Archives

Stanhope Primary School

  • Client

    Hampshire County Council

  • Contractor

  • Value

    £10.3m 

  • Completion Date

    August 2025 

The Challenge

The project required the selection of a structural frame that aligned with HCC’s fabric-first principles, prioritising energy efficiency through a high-performing building envelope. Unique to other panel systems, the Streif timber frame solution comprises fully made cassette, complete with pre-installed doors and windows and M&E systems pre-measured and cut-out. As a result, it was critical to finalise and coordinate these details from the outset, so the timber frame could be manufactured and dispatched on time to meet key programme milestones and meet the school’s readiness for the September 2025 term.  

 

The Solution

In-line with the fabric-first design intent, the Streif panelised timber frame solution was selected for its advantages over traditional construction methods, including improved U-values, reduced embodied carbon and quicker watertightness; while leveraging experience from previous Streif projects. Seamless coordination with the supply chain was critical to maintaining the programme. Numerous coordination meetings were executed with MEP, stairs and groundwork specialists, ensuring designs were fully integrated, enabling efficient manufacture and on-time delivery. This meticulous planning enabled a seamless ‘soft landings’ approach with FF&E and IT specialists, guaranteeing the school was fully operational for the new term start.



The Results

Championing the ‘fabric first’ design philosophy, the Streif system resulted in exceptional environmental performance with an air test rating of 1.16m3/(h.m2)@50Pa and near-Net Zero status of 205CO2. The proactive approach also ensured timely delivery of the timber frame; subsequently meeting key deadline dates.  

12


Apprentices

82.2%


SME Spend

£1,157, 163


Added Value

9/10


Client Satisfaction

Client Testimonials

“The project site team were consistently collaborative and transparent, and communicated well with the HCC design team and the school. While the project presented some challenges, there was a strong commitment to hold meetings and workshops with all relevant stakeholders to agree solutions and determine the best way forward.” 

Contractor Performance | Commitments


Legacy

12 apprentices, 37 SMEs , 27 beneficiaries, 6 jobs created 

108 trainee weeks and 2,722 students engaged 

£9,000 donations to charity 

39% social value created 

Community Quad – 2,574 hours  


Sustainability

100% timber responsibly sourced and waste diverted from landfill 

226kg/ 100k carbon footprint (against target of 454kg) 

30.6 tonnes CO2e saved in MSC 10 Tonne Carbon Challenge (embodied carbon) 

17 tonnes of CO2e saved from emissions (Scopes 1,2 and 3) 

Waste reduction with 0.71 tonnes per £100k spend, outperforming the national target of 1.28 


Aftercare

Soft landings for handover 

Dedicated Morgan Sindall point of contact 

On-line portal for notifying any defects with 3 priority categories for response times 


Fair

100% payment within 30 days terms  


Safe

Zero RIDDORs 

CCS Score 45/45 

CCS Bronze Award 

Liskeard Hub, Cornwall Council

  • Client

    Cornwall Council

  • Contractor

  • Value

    £11m 

  • Completion Date

    May 2026


The Challenge

The Liskeard Hub project faced several strategic and operational challenges. Cornwall Council needed to replace multiple ageing buildings, including Luxstowe House, Graylands, Laity House and Westbourne House, which were becoming increasingly inefficient and costly to operate. Delivering services from several separate locations created inconvenience for residents, duplication of facilities and higher maintenance costs. The project also had to support the wider regeneration of the former Cattle Market site while maintaining access to essential public services during the transition period. In addition, the Council sought to improve environmental performance, reduce its property footprint and create a facility capable of accommodating a diverse range of services and stakeholders. Achieving all these objectives within a constrained town-centre site added further complexity to the design and delivery process. 

 


The Solution

To address these challenges, Cornwall Council developed the Integrated Services Hub concept, bringing a wide range of public services together within a single modern facility. The hub was designed to co-locate services including the Family Hub, Registrars, Adult Education, Adult Day Care, Safe and Well services and the Department for Work and Pensions. The new building provides flexible accommodation, shared office space and meeting facilities that support collaboration between different service providers. Locating the hub on the former Cattle Market site aligns the project with broader town-centre regeneration objectives while improving accessibility for residents. Consolidating services into one purpose-built building reduces duplication of accommodation, enables more efficient use of resources and supports the Council’s ambition to lower operational costs and reduce the environmental impact of its estate. 


The Results

The Liskeard Hub is expected to deliver significant long-term benefits for Cornwall Council, service users and the local community. By replacing four separate buildings with one integrated facility, the Council will achieve more efficient property management, lower running costs and reduced environmental impacts. Residents will benefit from simplified access to multiple services within a single location, creating a more convenient and customer-focused experience. The hub will also strengthen collaboration between public service providers through shared facilities and co-location. Beyond operational improvements, the project acts as a catalyst for the wider regeneration of the former Cattle Market site, helping revitalise a key town-centre area and encouraging greater economic and community activity. The development demonstrates a modern approach to public service delivery that combines efficiency, accessibility and sustainability. 

