Live School Planning – One of the biggest challenges on site was progression of works being carried out based within a live school and having to accommodate being restricted and having less space to manoeuvre in certain areas that required attention to the most important areas. It became adherent that communication from all parties associated with the project was critical throughout the term to ensure there were safety measures in place to protect members of the public/staff and students during the progression of the project, whilst working towards handing over the building to projected contract end date.
E-Torch – The timber frame extension to the existing school, part of the school’s program education authority was chosen by Morgan Sindall as a pilot project for the introduction of a new ‘flame free technology’ using the ‘E-torch Max’, that
works in conjunction with Bauders self-adhesive flat roofing system. As with any timber frame building the risk of fire is of paramount concern, and this combining the need to drive down emissions the combination of the Bauder Air Tech Sa system and Imperial
Thermal’s hot air technology is the ideal solution. With the risk of fire, all but eliminated the speed of the E-torch Max in drying and the lap fusing processes, the installation proceeded at a competitive pace. The E-torch was effective in reducing fire risk, but it a slower application process compared to LPG, which further made it challenging to achieve contract programme milestones with a more sustainably efficient system but at a slower pace.
Live School Planning – Sequencing different work packages to begin during different timescales played an important factor to maintain progression to the job and was proven by prioritising the main extension build works, as works that were located in an existing areas of the school would continue to operate during school term. Prior to the summer holidays, we conducted a consultation with all subcontractors that had works arranged to be able to turn the classroom into 2 office spaces and sensory room in a 6-week programme. This strategy was proven beneficial, as we were able to successfully complete the refurbishment works within the programme time for the end-user to occupy prior to their return from the summer break.
E-torch System – The solution was to use the E-torch as a lap system with a sufficient number of operatives being able to lap the felt as the works progressed. An additional machine was supplied to the roofing contractor to assist in speeding the process to complete the roof within a 4-week period. The use of the E-torch system proved to be a success as an innovation point was awarded to Morgan Sindall By the ‘Considerate Constructors Scheme’ for the removal of LPG gas and the risks related to the use during flat roofing works.
Innovative Educational Design: Delivered a £4.0m extension comprising a modern Structural Insulated Panel System (SIPS) building with nine new classrooms, high-performance curtain walling, timber and brick external finishes, and integrated Mechanical Ventilation with Heat Recovery (MVHR) systems to provide an energy-efficient, healthy learning environment.
Designed for a Growing Community: The expansion was carefully planned to support increasing pupil demand within the rapidly developing Berryfields area while enhancing educational facilities and long-term operational efficiency.
The project acted as a pilot scheme for the introduction of the E-Torch Max flame-free roofing system, eliminating the need for LPG gas during roofing installation and significantly reducing fire risk on a timber-framed building.
This innovative approach received an Innovation Award from the Considerate Constructors Scheme (CCS). Achieved a perfect CCS score of 45/45, demonstrating outstanding performance in site management, safety, environmental responsibility and community engagement. Successfully delivered and handed over the facility in September 2024, despite the challenges of working within a live school environment and completing significant refurbishment works during a constrained six-week summer holiday period. Achieved zero RIDDOR incidents throughout construction while maintaining uninterrupted school operations.
Successfully maintained safe and effective operations within a live school environment through careful planning, phased delivery and close stakeholder engagement, enabling uninterrupted educational activities throughout construction. Achieved a high level of end-user satisfaction, recording a client satisfaction score of 9/10, with positive feedback on project delivery, quality and collaboration. Established long-term project legacy through comprehensive aftercare arrangements, including soft landings support, dedicated client contacts and a responsive defects management portal.
