural condition of its primary frame was generally good, there were some wear and tear problems associated with cracked lintels and corroded steel reinforcement helibars within concrete.
The refurbishment gives the building a major internal reconfiguration as well as adding a new steel frame structure which provides a three-storey film production studio and supporting facilities. The scope of works also included new windows and façade repairs to the existing building.
The existing 4 storey plus building was replaced with a 3 storey plus basement building and a third floor roof amenity space, provision of replacement doors and windows to include ventilation louvres, reinstatement of door on Highbury Grove frontage; provision of bicycle and bin storage and new fence along Kelvin Road frontage; new glazed roof on single storey extension to the south, and removal of the existing single storey structure on roof, extension of two existing stair cores and lift overrun, and provision of new balustrade, photovoltaic panels and a sedum roof at roof level in order to facilitate the use of the building as a specialist Class D1 sixth form school.
The former factory in Islington has been transformed into a new specialist sixth form-only free school for 1,000 16 to 19-year-olds, providing training in film and television, with specialist areas including editing suites and music and performance spaces.
The interiors team worked closely with the design team to deliver the project ready for the first intake of 300 students in September 2019, with the LSA expanding eventually to a capacity of 800-1000 pupils.
100% of payments made on time
98% of waste diverted from landfill
A key aspect was a heating system that makes use of passive heat recovery, using outdoor air to cool the building where possible.
Further low carbon technologies include 100% LED lighting throughout the building, with additional daylight dimming functionality and presence detection.
Extensive electricity, water and gas metering was installed and is monitored by the Building Management System (BMS) so that data can be analysed to further optimise energy usage.
The building’s roof has a green area to enhance biodiversity, solar PV panels to generate renewable electricity and export back to the national grid, achieving cost savings, improving occupancy wellbeing and retaining the building’s existing character.
Handover & Aftercare Contractor Promise
Email: james.wright@hants.gov.uk
Phone: 07761 330560
Email: guy.dawes@willmottdixon.co.uk
Phone: 07989179444
Client
Bay Education Trust
Project Manager
Torbay Development Agency
Architect
KTA Architects Ltd
Contractor
Midas Construction Ltd
Value
£2.4m
Contract Period
38 weeks
Procurement Type
Competitive tender – 2 stage
Form of Contract
JCT Intermediate Building Contract with Contractors Design 2016
Size
880m²
Apprentices
17
Supported by the Torquay Development Agency (TDA) and with capital funding secured via a Condition Improvement Fund from the Education and Skills Funding Agency, this project at Paignton Community and Sports Academy (part of the Bay Education Trust), saw construction of a single-storey, multi-use hall.
Delivered at the Academy’s live Borough Road campus, the new Events Centre provides a flexible working space suitable for a full range of sporting and extracurricular activities. The hall features retractable seating, a mezzanine level and dual-purpose lecture theatre/ performance space. The Centre includes a kitchen and dining area, entrance lobby and reception, and an external covered walkway.
Midas constructed the Events Centre following demolition of an outdated 1930s teaching block, further enhancing the Borough Road campus through groundworks, landscaping and improved car parking.
The project received a customer satisfaction score of 87% in the survey at practical completion.
Works took place on a live educational campus
The Academy took partial occupation of the building during the works
Challenging site containing several live services
Our Success
Our Learnings
Value Added
Apprentices: 17
Average AIR: 0.7
Average CCS: score 37
Waste diverted from landfill: 100%
Cost/m²: 2,874m2
Cost/m²: excl abnormals 2,189m2
Client
Nuclear Decommissioning Authority
Project Manager
Avison Young
Architect
Avison Young
Contractor
Morgan Sindall (Overbury)
Value
£2.4m
Contract Period
32 weeks
Procurement Type
Design & Build
Form of Contract
JCT D&B
Size
1600 m2 GIFA
The West elevation of Building 329 was the subject of a CAT B fit out, on the ground floor this will include wings G,H,J & K, cores 2 & 3 and link 2. To the first floor fit out works were to wings J & K and core 3. The existing WC blocks on the ground floor and first floor, although within the site demise, were not the subject of any works.