2


Apprentices

81.4%


SME Spend

£148,500


Added Value

10/10


Client Satisfaction

Client Testimonials

“The financial investment from Cornwall Council to develop the redundant Cattle Market site is welcome and confirms their confidence in the future growth of the town.” 

“This project will revolutionise the support that Cornwall Council can offer its local people.”

Contractor Performance | Commitments


Fair

promoting 2 stage open book through transparent and collaborative commercial practices. 

Procured and managed a supply chain comprising 32 businesses, including 31 SMEs. 

Achieved 81.4% SME spend, supporting fair opportunities for smaller businesses. 

Directed £7.27m of project expenditure to SME organisations. 

Generated £5.24m spend within the contracting authority area. 

Maintained collaborative relationships with local suppliers and specialist subcontractors. 

Adopted structured package procurement and transparent subcontract engagement. 

Supported local economic growth through early supply-chain involvement. 

Encouraged long-term supplier participation through framework delivery principles. 

Demonstrated responsible payment practices that helped sustain regional businesses throughout project delivery. 


Aftercare

Government Soft Landings principles embedded to ensure smooth transition from construction to operation. 

Early engagement with service/end users and Cornwall Council operational teams informed building delivery. 

Facilities designed to provide flexible, long-term accommodation for evolving public services. 

Building performance and operational efficiency considered throughout design and construction. 

Shared office and meeting facilities support efficient occupation from day one. 

Sustainable CarbonLite design supports lower running costs and improved building performance. 

Seasonal comprehensive commissioning, training and operational readiness activities support successful handover. 

Long-term aftercare focus ensures the hub delivers lasting value, efficiency and community benefits. 


Safe

Achieved an overall Green Health & Safety status throughout project reporting. 

Zero Harm / RIDDOR’s 

Utilities diversions completed safely ahead of main works. 

Major asbestos risk identified early and managed through specialist investigation and removal strategies. 

Risk & Opportunity management strategy agreed collaboratively with Cornwall Council and project partners. 

Community safety managed through revised pedestrian access and boundary arrangements. 

Strong focus on compliance, planning, coordination and proactive hazard mitigation throughout delivery. 


Sustainability

Designed to CarbonLite standards, reducing embodied and operational carbon. 

Achieved the CarboniCa 10 Tonne Challenge during pre-construction. 

Targeting 200 tonnes CO₂e savings through carbon reduction measures. 

Adopted diesel-free construction practices and lower-carbon fuels. 

Diverted over 99.6% of construction waste from landfill. 

Managed 4,027 tonnes of waste with only 14.9 tonnes landfilled. 

Delivered 267 hours of Green Skills training. 

Contributed 386 volunteering hours to community initiatives. 

Achieved an excellent Considerate Constructors Scheme score of 43/45. 


Legacy

Regenerated the former Liskeard Cattle Market site, bringing a key brownfield location back into productive use. 

Consolidated four outdated council buildings into one modern community asset. 

Created a long-term home for essential public services. 

Improved accessibility to Family Hub, DWP, Adult Education and Registrar services. 

Generated £6.26m of local supply-chain spend. 

Supported 31 SME businesses across the project. 

Delivered 386 community volunteering hours. 

Invested 267 hours in Green Skills training. 

Strengthened town-centre footfall and regeneration opportunities. 

Burlington Primary School

  • Client

    Royal Borough of Kingston Upon Thames  

  • Contractor

  • Value

    £27.8m

  • Completion Date

    Oct 2025


The Challenge

The Burlington Primary School redevelopment presented several unusual challenges. The project required the replacement of an ageing 1970s CLASP system building while maintaining a fully operational school campus throughout construction. Careful phasing was essential to ensure pupil safety, minimise disruption to teaching, and maintain access across the site. The scheme also needed to integrate a new contemporary building alongside a retained Victorian school building, balancing modern educational requirements with heritage considerations. In addition, the borough required increased pupil capacity to address future demand for school places, while achieving ambitious sustainability targets and delivering extensive external works, including sports facilities, landscaping and improved infrastructure within a constrained live school environment 

 


The Solution

To address these challenges, the project team adopted a carefully phased construction strategy that allowed teaching activities to continue safely throughout the programme. A new 2,800m² three-storey teaching block was constructed before the redundant CLASP building was demolished, ensuring continuity of school operations. The design combined refurbishment of the Victorian building with modern educational facilities, creating a cohesive campus. Sustainability measures included the installation of 72 photovoltaic panels, the use of low-carbon hempcrete insulation, energy-efficient building systems and a BREEAM Excellent design approach. The project also introduced two Multi-Use Games Areas (MUGAs), enhanced landscaping, upgraded infant school facilities and a new shared car park to maximise community and educational benefits. 