9no of SMEs
9no of businesses within a 30-mile radius, 14no jobs created within 30-mile radius, 3.5 trainee weeks
Schools’ engagement: 180no students for site visit & 60no students for book reading
£8k donations to charity, 100+ volunteer hours to local school talks and careers fairs
£950k spent on local supply chain LM3, 67.2% social value created
99% waste diverted from landfill
100% timber responsibly sourced
Any project specific initiatives / stats
Scored 10/10 for the H&S procedures on site. Excellent management of supply chain RAMS
100% payment within 30 days terms
Soft landings for handover
Dedicated Morgan Sindall point of contact, On-line portal for notifying any defects with 3 priority categories for response times
The site is located within the London Borough of Lambeth, bounded between the River Thames to the West and Lambeth Palace Road to the East. The site is situated between two Grade II listed façade building’s (Block 8 and Block 9) at the termination point at the southern end of Guy’s & St. Thomas Hospital (GSTT). The wider connections to the site are via Westminster Bridge to the North and Lambeth Bridge to the South via Lambeth Palace Road. The site is elevated above the Albert Embankment and within the Albert Embankment Conservation Area.
There was an existing vehicular access road throughout the existing development. This access road was required to be maintained during the works. As a result, this road was relocated and adapted during the multiple phases of the works. Notably the existing vehicular access road was pushed North within the building footprint once the exiting building has been demolished. Block 8 was a live hospital and is accessed by staff only. During the works access needed to be maintained including the two fire escape routes adjacent. All these access and egress routes were maintained and adapted in line with progression of works. Hoarding, scaffolding signage and barriers was employed throughout.
The solution combined innovative architecture, advanced engineering and collaborative project delivery. Backed by £16 million UKRPIF funding, over £32 million of industry investment and £15 million from King’s College London, the building was designed to encourage interaction through open-plan workspaces, flexible lecture areas, specialist laboratories and collaboration zones. Extensive surveys, careful logistics planning and stakeholder engagement enabled construction within a live healthcare environment while supporting future MedTech innovation and commercialisation.
LIHE is a brand-new research and education facility for King’s College London bringing together the world’s leading MedTech organisations, multinational companies, SME’s, and startups. Situated within the heart of London’s MedTech hub, the four-storey flexible office accommodation will foster collaboration and innovation through its unique design tailored specifically for research staff. The adaptable workspace suits different working styles while a signature showcase staircase that stands at the centre of the building provides not only a unique design feature but encourages staff from all parts of the building to come together.
14 No of SMEs
33 beneficiaries, 10 jobs created, 388 trainee weeks
Schools’ engagement: 30 students
£2,700 donations to charity, 75 volunteer hours
1.48 LM3
55% social value created , Social value created – £13,679,621
99% waste diverted from landfill , 100% timber responsibly sourced
BREEAM Excellent
LIHE transformed a brownfield site into a modern healthcare innovation hub featuring green roofs, blue-roof rainwater attenuation, permeable landscaping, biodiversity enhancements and 150 covered cycle spaces. Sustainable construction included environmental monitoring, heritage protection and adaptable workspaces. The facility promotes long-term healthcare innovation, collaboration and societal value through over £63 million investment.
Zero RIDDORs
CCS Score 43/45
Took part in the Morgan Sindall Dropped Objects Campaign
100% payment within 30 days terms
Soft landings for handover
Dedicated Morgan Sindall point of contact
On-line portal for notifying any defects with 3 priority categories for response times
The Core project was delivered within one of the most complex construction environments in the UK healthcare sector.
Located on the operational St Thomas’ Hospital campus, adjacent to Evelina London Children’s Hospital and within the Albert Embankment Conservation Area, the project faced significant constraints relating to site access, logistics, stakeholder management and planning requirements.
The team was required to work safely within a live hospital environment whilst ensuring uninterrupted patient care, emergency access and day-to-day clinical operations.
The high-profile central London location, combined with the technical complexity of a modern healthcare facility, created additional challenges around construction sequencing, service diversions and programme management.
Morgan Sindall adopted a highly collaborative approach from the earliest stages of project development, working closely with Guy’s and St Thomas’ NHS Foundation Trust, Mace, ADP Architecture and specialist supply chain partners.
Comprehensive pre-construction surveys and detailed service investigations were undertaken to understand the existing hospital infrastructure and minimise risk during delivery.
Robust logistics and stakeholder engagement strategies ensured construction activities were carefully coordinated around hospital operations.