Overbury took overall responsibility as principal contractor for the whole of the above areas and coordinated their works accordingly with adjacent tenants and the landlord contractors at the east end within building 77.
The floor plates included works to provide open office space complete with office desks and enclosed meeting rooms and offices; new comms and patch rooms to both floors. Existing carpet finishes remained in the majority of areas with new feature carpet to various walkways and offices. Decorations completed to all areas in line with finishes plan. Amendments to services were carried out to align with the new layout and occupancy levels. Kitchenette, and post room provided to the ground floor and a kitchenette to the first floor. Services included Access control, FA, CCTV, Intruder alarms and data to all areas.
The west elevation entrance was altered to accommodate new revolving entrance doors, with extended external paved landing and steps. Internally the entrance was fitted out with security speed lanes, reception desk, visitor WC and security office including ceramic floor tiles throughout.
All external windows had Anti Shatter clear film applied. The north of wing K had a sliding wall installed to provide a large conference room or 2 x smaller seating areas.
Due to the known presence of ACM, this required specialist attendance to accommodate removal of base build structures to facilitate the installation of services and finishes. Fixing of high and low level components were the subject of strict procedures to negate penetrating through the known ACM.
New service and drainage connections and ducting required both external and internal excavations.
Extent of asbestos remaining within the building
This could not be removed as encased within the base build floor slabs across the entire area. We had to re-sequence all works and re-programme the works to allow the asbestos contractors to “deal” with installing our fixings and provide us with service penetrations before handing the areas back to us following air clearance certificates being issued.
Fixing methods of all components due to asbestos
This encompassed all services, specifically at high level. We achieved this by installing 4000 meters of Uni-Strut to suspend all services and ceilings from it. The Uni-Strut was fixed by our specialist Asbestos Contractor using circa 8000 fixing bolts. Fixing of components to floor was also problematical as limited to depth of fixing so we did not penetrate the Asbestos. Re-designed base units and fixings and depth gauges on drilling tools were used.
Security design and installation extremely sensitive and classified as “Official Sensitive” in all correspondence
This meant that we and our security contractor had to under go security clearance checks, with our security contractor being subjected to extensive checks by the NDA authorities.
Distribution of all security designs and drawings could only be carried out via a specific PC located within NDA premises. Displaying of any designs or drawings could only be done on any floors above 1st floor level, all items had to be removed at the end of the working day and placed under lock and key.
Our Success
Our Learnings
Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
---|---|---|---|
Cost | £2,105,632 | £2,105,632 | 0% |
Time | 29 weeks | 31.3 weeks | +2.3 weeks |
The epitome of Team Collaboration
Appointed by Royal Borough of Greenwich, Galliford Try recently completed a 2 form entry community primary school for 420 primary and 26 nursery pupils, including a Behaviour Support Unit hosting up to 18 children. The works comprised a two-storey building, extensive landscaping and sports facilities served by a standalone changing block, which are used by the local community. In addition to a new multi-use games area (MUGA), there are outside learning areas including a wild meadow orchard, forest skills area, trim trails, horticultural area with raised planters and an amphitheatre. The project achieved BREEAM Excellent by maximising passive techniques to reduce energy consumption and environmental impact.
There were several challenges the team faced. Budget constraints and keeping to programme despite being bookended by Covid and three national lockdowns and consequently material shortages and delay were their biggest.
Keeping to budget: By engaging with their supply chain partners early in preconstruction, with an emphasis on added value, improved buildability and thus cost efficiencies and actively identifying alternative materials throughout, Galliford Try were able to provide significant savings on the project. Some included redesigning the ground floor slab to in-situ suspended slab, simplification of the window head brick detail and creating dual site access to optimise sequencing, enabling the building and landscape works simultaneously. Comprehensive surveys and ground investigations prior to Contract Award mitigated risks by preventing abortive designs based on assumptions.
The use of BIM Level 2 even though it was not a project requirement reduced both design and installation inefficiencies, saving time and money.
On time delivery: In addition to placing orders early and using more readily available materials to compensate manufacturing shortfalls in the UK and abroad, Galliford Try replaced in-person site visits with Zoom, GoPro cameras and drones for client and end user progress updates and inspections when Covid restrictions and lockdowns were in place.