The Results

The completed redevelopment has delivered a future-ready educational environment that significantly improves learning, wellbeing and operational efficiency. The school gained 120 additional pupil places, helping meet increasing local demand while providing 15 modern teaching spaces, a sports hall and collaborative learning areas centred around a striking three-storey atrium. Sustainability outcomes were equally impressive, with 98% of construction waste recycled and zero waste sent to landfill. Renewable energy generation from rooftop solar panels supports lower operational carbon emissions, while the use of innovative materials reduced embodied carbon. The project successfully combines heritage refurbishment, modern educational design and environmental excellence, creating a high-quality asset for pupils, staff and the wider New Malden community 

11


Apprentices

81.1%


SME Spend

£3,559,850


Added Value

9/10


Client Satisfaction

Client Testimonials

“Supporting children and young people to have the best possible start in life is a top priority for us at Kingston Council, and providing excellent facilities for that to take place is very important. This is an exciting time for the school, and I hope that students and staff alike flourish in ”

“It’s been a real privilege to work alongside the Royal Borough of Kingston upon Thames, the Burlington Junior School team, and of course the wider Burlington community on this project.” their new spaces.”

Contractor Performance | Commitments


Aftercare

Delivered a carefully phased programme that enabled the school to remain fully operational throughout construction, ensuring a smooth transition into the new facilities with minimal disruption to teaching and learning.  

Refurbished the retained Victorian building alongside the new teaching block, preserving existing assets and extending their long-term value in line with Government Soft Landings principles.  

Engaged extensively with school staff, governors and stakeholders throughout design and construction, ensuring the completed facilities met user needs and operational requirements.  

Delivered training, site familiarisation visits and educational engagement activities to support users before and after occupation.

Achieved a BREEAM Excellent building with low-maintenance, energy-efficient systems designed to reduce operational costs and support long-term performance monitoring.  

Continued support after handover through community investment, additional school improvements, donated equipment, landscaping enhancements and maintenance activities valued at over £22,000.  

Successfully delivered facilities that increased capacity from 480 to 600 pupils, ensuring the school remains fit for future educational demand.  

 


Safe

Zero RIDDOR reportable accidents recorded throughout the project, demonstrating excellent health and safety performance over 198,224 operative hours worked.  

Achieved outstanding Considerate Constructors Scheme (CCS) scores of 45/45.  

Delivered 255 toolbox talks and 23 safety stand-downs to reinforce safe working practices and Conducted 35 senior management site safety visits to maintain strong leadership and oversight.  

Implemented rigorous safety controls to enable construction within a live operational school environment with minimal disruption to pupils and staff.  

Delivered community safety initiatives, including CLOCS traffic marshal training and school engagement activities focused on construction safety awareness.  

Supported workforce wellbeing through mental health campaigns, wellbeing initiatives and on-site health support services. 


Sustainability

Achieved BREEAM Excellent standard for sustainable building design and operation.  

Installed 72 solar PV panels to generate renewable energy and reduce operational carbon emissions.  

Utilised hempcrete insulation, a low-carbon bio-based construction material.  

Recycled 98% of construction waste with zero waste sent to landfill  

Delivered a Gold Carbon Management Plan, Gold Air Quality Plan, and Silver Biodiversity Legacy Plan.  

Enhanced the site through landscaping, biodiversity improvements and sustainable procurement initiatives.  

Achieved a perfect 45/45 Considerate Constructors Scheme score, recognising excellence in environmental management and workforce welfare. 


Legacy

16 work experience placements (target: 15)  

12 workless job starts  

1,167 students engaged through educational and STEM activities  

116 school engagement hours delivered 


Fair 

Commitment to the Fair Payment Charter with prompt & transparent payment

Engaged 26 SMEs throughout construction.  

Supported responsible procurement through local supply chain portal engagement and opportunities for regional businesses.  

Achieved a Growth and Responsible Regional Business score of 9/10 within the SCF Social Legacy framework.

Woolwich Leisure Centre

  • Client

    Royal Borough of Greenwich 

  • Contractor

  • Value

     £82m

  • Completion Date

    Dec 2025


The Challenge

The delivery of The Wave presented a series of complex design, construction and stakeholder challenges. The project required the creation of a modern, multi-purpose leisure destination capable of serving a diverse range of users, including competitive athletes, fitness enthusiasts, families, children, older residents and people with disabilities. The design needed to successfully integrate swimming pools, fitness facilities, sports spaces, wellness amenities and community areas within a single building while maintaining intuitive navigation and an inclusive user experience.

From a stakeholder perspective, the project was replacing the much-loved former Waterfront Leisure Centre, creating high public expectations around retaining popular facilities while delivering a significantly enhanced offer. Construction was further complicated by the scale of the £82 million development, specialist engineering requirements and its location within a busy town centre regeneration programme close to major transport hubs. Sustainability targets added further complexity, with the facility required to achieve exceptional environmental performance despite the energy-intensive nature of leisure and aquatic facilities. 