The building incorporated a range of specialist healthcare systems, including medical gases, operating theatre infrastructure, standby power generation, fire suppression systems, high-voltage electrical installations and integration with the Trust’s existing Building Management System.
The project was also designed to provide flexible, future-proofed accommodation capable of adapting to evolving clinical and educational requirements.
The successful completion of The Core has delivered a state-of-the-art five-storey facility that significantly enhances both healthcare provision and medical education at Guy’s and St Thomas’ NHS Foundation Trust.
The new development provides a dedicated children’s day surgery centre alongside high-quality teaching, training and staff development facilities, supporting the continued growth of Evelina London Children’s Hospital.
Delivered with minimal disruption to ongoing hospital services, the project has increased patient treatment capacity, improved the quality of the clinical environment and created a flexible asset that will support future healthcare needs.
The Core now forms a key part of the Trust’s long-term vision to provide world-class care for children, young people and their families while strengthening the development of the healthcare workforce of the future
The Core was designed as a flexible, future-ready healthcare and education facility that maximises estate efficiency while supporting evolving clinical needs. Sustainability is embedded through the use of a hybrid Combined Heat and Power (CHP) system, intelligent Building Management System (BMS) controls, energy-efficient lighting and modern chilled water infrastructure to optimise operational performance and reduce energy demand.
Delivered as a five-storey development within a live hospital environment, the project expanded clinical capacity through a dedicated Children’s Day Surgery Centre while minimising disruption to ongoing healthcare services. Early contractor involvement, detailed service investigations and collaborative delivery through the Southern Construction Framework reduced project risk, avoided unnecessary rework and supported efficient resource utilisation throughout construction.
The facility combines healthcare and medical education functions within a single building, creating long-term operational efficiency, supporting workforce development and providing adaptable, resilient infrastructure designed to meet future healthcare demands
Delivered within a live, operational hospital environment, requiring stringent controls to maintain uninterrupted patient care and emergency access throughout construction.
Extensive pre-construction surveys and service mapping were undertaken to identify critical infrastructure and reduce risks associated with working adjacent to active clinical facilities.
Detailed logistics and sequencing plans were implemented to safely manage deliveries, workforce movements and construction activities within a constrained city-centre site.
Installation of specialist life-safety systems, including fire suppression, sprinkler protection, smoke ventilation, standby power generation and essential electrical infrastructure.
Robust stakeholder engagement ensured safe separation between construction activities, hospital staff, patients and visitors.
Successfully completed with minimal disruption to ongoing hospital operations while maintaining the highest standards of health, safety and patient protection
Delivered 31 school and STEM engagement activities, investing over 302 hours to inspire young people and promote careers in construction and engineering.
Provided 14 work experience placements, 5 undergraduate placements and 6 mentoring opportunities, supporting education and employability outcomes
Created 11 new entrant jobs and delivered 879 apprentice training weeks, significantly exceeding project targets.
Contributed £5,457 in community investment and 288 volunteer hours, supporting local schools, charities, parks, foodbanks and Evelina Children’s Hospital.
Donated toys, books, PPE, furniture and community resources, creating lasting social value across Lambeth and the wider local community
Each package was carefully considered on its own merit and procured through a competitive tendering process, using LSCP.
Enquiries were issued to known companies and on a specialist level to protect quality.
Expectations regarding pricing, delivery, programme and payment terms were clearly communicated and this ensured trust was built from the start and minimised any misunderstanding. The team ensured that prices offered by suppliers were fair and competitive within the industry.
Payment terms negotiated ensured they that were fair to both parties and considered factors such as the supplier’s cash flow and the nature of the goods or services provided.
Following completion, The Core underwent a structured handover and commissioning process, including a dedicated medical fit-out period prior to becoming operational for patient care.
The project delivered a flexible, future-proofed facility supported by integrated Building Management Systems, enabling efficient operation, monitoring and maintenance throughout its lifecycle.