The school was completed eight weeks early despite the challenges faced with the additional pressures of three national lockdowns, social distancing and reduced productivity (less people on site and delayed materials). The team achieved an overall client satisfaction of 9/10, with 10/10 in time management and Health & Safety.
Payment timescales to all: supply chain and manufactures were agreed and adhered to throughout the project. Payment notices were issued on time with zero ‘pay-less’ notice and 97% of subcontractor final accounts were agreed within two months on Practical Completion.
The project and site manager stayed on site four weeks post project completion and continue to keep in touch with the school, in conjunction with our Aftercare team.
To compliment the Aftercare team’s collaborative workshop to the end users 12 weeks prior to completion, the project team completed several site tours with the school’s executives and headteacher during the final construction phase, where defect sheets were presented, and reporting procedures explained during the walkabouts.
The team achieved AFR ratio 0 and zero RIDDOR, had an average CCS score of 42 and was able to continue to operate safely during Covid with no major outbreaks. The site was awarded ‘Quarterly Safety Award’ twice.
Designed to achieve BREEAM Excellent and with that included details that maximised passive techniques to reduce energy consumption and environmental impacts. Additional features incorporated a highly insulated building envelope, high thermal mass for night cooling, ventilation stacks with heat recovery, 90sqm of solar panels and electric charging points. Acoustic ceiling and breathing building units were installed in classrooms to enhance air quality for better student learning environment and achieved A for energy performance.
Following some tree removal, we reused the logs to form the forest trail and created pathways around the site using mulch (shredded trees). The mulch provided a more stable ground to work on, as well as acting as a nutrient bed for plants.
Employment Skills Plan: 68no of apprentices, 4no of employees who were previously unemployed, 5no careers, curriculum and literacy talks and 8 hours of improving staff wellbeing sessions. Covid-19 prevented us achieving our targets in full during the construction phase. In agreement with Royal Borough of Greenwich, we delivered our promises post project completion.
Greenwich’s own: A labourer, gateperson and welfare labourer/cleaner were employed through Greenwich council’s employment scheme, Greenwich Local Labour and Business.
Looking after the smaller businesses: To encourage greater micro and VCSE participation, we held a Meet the Buyer event at Greenwich Town Hall. To ensure that they could work with us and other contractors in the future, we held individual workshops and supported them by completing minimum requirements like PAS91 and Builder’s Profile registration.
Greater emphasis on health and wellbeing: During the early stages of the pandemic, we arranged for a top medical visitor to deliver a toolbox talk to explain Covid 19 and ‘debunking some of the myths’ surrounding the illness. Not only did this reassure our operatives, but also provided them the opportunity to ask questions and have first-hand information affecting both theirs and their families’ health.
Lasting school legacy: We donated a mosaic plaque with the school’s crest at part of the Opening Ceremony.
Email: james.wright@hants.gov.uk
Phone: : 07761 330560
Email: Angela.Purse@gallifordtry.co.uk
Phone: 07593 561855
Client
Valley Invicta Academies Trust
Project Manager
Arcadis
Architect
KSS
Contractor
BAM Construction
Value
£25.54 million
Contract Period
93 weeks
Procurement Type
Design & Build
Form of Contract
JCT 2017
Apprentices
12
BAM has built a new secondary school for pupils aged between 11 and 18, with an annual intake of 180 pupils. The school will help Kent County Council to meet the predicted shortfall in secondary places in the Maidstone area.
The curriculum offers world-class teaching and learning with a focus on Science, Technology, Engineering and Mathematics (STEM subjects). The school’s industry partners include Maidstone and Tunbridge Wells NHS Trust, and international educational partner, the School of Science and Technology in Singapore.
Student Support
Career Development
Local Transport Links
Maidstone Borough Council were imposing a number of conditions, including significant development of local transport links. Some initial concerns were raised by residents about the potential impact on queuing traffic around the entrance of the school. This was addressed by creating a large drop off zone within the car park area.
Planning
The team worked tirelessly to get the scheme through a challenging planning process. Early contractor appointment was essential to ensure affordable design prior to planning submission. The team have worked hard to achieve this ahead of planning.