The Solution

The project team adopted an integrated design and construction approach to address the technical, operational and community challenges. A carefully planned facility mix was developed, including a 25-metre eight-lane competition pool, leisure pool with flumes, training pool, two-storey gym, fitness studios, spa facilities, sports hall, squash courts, indoor football pitch, soft play areas and community spaces. This diverse provision ensured broad appeal and long-term usability for all sections of the community.  

  To maintain continuity with the former leisure centre, popular family-focused attractions, including water slides and leisure water facilities, were incorporated into the new design. Accessibility was embedded throughout through the inclusion of Changing Places facilities, accessible changing rooms, specialist pool access equipment and inclusive circulation routes. Construction activities were carefully coordinated with the wider regeneration programme to minimise disruption in a busy urban environment. Sustainability objectives were achieved through innovative solutions including one of the UK’s largest air source heat pump arrays, rooftop solar panels, green roof systems and a stacked multi-storey design that maximised a constrained town-centre site. 


The Results

The completed Woolwich Waves leisure centre has become a landmark community asset that delivers significant social, environmental and economic benefits for the Royal Borough of Greenwich. The 12,800m² facility provides some of the most comprehensive leisure, fitness and wellbeing amenities in the region, creating opportunities for healthier lifestyles, increased physical activity and greater community participation. The centre has also become a key catalyst within the wider Woolwich regeneration programme, encouraging investment and supporting local economic growth. 

 Construction performance was equally impressive, achieving zero RIDDOR incidents across more than 600,000 working hours, a perfect 45/45 Considerate Constructors Scheme score and 100% waste diversion from landfill. Sustainability outcomes include achieving BREEAM Outstanding at design stage, establishing a low-carbon energy network and creating infrastructure capable of supplying sustainable heat to neighbouring community assets and more than 500 future homes. Community legacy benefits included 39 apprenticeships, 31 jobs created, over 770 students engaged in education initiatives and £12.6 million of added social value 

39


Apprentices

72.4%


SME Spend

£12.6m


Added Value

9/10


Client Satisfaction

Client Testimonials

“It’s not just an exemplar leisure centre any city would be proud to have… Woolwich Waves will be at the forefront of improving the quality of life and health of our residents.”

“Woolwich Waves represents exactly the kind of community facility that Sport England is committed to supporting. It will help to break down barriers to activity, bring communities together, and create opportunities for people of all ages to lead healthier, more active lives.” 

Contractor Performance | Commitments


Sustainability

Achieved (or is on track to achieve) BREEAM Outstanding, one of the highest sustainability ratings available, making it only the second leisure centre in the UK to reach this standard.  

Features one of the UK’s largest Air Source Heat Pump (ASHP) arrays, providing low-carbon heating for the leisure centre.  

The ASHP-fed energy centre also supplies sustainable heat to the neighbouring Tramshed Theatre and community arts hub, reducing overall carbon emissions across the wider development.  

Designed to become the heat source for more than 500 new homes being developed nearby, creating a community-scale low-carbon energy network.  

Incorporates a substantial planted green roof, improving biodiversity, supporting rainwater attenuation, and helping to reduce the urban heat island effect.  

Adopted an innovative stacked, multi-storey design to maximise the use of a constrained urban site, reducing land take while delivering a large leisure facility in the town centre.  Sustainability was embedded throughout the design, construction and operational phases, forming a core project objective from inception.  

The facility forms part of the wider Woolwich regeneration programme, combining health, community and environmental benefits within a sustainable urban development.  

Designed to support active, healthy lifestyles for residents, contributing to the social sustainability and wellbeing objectives of the Royal Borough of Greenwich.  

Achieved BREEAM Outstanding at design stage, demonstrating exceptional environmental performance alongside strong social value outcomes 


Legacy

Generated 31 jobs, 39 apprenticeships and 40 work experience placements and engaged 770+ students through careers STEM initiatives and Developed a Knowledge Quad training hub.

Established a low-carbon energy network benefiting the leisure centre, neighbouring facilities and future homes 


Safe

Achieved zero RIDDOR reportable accidents throughout construction, demonstrating exemplary health and safety management across a complex £80m leisure centre project.   

Delivered over 600,000 person-hours of work while maintaining strong safety performance and workforce engagement.  


Fair

100% payment within 30 days terms 

Collaborative two-stage procurement 

Open-book cost planning  and early supply-chain engagement 


Aftercare

Deployed Government Soft landings for handover 

Digital handover providing a single source of truth with QA records 

Drawings and asset information 

 

Acklam Road

  • Client

     Royal Borough of Kensington and Chelsea

  • Contractor

  • Value

    £20m

  • Completion Date

    June 2023


The Challenge

Proximity to Infrastructure: The plot sat a mere 3.5 meters away from the elevated Westway (A40 dual carriageway) and was bounded tightly by nearby railway lines. This caused massive acoustic disruption, high levels of traffic pollution, and complex structural foundation concerns. 