Ongoing stakeholder engagement with Guy’s and St Thomas’ NHS Foundation Trust ensured a smooth transition into use, while the resilient design and high-quality healthcare infrastructure provide long-term value, operational reliability and adaptability for future clinical requirements
The Thames Valley Police Forensic Services Centre is a new purpose-built facility delivered as part of the wider Thames Valley Police Improvement Programme. The centre has been designed to modernise forensic services, increase capacity, and enhance the speed and quality of evidence processing due to increasing demands.
Replacing outdated accommodation, the facility brings previously separate teams together under one roof. It includes digital forensics and crime scene investigation facilities, training areas, and office space to support up to 200 staff.
Although a completely new build, the force-owned site on Howes Lane was adjacent to the Thames Valley Police traffic base, which stayed operational throughout the project’s lifecycle.
It was essential that operational works from the live traffic base were not interrupted or hindered by our construction work, avoiding “blocking blue light access” at all times, a mandatory rule set out by the force ahead of commencement of works.
We created a site-specific layby for waiting vehicles, to prevent the blocking of blue light access.
Two banksmen were also stationed at the gate and access road, to manage vehicle movement.
Communication, openness and honesty were big factors to ensure the overcoming of this challenge presented to us and as such we were in constant communication with the traffic base with regards to our evolving site works and their operational changes.
As a result, our construction work had no effect on the traffic base fulfilling their duties.
This new Forensic Centre sets a benchmark for blue light facilities. Combining modern infrastructure and high-tech policing equipment, this purpose-built home for forensic services supports the vital works carried out by teams across Thames Valley Police and helps to meet future demands.
The new facility replaces outdated and delipidated spaces and brings together previously dispersed teams housing, modern laboratories, digital technologies and dedicated training facilities.
With it’s thoughtful design, this facility will not only futureproof the force and enhance training capabilities for new employees, but also ensure existing employee wellbeing and collaboration is maximised.
436 Training weeks onsite. Onsite T-Level placements x3 from local colleges and X3 local apprentices hired for the project, over 30 events took place for local young people including employability workshops and careers focused events.
99.42 total waste diverted from landfill
Scored 10/10 for the H&S procedures on site. Excellent management of supply chain RAMS
100% payment within 30 days terms
Soft landings approach. Satisfaction score of 10/10 for aftercare service
Navigating the logistics of site access posed a significant challenge from the outset for this ambitious project. The site area for the football pitch was bounded by a new housing development, secured through a joint planning application with Cala Homes. Galliford Try’s (GT’s) early works package required extensive use of their site entrance, requiring careful planning and coordination. Once works progressed to create the new pitch, the level difference between Cala’s access road and the site made it no longer usable, demanding a new strategy.
The job was further complicated by poor ground conditions resulting from a nearby river, requiring extensive investigation and remediation to create the necessary levels and compaction to alleviate soft spots. The groundworks alone accounted for a third of the overall contract, an extensive package for an education project of this size. The college needed to remain operational throughout construction.
GT held a pre-start meeting with Cala and NHC to discuss access arrangements followed by fortnightly updates and informal daily coordination with their groundworkers once on site. This ensured they remained effective and responsive to any changes, particularly when admitting crane deliveries to erect the steel frame. GT carefully planned and executed the groundworks through extensive surveys, silt traps to protect the adjoining river from contamination and careful assessment of excavated material to reuse as much as possible on site e.g. raising the pitch by 200mm.
Recognising the limitations posed by the evolving site conditions once the football pitch was underway, GT identified the most appropriate window in the build sequencing and worked with NHC to agree a safe alternative access route through their grounds. Deliveries were carefully coordinated to ensure safe segregation of the college users at all times.
The proactive measures taken to manage site access enabled effective collaboration between all parties and allowed the college to carry on as normal throughout the works with no complaints received. GT’s inventive groundworks solutions worked with the site’s topography to support maximum material retention on site whilst achieving the required strength. Extensive ground investigations drove the car park foundation design to mitigate the risks associated with the existing ground while eliminating the need for disruptive and costly piling. The surveys, Stage 4 design and pricing process were completed within just 10 weeks.
Project team supported 10 career events to highlight opportunities in construction, including Generation Hitchin for local 15-18 year olds (opened by Apprenticeships and Skills Minister, Alex Burghart) and a Building Heroes site tour for 7 military veterans.