Contact: Darren Birch, Framework Manager
Email: dbirch@bam.co.uk
A bespoke ‘BREEAM Excellent’, 3-storey engineering and research building, housing the world-leading VSimulator facility, providing specialist engineering facilities and open-plan, flexible workspace. The facility will play a major role in spearheading Exeter Science Park’s aspirations and reputation for research and innovation, stimulating a knowledge-based economy, delivering jobs, higher productivity and economic growth.
Providing unique simulation capabilities far beyond anything available worldwide, the VSimulator facility will be used by academics and industry to support multi-disciplinary research factors. Helping to address critical issues of human engagement with the surrounding environment, it will present research, commercial and training opportunities within an endless range of disciplines.
Imperative to the successful project outcome, the Virtual Simulation Chamber had to be handed over to the specialist engineers on time to commence installation of the state-of-the-art motion platform and other equipment.
Additionally, the basement concrete floor had to be within a 2mm-tolerance level and strict water-proofing specifications had to be achieved prior to the VSimulator installation.
Further adding to the challenge were complex logistics and mechanical and electrical installations, and the involvement of multiple, including global, specialist installers.
Through sectional completion (in October 2019), we handed over the basement to the University for fitting-out of the simulator, whilst the remaining works continued. We worked closely with the University throughout the fit-out works, ensuring this was undertaken safely while the remaining works took place concurrently.
During early design collaboration, we were able to offer our experience with basement construction to align buildable-construction details with specialist tanking manufactured products. It was at this early stage when a significant change in tanking membrane manufacturers occurred and, with the help of our supply chain family, we were able to provide a quick solution to the benefit of the client.
Communication was critical to ensuring we kept to programme, and we successfully managed the co-ordination of overseas meetings, held virtually, regarding set-up, installation and delivery of equipment for the motion platform.
Drawing upon the expertise and skills of the project team, the challenging project objectives were all achieved, to the delight of the client.
100% payment within 30 days terms
BREEAM Excellent
99% waste diverted from landfill
100% timber responsibly sourced
Zero RIDDORs
CCS Score 43/45
38 No of SMEs
10 beneficiaries
4 jobs created
49 trainee weeks
Schools engagement: 28 students
£200 donations to charity
39 volunteer hours
88% social value created
Soft landings for handover
Dedicated Morgan Sindall point of contact
On-line portal for notifying any defects with 3 priority categories for response times
Email: kingsley.clarke@devon.gov.uk
Phone: 07805760622
Email: alan.smedley@morgansindall.com
Phone: 07967 686066
A new build four-storey steel frame building which includes two sports halls, three fitness studios, a health and well-being gym, a strength and conditioning high-performance gym and high-quality teaching facilities on a live university campus. The scheme also includes underground car parking.
The ambitious vision for the University was to create a new sports facility to improve and modernise the University’s offering and enable excellence in sport, health and fitness related degree programmes and associated teaching and research for staff, students and the local community.
The seminar and gym areas of the sports complex are fitted with 20mm soft joints between the room floor slabs. These help to isolate them and significantly reduce the vibration that passes through them. In the weight training area, they went a step further and introduced a cast in-situ reinforced concrete sprung floor. This innovation means that the sports hall can be enjoyed by everyone, no matter what activity they are involved in.
The iconic cladding system to the tower block represents the former use of the site with historical maps – a subtle presence in the perforation in the cladding system next to the standout face brickwork wrapping the sports halls. The building has provided a head turning modern build in Southampton’s old city centre.
The city centre project was constructed within a 86 week programme, delivering a four-storey sports complex with state-of-the-art gyms for both student and staff use. Along the stacked tower block of gyms and studios, the project had two full sized sports halls; one for multi-use catering for over 13 different sports, the other was dedicated to basketball, allowing Student Kestrels, the university’s leading sports team, a home court. Below the sports halls, basement parking was provided for staff, students and the public as well as accessible parking bays.
The project is a visually stunning, flagship sports facility which is enhancing Solent University’s offering in advanced sports degree courses, and it is already attracting more students to the local area and inspiring people to take part in sport.