Post-Grenfell Safety Imperative: Located in North Kensington, the project carried immense emotional and civic responsibility following the Grenfell Tower tragedy. The building demanded the absolute highest tier of structural fire safety and evacuation compliance. 

Tight Brownfield Footprint: The plot was narrow, highly restricted, and left very little room for standard resident green spaces, play areas, or construction staging. 

 


The Solution

To overcome these barriers, RBKC teamed up with project manager Arcadis, architect PRP, delivery architect HNW Architects, and contractor Morgan Sindall Construction to execute targeted technical interventions: 

Environmental Buffer Engineering: Dual-aspect wide frontages were incorporated alongside fully enclosed winter gardens (indoor-outdoor hybrid rooms). These acted as physical acoustic and pollution shields against the Westway highway. 

Ground Movement Assessments: Engineers produced rigorous ground movement evaluations to get approvals from Transport for London (TfL), ensuring construction wouldn’t compromise the existing Westway highway foundations. 

Advanced Fire Safety Infrastructure: The building was upgraded far past standard regulation, integrating a commercial-grade sprinkler system, early smoke detection/evacuation alerts, a dry riser, two standalone emergency staircases, and two dedicated evacuation lifts. 

Imaginative Amenity Design: Because ground space was limited, architects designed a third-floor raised podium garden. This provided seating, soft landscaping, and a secure children’s play area isolated from traffic. 

Co-Design and Contextual Architecture: The building’s intricate, textured brickwork was explicitly designed to mirror the patterns of the adjacent Al-Manaar Muslim Cultural Heritage Centre. Local groups—including the Swinbrook Residents’ Association—directly co-designed the layout of the new community facilities 


The Results

Acklam Road successfully set a new benchmark for municipal urban regeneration: 

High-Quality Housing Stock: Delivered 32 new homes, comprising an inclusive blend of 20 social rent units and 12 market rent flats. 

Fully Accessible Living: Integrated four purpose-built, fully accessible wheelchair homes within the social housing allocation. 

Tenure-Blind Inclusivity: All residents access the building through a singular, high-quality tenure-blind lobby, removing the social segregation of traditional developments. 

Vibrant Social Infrastructure: Successfully handed over two newly constructed ground-floor community spaces. One serves as a replacement hub for the Swinbrook Estate, and the other expands youth and community programming run by the Al-Manaar Centre. 

Eco-Efficiency: Reached a “fabric-first” energy rating using air-source heat pumps and thermally efficient windows, driving down utility costs for council tenants. 

Industry Recognition: The project’s success earned it a prestigious shortlisting for Affordable Housing at the British Homes Awards. 

8


Apprentices

70.2%


SME Spend

£4.9m


Added Value

9/10


Client Satisfaction

Client Testimonials

“As the lead member for housing, I’m pleased to be taking on the new homes programme from Cllr Taylor-Smith, my predecessor, who has spearheaded the programme. Acklam Road is a beautifully designed scheme with such attention to detail. All of the homes are of a high spec, and the brickwork intentionally mirrors that of the Al Mannar Cultural Heritage Centre opposite so is in keeping with the local area.”

Contractor Performance | Commitments


Legacy

Inclusive Mixed-Tenure Housing: Promotes a balanced community by integrating 20 social rent homes and 12 market rent homes.  

Tenure-Blind Design: All residents share a high-quality main entrance lobby, ensuring an equitable standard of living regardless of tenure.  

Universal Accessibility: Includes four fully adapted, accessible wheelchair homes.  

Community-Led Spaces: Ground-floor units were co-designed with local stakeholders. They offer a replacement hub for the Swinbrook Estate Residents’ Association and an expanded facility for the adjacent  

Third-Floor Podium Garden: Maximizes space on a tight brownfield site. It features soft landscaping, casual seating, and play zones for young children to boost biodiversity and resident wellbeing. 

Borough-Wide Bee Superhighway Integration: Works alongside the local. The broader Acklam Road area utilizes pocket parks, vertical climbers, and pollinator-friendly marsh plants to clean localized air and support urban wildlife 


Sustainability

Fabric-First Approach: High-performance insulation and thermally efficient doors and windows significantly lower heating demand. 

Fossil Fuel Elimination: Individual low-carbon air-source heat pumps power the heating and hot water systems across all apartments.  

Innovative Acoustic & Air Mitigation: Located just 3.5 meters from the elevated Westway (A40) dual carriageway. Smart structural design protects residents from extreme roadside noise and air pollution.  

Enclosed Winter Gardens: Every home features a fully glazed, versatile indoor-outdoor winter garden. These serve as thermal buffers to retain heat while offering acoustic insulation.  

Durable, Low-Carbon Envelope: The distinctive brick exterior was chosen for extended lifespans, low-maintenance requirements, and reduced embodied carbon. 