Acting on guidance from the North Herts Bee Keeping Association, we protected a colony of 3,000 mining bees, crucial pollinators, by cordoning off their earth bank home on the site.
Successfully managed 100+ variations to the contract whilst remaining compliant with payment periods set out with suppliers.
An Aftercare Charter outlining the client’s preferred approach to aftercare was agreed in discussion with the College. NHC’s FM team were also invited to spend time with the commissioning engineers to undertake familiarisation training the week prior to handover.
Coordination of over 300 lorry deliveries via the shared access with Cala Homes and the College with zero RIDDORs.
Morgan Sindall team’s review of the initial Employer’s Requirements and MAC’s RIBA Stage 1 proposals identified several challenges. The initial MAC design did not fully satisfy the Employers Requirements (ERs), particularly regarding departmental adjacencies and the relationship between teaching, support and the amenity spaces. The existing Dining provision for sixth form students lacked flexibility for future growth so the design team considered an alternative approach.
Where the existing Wellbeing Hub was located adjacent to the Sixth Form Centre, the initial proposal was to temporarily adapt the existing Drama Halls within a separate part of the site to introduce temporary wellbeing facilities in place due to the reduced capacity and disrupted Wellbeing Hub assumed within the construction phase as well as temporary classroom hire to serve the required teaching capacity during the works.
Within the existing school a math classroom was to be converted to a science laboratory and had to be delivered all within a live environment. Adjacent to this classroom a proposal to relocate an existing washroom facility to the opposite side of the same corridor introduced significant implications for utilities, structural works and building alterations, which the design team questioned how this would add value. The team needed to improve functionality, safeguarding and student experience whilst ensuring the project remained affordable, buildable and operationally efficient. After careful evaluation through survey, optioneering and consultation with the client team on the priorities we realised these proposals created unnecessary cost, disruption, work complexity and programme risk.
Morgan Sindall took opportunity during the CEM process to present some alterative design proposals that considered to improve the adjacencies and lessen the disruptions for the school and worked closely with the client stakeholders and end user and identify more efficient solutions.
The Sixth Form Centre design layout was refined to improve departmental adjacencies and provide stronger connectivity between teaching spaces, student amenities and those support facilities. The Dining and study area was expanded to increase capacity it required and provide more flexibility for students.
The role of the existing Wellbeing Hub was also re-evaluated. The revised design approach helped with construction logistics and phasing plan improvements during operational phase, which helped to link and maintain the existing access routes particularly through construction and create a more supportive environment for those teaching and learning.
Within the existing school building, the maths classroom was successfully adapted to form a compliant science laboratory with minimal disruptions to the existing roof and building fabric within the live school environment. The washroom proposals were also rescoped to retain the existing location and internally reconfigured to improve passive supervision, visibility and safeguarding. This achieved the project’s objectives while avoiding extensive utility diversions, structural works and alterations to the building envelope.
The rescoping to the design proposals signed off within PCSA and CEM processes were delivering improved functionality, increased capacity and better value for money while minimising disruption to the school. Buckinghamshire Council and The Cottesloe School team commended the innovative approach by Morgan Sindall’s team and helped improve satisfaction across several measures.
Additional teaching, dining and study space was created within the Sixth Form Centre without introducing inefficiencies in layout or operation. This formed a geography department in one location and better relationship between learning, support and social spaces, which created a more effective environment for students and staff.
The Wellbeing Hub remained fully operational throughout construction, maintaining uninterrupted access to this resource. Revising the accommodation strategy also removed the need for Morgan Sindall to provide temporary classroom accommodation due to occupying school facilities realised could be avoided and incur unnecessary cost and programme impacts.
By retaining and reconfiguring the existing washroom in the existing school building, the project avoided costly and complex utility diversions and structural alteration, while still improving the washroom provision with better a safeguarding outcome.
The extension was meticulously designed to complement the existing Sixth Form Centre aesthetic, with colour-matched brickwork and mortar, matching roof tiles, windows and doors establishing a seamless appearance tied to the base building. Staff Car parking provision was increased, while landscaping works were minimised to retain mature trees and preserve the character of the site. The result was a cost-effective and highly functional development that met requirements and enhanced both the teacher and student experience.