100% payment within 30 days terms
99% waste diverted from landfill
100% timber responsibly sourced
Zero RIDDORs
CCS Score 44/45
36 No of SMEs
59 beneficiaries
18 jobs created & 184 trainee weeks
Schools’ engagement: 577 students
£3,046 donations to charity & 1,845 volunteer hours
84% social value created
Soft landings for handover
Dedicated Morgan Sindall point of contact
On-line portal for notifying any defects with
3 priority categories for response times
Email: james.wright@hants.gov.uk
Phone: : 07761 330560
Email: alan.smedley@morgansindall.com
Phone: 07967 686066
Client
University of Exeter
Architect
Stride Treglown
Contractor
Kier Construction
Value
£8.2m
Contract Period
December 2017 – February 2019
Form of Contract
NEC Option A with design
The design and construction of two buildings for laboratories and research facilities to allow further growth of Exeter Business School, the College of Engineering, Mathematics and Physical Sciences and the College of Life and Environmental Services.
This new Science Engineering Research Support Facility (SERSF) building provides facilities for around 200 researchers and postgraduate students specialising in science and engineering.
The new facility accommodates many disciplines, including the newly established Business School, the Centre for Ecology and Conservation, Renewable Energy and Camborne School of Mines. It is also the new home for Law, Energy Policy and Mathematics
A large glazed atrium forms the main entrance and the vertical circulation route to all floors. The installation of a key operated lift allows lab users to access the autoclave area on the lower ground floor which creates a link for users to transport any contaminated waste, safely through the building.
A new seminar facility provides space to facilitate linkage with external agency researchers in marine science and wildlife research.
Previously constructed buildings.
The project consists of three linked buildings. The first phase of the project had already been constructed, which made the construction of the next two phases more complex as we were connecting and linking floor levels.
Existing services and diversions on main vehicular route.
The site was riddled with existing services and diversions impacted the main vehicular route into the campus. These works were brought forward in an enabling package at a more convenient, less disruptive time for the university.
Our Success
Our Learnings
Value Added
Client
Somerset County Council
Contractor
Morgan Sindall
Value
£736k
Contract Period
32 weeks
Expansion of the existing primary school with the addition of three new classrooms using the ‘Class Space’ standard design. The classroom extension included toilets and was situated on the old basketball court, north of the school’s sports hall.
The client wanted the classrooms to be flexible for potential future use and expansion. Therefore, the internal dividing walls were stud work and the school’s preferred option of radiators were used instead of underfloor heating. The position and orientation of the building on the basketball court area were carefully designed so the school could construct another block adjacent to this one in the future. Other considerations included design items, such as mains cable sizes.
The extension was constructed of steel frame, blockwork rendered externally, with a profiled metal roofing system.
Fair Payment Charter
Sustainable Development Charter
Health & Safety Charter
Legacy Charter
Handover & Aftercare Contractor Promise
Careers Opportunities
Maintaining the school’s curriculum while working in a live school environment
Ensuring business continued as normal while coordinating deliveries
Ensuring the design allowed for future use and expansion
Our Success
Our Learnings
Value Added
Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
Cost | £2,462k | £2,417k | -1/8% |
Time | 32 weeks | 32 weeks | 0 |
Contact: Alan Smedley, Framework Manager
Email: alan.smedley@morgansindall.com
Client
Dorset County Council
Project Manager
Dorset County Council
Architect
Dorset County Council
Contractor
Morgan Sindall
Value
£2.7m
Contract Period
49 weeks
Procurement Type
Construction only
Form of Contract
JCT 2011 SFC
A new build two storey, separately annexed, classroom block extension to the existing school to increase capacity from 5 Form Entry (600 pupils) to 6 Form Entry (720 pupils). The new building, located to the eastern side of the existing school, provides four spacious classrooms, a multi-purpose resource teaching space, and a new dining hall and kitchen. The Multi Use Games Area (MUGA) was also replaced as the new building was located on the existing facilities.
Live school environment
Phasing of the works, sectional handovers and decanting pupils as works completed
Our Success
Our Learnings
Value Added
Value engineering was carried out with the following outcomes:
Contract | Gateway 3 Contract Agreement | Gateway 4 Practical Completion | Variation |
---|---|---|---|
Cost | £2,707,877 | £2,521,556 | -7.4% |
Time | 45 weeks | 43 weeks | -2 weeks |