Aftercare

Soft landings for handover  

Dedicated Morgan Sindall point of contact 

Awards  

LABC Awards 2025 – Best Small Social Housing Regional Winner.  

Inside Housing Development Awards 2024 – Best Affordable Housing Development (Under £20m) Winner. 

Property Week RESI Awards 2025 – Outstanding Residential Design Finalist. 


Fair

Fair payment Charter and its principles underpinned delivery through transparent, open-book processes, prompt payment within 30 days, aligned cash flow across the supply chain, proportionate retention practices, and collaborative contract management, supporting a resilient, sustainable and trusted project environment


Safe

0 RIDDOR reportable incidents recorded during the reporting month. 

0 accidents/incidents recorded during the reporting month. 

0 HSE, Environment Agency or Environmental Health visits during the month. 

0 learning events and 0 positive intervention cards recorded during the month. 

7 Toolbox Talks delivered in the month, attended by 31 operatives (2 direct employees and 29 subcontractors) 

Hounsome Fields Primary School

  • Client

    Hampshire County Council   

  • Contractor

  • Value

    £11.7m 

  • Completion Date

    August 2025


The Challenge

Hampshire County Council committed to providing new schools in areas with significant housing growth and population increases. One of these new schools was required to meet the anticipated demand for primary school places arising from the approximately 1,750 new homes to be built in the residential developments at Hounsome Fields and the adjacent Basingstoke Golf Course on the southwest of Basingstoke. 

Hounsome Fields Primary School needed to accommodate 2 forms of entry, providing primary education for up to 420 children aged between 4 and 11 years old, together with a resource provision for 8 pupils with special educational needs. The selected school site is approximately 3.0 hectares of previous farmland and will be sufficient to accommodate an expansion of the school by a further form of entry (210 pupils) if necessary, in the future. 

The project included the construction of the school building, car parking, external play areas and playing fields and the in-house property team at Hampshire County Council designed the facilities with energy efficiency and modern construction techniques in mind, prioritising the learning experience of pupils.

The Solution

Hounsome Fields Primary School is one of the first schools to be built to Passivhaus Classic standard in Hampshire.  

The two-storey school features a shaded loggia, a single-storey canopy for outdoor play, and an off-site timber frame to reduce embodied carbon. It is finished with brick, triple-glazed windows. The school building comprises: of a main hall, studio, 14 classrooms, a classroom for pupils with special educational needs and disabilities, a specialist practical classroom, group rooms, a learning resource centre, staffroom and administration offices, pupil and staff toilets, accessible toilets and a hygiene room, kitchen and other ancillary support facilities. 

The school’s exterior includes play courts and dedicated play areas for different age groups, a pedestrian entrance, two grassed playing fields, soft landscaping with trees, an all-weather path around the fields, car parking, service access, and covered bike and scooter storage. 

The project was adopted as a Climate Change Primary School Pilot project, aiming to achieve zero on-site carbon emissions with all-electric heating and solar power, low embodied carbon meeting the RIBA 2030 Challenge, and enhanced resilience to future overheating and flooding. 



The Results

Hounsome Fields Primary School is the first “Standard Primary School” model by Hampshire County Council targeting Passivhaus Classic certification (pending). The two-storey building, designed for energy efficiency and sustainability, excellent thermal comfort and air quality, creating a healthy, low-carbon learning environment for pupils and staff. 

To meet the heat and energy objectives behind the Climate Change Primary School Pilot, the design and construction of Hounsome Fields incorporates a ground-source heat pump, rooftop solar panels, and a highly insulated, airtight Passivhaus-standard building envelope with triple glazing and MVHR ventilation. Energy-efficient lighting and heating controls are used, and post-occupancy monitoring evaluates the building’s actual energy performance. 

The building reduces embodied carbon by using a sustainably sourced timber frame and low-carbon concrete, targeting 540 kgCO₂e/m², with a site waste management plan to minimize construction waste. 

It is oriented east–west with shading and special glazing to keep it cool and reduce glare. Night-time ventilation helps lower indoor temperatures in summer. The main play area is placed away from the sun and shaded by trees. Water-saving fixtures are used, a drainage swale manages rainwater, and landscaping boosts biodiversity. 

9


Apprentice training weeks

84.43%


SME Spend

203,000


Added Value

7/10


Client Satisfaction

Contractor Performance | Commitments


Legacy

230 training weeks : 26 Careers events and workshops : 30 weeks wex for supported Internship : x1 building lives academy : 41 workers within 10 miles : 89 workers with 20 miles


Sustainability

100% waste diverted from landfill


Safe

Zero RIDDORS 


Fair

100% payment within 30 days terms


Aftercare

Soft landings for handover 

CMA Fit Out

  • Client

    Confidential Client

  • Contractor

  • Value

    £26.6m

  • Completion Date

    March 2020


The Challenge

The design and fit out to Cat B from shell and floor including the design, supply and installation of furniture requirements, AV, room booking installation, access control, CCTV and security installations to provide all accommodation and functional areas to achieve the client brief. Approximately 113,000 ft sq of employee and public-facing space within newly leased office premises across three main floors (7, 8 and 9) with a new interconnecting staircase, plus additional back of house areas to two further floors (Ground and Mezzanine).  