Over the reporting period, we delivered 54 weeks of training and supported 13 community events, reaching over 500 students.
We also donated a total of £6,200 in the local community and dedicated 100 hours to delivering CV and employability workshops, helping individuals enhance their career readiness and job prospects.
Thermally efficient building as air tightness achieved of 2.
PV array was installed to the 6th form.
Carbonica assessment done to monitor embodied carbon.
Aftercare process shared and implemented with the client team in the run up to handover to ensure smooth handover from construction project team.
All payments were made as per the contract terms.
Payments from the client to the contractor were all on time or early.
Zero Hard and 0 Riddors
The University needed to create a world-class facility for engineering and design while working with an existing 1970s building. Rather than demolishing the building, the project team had to take it back to its structural frame and work within the constraints of the retained structure. The specialist equipment also presented significant coordination challenges: laboratories, clean rooms, precision manufacturing facilities, high-performance computing and a sub-sonic wind tunnel all had to be integrated into the building. The project was delivered alongside another major University redevelopment, InterCity Place, creating additional programme and resource pressures.
BAM transformed the existing Babbage Building, retaining its principal structural frame while adding significant new-build elements. The design integrated specialist research and teaching environments around the needs of the equipment they would contain, including slotted bed-plates, specialist laboratory services and the wind tunnel.
The approach enabled the University to retain the embodied carbon within the existing structure while delivering a building with a completely new architectural identity, improved accessibility, renewable technologies and modern teaching and research facilities. BAM worked collaboratively with the University’s Estates and Facilities team and the design team throughout the transformation.
The transformed Babbage Building opened to students in November 2023, with formal opening taking place in March 2024.
The completed facility provides more than 10,000m² of teaching and research space and now houses specialist engineering and design facilities including a wind tunnel, clean rooms and laboratories supporting energy and sustainability, autonomous systems, precision manufacturing, digital fabrication and immersive visualisation.
The project also provided a significant improvement to the University campus and student experience.
Re-use of existing 1970s structure; major embodied-carbon/waste savings; ASHP; PV; heat recovery; low-energy-in-use design.
Decarbonisation: Use of Electric Air Source Heat Pumps and installation of 140 Solar Photovoltaic panels providing 24% CO2 emissions saving. Retained structure, saving up to 1,700 tCO₂e of embodied carbon and achieves SCORS A+ rating and exceeded LETI & RIBA 2030 targets.
Building fabric upgrades, including significantly improved U-Values. EPC A Rating, 31% saving in regulated carbon emissions over Part L. Space heating demand designed to achieve 15/kWh/m2/yr. Circularity:
5100kg of waste saved and 5,415kg CO2e saved using Zentia takeback scheme. Climate adaption/Low water use: Low flush toilets and sensor taps
Handover to University; commissioning of specialist engineering facilities; FM/operational requirements
The university actively supported BAM initiatives on SV.
Supported and continue to engage with annual Construction Panel and associated events.
Jess Morgan ran online employability sessions for overseas students.
Live university campus; complex refurbishment/extension; demolition avoided; constrained site logistics; segregation and access management
Bath Quays South occupied a highly constrained riverside site surrounded by occupied buildings, listed heritage assets and the River Avon. The project had to respect Bath’s UNESCO World Heritage status while overcoming significant geotechnical challenges, flood risk requirements and strict controls protecting the city’s historic thermal springs. Limited site access, extensive underground obstructions and the need to deliver new flood defences alongside commercial development further increased the complexity of the scheme.
BAM delivered a carefully phased design and construction solution incorporating a five-storey Grade A office building founded on piled foundations, new flood defence infrastructure, riverside public realm improvements and enabling works for the new pedestrian bridge. Close collaboration with BANES Council, environmental stakeholders and the design team ensured protection of sensitive heritage features and thermal spring resources while creating a modern workplace environment that complements the historic cityscape.