The project was tendered based on a complete stage 1 design however, upon appointment, there was only a limited design brief. Overrunning programme on the basebuild (by others) resulted in delays of varying lengths on all floors to works commencing.  

The Solution

Overbury, along with Architect TP Bennett, developed the design brief working closely with the client through all stages, using engagement sessions with the workplace champions to understand the intended building use and circulation.  Multiple presentations were given to client user groups at each design stage. Recommendations from a Leesman Report undertaken at the client’s previous office space were also incorporated into the final design solutions.  

 The team assisted the client with proactive advice on how best to mitigate and deal with the delays to the base build, monitoring quality and programme. This became almost a full-time role for the Overbury project manager. This high level of collaboration engendered reciprocal trust that continued throughout the building fit out.  


The Results

The completed project achieved a BREEAM Excellent rating, the WELL Building standard, and a score of over 70 on the Leesman Survey, putting it in the top 5% globally of the survey.  


188 Weeks


Apprentices

78.2%


SME Spend

£1,056k


Added Value

9.2/10


Client Satisfaction

Client Testimonials

“I want to thank the team as they were patient with the landlord issues and I appreciate that!”

“It was a fully collaborative experience and Overbury were very much a part of the team. Nothing was too much trouble and there was always a solution from everyone”

Contractor Performance | Commitments


Sustainability

97% waste diverted from landfill 

100% timber responsibly sourced 


Fair

100% payment within 30 days terms


Safe

Zero RIDDORs 

CCS Score 39/50 


Aftercare

Soft landings for handover 

Dedicated Morgan Sindall point of contact – Senior Project Manager, Graham Holland 

On-line portal for notifying any defects with 3 priority categories for response times. Once reported, defects were logged on Project+ to track and close out.  


Legacy

31 No of SMEs   

7 jobs created 

363 trainee weeks 

Schools engagement: 4 events 

Pembroke Road Office Refurbishment

  • Client

    Royal Borough of Kensington and Chelsea

  • Contractor

  • Value

    £9.9m

  • Completion Date

    July 2023



The Challenge

RBKC undertook these works to upgrade their existing office space, reshaping the floor plan layout to suit the new needs of the space. 

The building remained occupied throughout the project, with RBKC staff continuing to use the building, requiring a phased programme, and residential dwellings above the plant deck area on the upper floors. Therefore planning, communication and minimising disruption were key focuses throughout the project. Positive feedback was received from the residents at the end of the project demonstrating how well this was managed as a team.  

The Solution

RBKC undertook these works to upgrade their existing office space, reshaping the floor plan layout to suit the new needs of the space.

We replaced many features throughout this project including the: Service plant Toilets, Tea points, Building management systems, Air conditioning systems, Doors  Refurbishment of existing fire-rated doors, Improved compartmentation, Radiators 

Mechanical services transitioned from Gas to electricity and public health services were segregated from the residents’ systems. 



The Results

RBKC also upgraded all their fire safety doors. By upgrading the services and newly installed BMS, the building became more efficient and user-friendly to run. This also reduced maintenance and running costs. 

5


Apprentices

100%


SME Spend

£3,098.93


Added Value

8/10


Client Satisfaction

Client Testimonials

“One of the key reasons Overbury was chosen was because of your previous track record of delivering projects in occupied buildings. This was key for us so knowing you had that experience gave me confidence.” 

 

“I enjoyed working with the team, there is nothing you could’ve done to improve your performance.” 

Contractor Performance | Commitments


Sustainability

waste recycled 99%

100% timber responsibly sourced 

11 tons of Asbestos removed  


Legacy

29 No of SMEs  – 5 jobs created – 265 trainee weeks – Schools engagement:  3 events 70 pupils over all – 12 volunteer hours 

£3,098.93 donations to charity  –  0.03% social value created

MS got involved with the tenants in the flats above the office space and redid there garden  


Aftercare

Soft landings for handover – yes training session 

On-line portal for notifying any defects with 3 priority categories for response times 


Safe

Zero RIDDORs

CCS Score 45/45 


Fair

100% payment within 30 days terms

University College London – Bloomsbury Theatre

  • Client

    University College London 

  • Contractor

  • Value

    £12.1

  • Completion Date

    25th August 2018 

The Challenge

Live university campus
During the course of the Theatre refurbishment, all of the surrounding areas were fully occupied by either students, academics or were the subject of construction work. Overbury successfully delivered the 36 weeks project without disruption by diligently planning and sequencing the works, ensuring all live and transient services were maintained, while liaising with a wide variety of stakeholders. 