The completed development has created a high-quality commercial destination at the heart of Bath’s Enterprise Zone, providing approximately 45,500 sq ft of Grade A office accommodation together with enhanced flood resilience, improved public realm and better connectivity across the River Avon. The scheme has helped establish a new business quarter designed to support economic growth, attract investment and create employment opportunities in the city.
EPC A / high energy performance; PV; EV charging; sustainable transport; cycle infrastructure; flood mitigation; public realm/ecology.
Decarbonisation: Solar PV, Electric Air Source Heat Pumps.
BAM provided post-completion support and handover services in line with project requirements and client expectations.
Held online education programme during COVID
Urban construction environment; public interface; pedestrian/cycle routes; traffic and logistics management
The existing school required replacement while the site continued to serve the local community. The project therefore needed to be phased so that new accommodation could be provided before the existing buildings were demolished. The scheme also had to deliver a high-performance Passivhaus building within a constrained existing school site, while managing construction traffic, pedestrian movements and the interface with pupils, staff, parents and neighbours. A particularly important challenge was managing people/plant segregation safely within the active construction environment.
BAM delivered the new school in phases, enabling the new accommodation to become operational before demolition and completion of the wider site. The building was constructed to Passivhaus standards, incorporating high-performance insulation, efficient windows and ventilation, air-source heat pumps and solar PV. BAM also worked collaboratively with FHOSS to develop and implement an illuminated pedestrian/plant crossing system specifically for the project. The solution removed reliance on a dedicated banksman at the crossing point and created a visible, fail-safe system for controlling interaction between pedestrians and construction plant.
The project delivered a new 210-place Passivhaus primary school with community facilities and improved outdoor spaces. South Gloucestershire Council subsequently recorded the completion of Elm Park Primary School as a key achievement in its 2023/24 capital programme.
The innovative FHOSS safety system won a Constructing Excellence South West 2023 Health, Safety & Wellbeing award, providing independent recognition of BAM’s collaborative approach to improving construction-site safety.
Passivhaus construction, high-performance insulation, efficient ventilation, air-source heat pumps and solar PV.
Decarbonisation: EPC A, DEC B rating
Kurt Williams, Handover to South Gloucestershire Council; Passivhaus performance/commissioning; operational guidance and building performance
BAM delivered on SV goals – CCS 45 Silver Award. Women in Construction focus, STEM programme delivered with female pupils.
Payment periods not exceeding 30 days
Innovative FHOSS illuminated pedestrian/plant crossing; Constructing Excellence South West Health, Safety & Wellbeing award.
The project needed to replace an existing school while responding to rapidly increasing demand for school places in the local area. It was also one of South Gloucestershire Council’s flagship responses to its Climate Emergency, requiring BAM to deliver a highly energy-efficient building while maintaining rigorous Passivhaus quality requirements. The project was constructed on the former Frenchay Hospital site and required careful consideration of the surrounding woodland and local community.
BAM used its experience in Passivhaus education projects to deliver a high-performance timber-framed building with triple glazing, high levels of insulation, air-source heat pumps, MVHR and photovoltaic panels. Digital modelling and 4D planning were used to support delivery. The project team also engaged with the school community, including visits from pupils during construction, helping children understand how the building was being created and the principles behind its environmental performance.
BAM and the project team also worked with the local Frenchay Residents’ Association to improve a nearby pond and picnic area as a community legacy initiative.
The new school opened in September 2022, providing capacity for 420 pupils in a modern, low-carbon learning environment.
The project became South Gloucestershire’s first Passivhaus school and provides a strong demonstration of BAM’s ability to combine educational requirements, sustainability and high-performance construction
Passivhaus; triple glazing; high insulation; air-source heat pumps; MVHR; solar PV; zero fossil-fuel consumption.
Decarbonisation: EPC A rating, DEC B rating
Passivhaus commissioning, certification and handover; user/operational considerations
Pupil site visits and community pond/picnic-area improvement.
Worked closely with SEETEC to support programme to support with employability skills post – COVID.
Safe construction alongside developing residential/community area; logistics and construction sequencing; Passivhaus quality/airtightness controls