3D modelling
As the project was being designed in a 3D environment, but with the absence of an existing model of the buildings structure, additional point cloud surveys were utilised during the strip out and enabling phase to assist in developing the building services model and co-ordination with structure.

Scaffold design
In order to work at high level and low level simultaneously, a birdcage scaffold was utilised, along with a number of other innovative scaffold designs, in order for works to adjacent areas to progress concurrently. 

 

The Solution

During the Theatre refurbishment, all areas were fully occupied by either students, or were the subject of construction work. 

At no point were any occupants, adjacent buildings or building projects disturbed during our 36 weeks on site, and all live and transient services were maintained throughout 


The Results

Programming was a challenge particularly towards the end of the project, but we flagged issues early, provided extra staff to mitigate any impact, and updated on our progress weekly. 

3


Number of apprentices

70%


SME Spend

29.5%


Added Value

8/10


Client Satisfaction

Client Testimonials

“t’s all about building relationships with your team; I get honesty, transparency and team work. You always have a willingness and involve the Directors in the project. Senior people on the client side are interested in the project at every level. Even given the difficulty of the project, within two months, UCL were ready to re-appoint you for two new projects which is testimony to you.” 

“Everyone, the whole client team, seemed to get on well with Overbury. It was a real team effort. Whenever there were problems we would work together to resolve them. Feedback from the client is that they are really pleased with the quality.” 

Contractor Performance | Commitments


Legacy

15 SMEs (9 local), 13 beneficiaries, 3 jobs created, 130 trainee weeks 

Schools engagement: 949 students 

£1.93 LM3, 92% social value created 


Sustainability

16.2 tonnes carbon equivalent saved in Morgan Sindall’s 10 Tonne Carbon Challenge by changing the heat protection tile supplier to a UK supplier, reducing number of and distance of deliveries 

98% waste diverted from landfill 

7 biodiversity enhancements 


Aftercare

Soft landings for handover 

Dedicated Morgan Sindall point of contact 

On-line portal for notifying any defects with 3 priority categories for response times 


Safe

Zero RIDDORS

CCS Score 40/45 


Fair

100% payment within 30 days terms

Winterstoke Hundred Academy

  • Client

    North Somerset Council   

  • Contractor

  • Value

    £30.5M

  • Completion Date

    August 2023


The Challenge

The Winterstoke Hundred Academy project needed to meet a rapidly increasing demand for secondary school places in North Somerset.

The scheme required delivering a new 900‑place secondary school (expandable to 1,200 pupils) across a large, multi‑hectare site while meeting high environmental performance standards including Net Zero Carbon, BREEAM Excellent and a 10% biodiversity net gain.

It also required integrating sports facilities, community‑focused spaces and on‑site energy generation, all while coordinating with Homes England funding requirements and the existing Academy’s expansion strategy. 


The Solution

The design team created a future‑proofed secondary school across two sites, incorporating a main school building, sports hall, Sustainability Lab, all‑weather pitches, parking, and extensive outdoor learning spaces.

The school was designed using standardised, low‑carbon solutions aligned with Net Zero Carbon in Operation requirements. Community legacy was embedded through the Sustainability Lab, offering training, skills development, and local business support.

Kier worked collaboratively with North Somerset Council and the Cabot Learning Federation, enabling the project to progress from concept to site start within months. 


The Results

The project successfully delivered a £30m+ Net Zero Carbon secondary school providing 900 new pupil places with capacity for future expansion. The completed school achieves BREEAM Excellent, 10% biodiversity net gain and includes low‑carbon energy systems, sustainable transport infrastructure and significant community facilities.

The scheme met the client’s tight programme expectations and has created a modern, sustainable, and community‑focused education environment for North Somerset 

22


Apprentices

30%


Biodiversity net gain

1,871 m3


Waste diverted from landfill

39


Qualifications gained

Client Testimonials

“Listening and responding positively to client concerns or requests in a proactive, supportive way has helped the project go from inception to commencement on site in a matter of months – a real achievement.” 

Contractor Performance | Commitments


Sustainability

There is a large array of photovoltaic panels on the main building roof, which contribute towards achieving Net Zero Carbon in Operation   

BREEAM ‘Excellent’  

EPC rating  

NSC have declared a climate emergency and have policies aligned with this. 

As such it was imperative that this building minimised impact on the climate through both construction and operation as far as was practical with budget and programme constraints. 

Within this context the architects decided to focus on the delivery of a building which is net-zero carbon in operation which has been achieved.  


Legacy

376 waged training weeks on site

39 Qualifications gained

29 work placements

22 new jobs

45 hours volunteering 20 career and guidance events


Safe

This collaborative approach to passive fire protection was encouraged throughout the project, starting with upskilling the team.

Toolbox talks on the topic of the Building Safety Act and the importance of quality design, install and recording of fire protection was led by the Design Manager through the project.