• SCF Client Portal
Logo
  • Support
    • Working with SCF
    • Meet the team
  • Our Frameworks
    • SCF Construct
      • Partnering Contractors
    • SCF Intermediate
      • Intermediate contractors
    • SCF Consult
      • Consultant Partners
  • Our Projects
    • Case Studies
    • Video Testimonials
    • SCF Contractor Apprenticeships
  • Resources
    • Market Intelligence
    • Sustainability
    • Contractor and Suppliers Support
    • SCF Documents
    • SCF Passport Training
    • Building Safety Act 2022
  • SCF6 Procurement
  • News
  • Contact
  • Click to open the search input field Click to open the search input field Search
  • Menu Menu

Archives

You are here: Home1 / Matthew Elliott Contact details2 / Case Studies

Hillbourne Primary School

August 25, 2023/in Education: Primary/by Andrew Real

Hillbourne Primary School

  • Client

    BCP Council

  • Contractor

  • Value

    £8.54m

  • Completion Date

    June 2022

The Challenge

This would be the last school designed and delivered for the Borough of Poole before the councils merged to become the wider BCP Council. The client wanted a design which was slightly different to the traditional standard block form. Better education provision and a more sustainable building was required through the development of a new primary school.

The current school had to remain operational until the new school was ready to move into which was only 3m away from its new building as well as being in a very built-up residential area. This school was also delivered through the height of the Covid-19 pandemic and Brexit.

The Solution

Both the existing school and council were fully involved with the design looking for a school which “stood out”.  This was achieved with a local architect, Cube Design, bringing their extensive education experience to the table. The whole look of the building was designed to be more aesthetically pleasing.

The project team worked closely with the client, going out of their way to ensure the project fully met their needs, discussing with the school and architects to make things as perfect as they could be for the end users.

The project team managed resources, materials and logistics throughout adapting to Covid-19 SOP requirements. A segregated walkway was created to allow staff and pupils to safely move between their two buildings. All construction traffic had to be pre-booked through Kier’s Mi-site system.

The project was undertaken in two phases: the first phase seeing the construction of the primary school and the second stage saw the demolition of the existing schools creating the sports pitch. The hall and sports facilities will also be utilised by the local community not just the current pupils. The surplus land following demolition is being used for a new housing development creating 110 new homes.

The Results

By creating some variation with the building heights, the school now has two, two-storey blocks on either side and a one-storey library adjoining the two buildings to create a u-shape looking onto a central courtyard.  The modern buildings now include 14 classrooms, a practical teaching room and learning space centre, an administrative block, large multi-purpose hall with adjoining kitchen, a pre-school with dedicated play area, two multi-use games areas and a purpose-built (Sports England standard) sports pitch.  The light and airy building has a modern feel, providing the perfect environment to learn and now enables all staff and pupils to finally be under one roof.

The new school has multiple sustainable and efficient features including solar panels, mechanical ventilation, intelligent lighting, non-combustible envelope and external VO cladding.  High quality materials such as glazing and American white oak veneered doors have also been incorporated creating a warm and inviting place to learn and flourish in.

Despite being delivered during the Covid-19 pandemic and the early stages of Brexit, this project was delivered successfully on time and within budget.

7


Apprentices

82%


SME Spend

£4,461


Added Value

9/10


Client Satisfaction

Client Testimonials

“It’s fantastic to see the new school taking shape and on track to welcome the staff and pupils in October. I’m delighted that we have been able to develop a brand new fit-for purpose building for the Hillbourne community, that will benefit and support our young people to receive a high quality education and give them the best opportunities to grow and flourish.”

Councillor Nicola Greene, Portfolio Holder for COVID Resilience, Schools and Skills

“To have all of our children and teachers in one school, is just amazing. Being in a school that was built for these children to learn in, rather than two buildings that over 70 years have been adapted to whatever provision needed to be made, just makes all the difference.” The new two-storey structure has created a fluid working environment that has already had a profound influence on how the pupils feel. Helen added: “It’s a massive difference from what it was before, absolutely massive. I think in terms of practical ways, it’s really good, but also in the way the children feel about themselves. They’ve walked into a really beautiful building and it makes them value themselves more, and then, in turn, value themselves more as learners.”

Headteacher, Helen Roderick
Previous Previous Previous Next Next Next

Contractor Performance | Commitments


Fair

Regular payments and have payment periods not exceeding 30 days


Sustainability

94% waste diverted from landfill

100% timber responsibly sourced

BREEAM Good


Safe

Zero RIDDORs
CCS Score 43/45 (Beyond Compliant)


Legacy

11 beneficiaries

7 jobs created

228 trainee weeks

Schools engagement: 3,540 students

£3,830 donations

41 volunteer hours

80% social value created which included food bank donations, a time capsule burial, Christmas card competitions, Easter egg fundraisers, and lamppost renovations.


Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times

SCF Framework Manager

Kingsley Clarke

Email: kingsley.clarke@devon.gov.uk

Phone: 07805760622

Contractor Framework Manager

Alan Smedley

Email: alan.smedley@morgansindall.com

Phone: 07967 686066

https://southernconstructionframework.gov.uk/wp-content/uploads/2023/08/Picture1.jpg 738 1379 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2023-08-25 14:23:352024-02-13 11:33:34Hillbourne Primary School

St Sidwell’s Point Leisure Centre

April 3, 2023/in South West Sports and Leisure Leisure/by Gabby Stevens

St Sidwell’s Point Leisure Centre

  • Client

    Exeter City Council                 

  • Contractor

  • Value

     £34m

  • Completion Date

    April 2022


The First Passivhaus Leisure Centre.

The Challenge

The overarching challenge was to build the world’s first dry and wet leisure Passivhaus Leisure Centre. This not only involved upskilling the supply the domestic supply chain but leisure specialist too. Delivering Passivhaus requires collaboration at every stage to be successful and this was recognised early by the delivery team. Any part of the wider team could negatively impact the airtest result or energy performance when working to such a tight standard.

Therefore the quality culture had to be set and consistently disseminated throughout the client, design and construction teams, throughout the supply chain. Collaboration and quality control were significant factors considered during procurement. Some trades, for example groundworks, M&E and façade are integral to achieving the air tightness rating, which is essential for Passivhaus certification, their training was very detailed and complex around minimising thermal bridging, for example.

There was a large supply chain involvement including 71 different trades, the delivery team realised it wouldn’t be feasible to have site managers checking every detail. That led to the idea of the Passivhaus Passport to act almost as a ‘safety net’.

The Solution

In order to achieve the stringent build criteria, Kier worked closely with its subcontractors to deliver a ‘Passivhaus Passport’ training scheme, equipping its staff with the knowledge and skills to meet the requirements.

The training developed by consultants WARM provided an introduction to Passivhaus principles, the essential controls in delivery and an understanding of the positive benefits to the end users, wider community and our environment. The trade specific training modules were supported with input from the relevant manufacturers too.  It was a fantastic opportunity for people to further their knowledge and skills in their respective trade.

The Results

Kier introduced the Passivhaus Passport. The passport is awarded for the successful completion of Passivhaus induction and training. All operatives take part in the induction and the training is specific for each trade, with >2,500 passports issued to the supply chain. The impact of this understanding had significant benefits beyond Passivhaus risk mitigation. The quality culture developed and the pride in the project was so strong that sub-contractors would post photos of their work on social media. That’s part of the reason Kier achieved an air tightness rating of 0.3m³/hr/m²@ 50Pa against a target of 0.4m³/hr/m²@ 50Pa, which is 20 times stricter than building regulations.

The air tightness results is fantastic, but there were other knock-on benefits of the Passivhaus Passport. There was a much more consistent workforce on the site throughout the duration. On a traditional build, you might have different sub-contractors or operatives on different days, but At St Sidwell’s Point the project team didn’t have that because of having to go through the passport process. The project ended up with a consistent group of people working to a common goal and that contributed to the quality and safety of the project.

Client, designers, contractor and supply chain worked closely throughout to deliver a successful outcome. This has delivered a building with no performance gap to the highest of design standards, St Sidwell’s Point is Passivhaus accredited.

8


Apprentices

25%


betterment on Passivhaus air tightness target and 20 times stricter than building regulations

9/10


Client Satisfaction

Contractor Performance | Commitments


Fair

100% payment within 30 days terms


Sustainability

70% off annual running costs


Safe

Zero RIDDORs


Legacy

24 new jobs created (15 new entrants, 8 apprenticeships, 1 graduate)

13 qualifications gained (7 main contractor, 6 sub-contractors)

35 work placements (27 in education, 22 T-Level students, 5 school placements, 8 not in education)

>2,500 people issued PassivHaus Passport

Awards

Constructing excellence Southwest 2022 – Net Zero winner

Constructing excellence Southwest 2022 – Project of the Year

Constructing excellence Southwest 2022 – Winners Winner

SCF Framework Manager

Kingsley Clarke

Email: kingsley.clarke@devon.gov.uk

Phone: : 07805760622

Contractor Framework Manager

James Parr

Email:  james.parr@kier.co.uk

Phone: 07794218011

https://southernconstructionframework.gov.uk/wp-content/uploads/2023/04/SSP-5.jpg 698 1220 Gabby Stevens https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Gabby Stevens2023-04-03 18:13:432025-09-24 11:07:45St Sidwell’s Point Leisure Centre

Wimborne First School

January 16, 2023/in Education: Primary/by Andrew Real

Wimborne First School

  • Client

    Dorset County Council

  • Contractor

  • Value

    £7.75m

  • Completion Date

    November 2019

Although Dorset County Council (DCC) used a traditional form of contract, we were appointed under a PCSA during RIBA Stage 4 to provide cost and buildability advice and to offer the benefits of early engagement with our supply chain. Through clever works sequencing, the team delivered the playing field earlier than programmed.

Construction of a new three-form entry first school,  on a shared new housing site with Bloor Homes, fit for the 21st century teaching and learning to accommodate an increase in pupils generated by the surrounding housing developments in Wimborne. The new school will accommodate 450 pupils and is located just 0.8 miles from the town centre.


The Challenge

DCC’s key drivers for the project include delivering within their approved budget and maximising investment in the local area.

The Solution

By agreeing a procurement strategy with DCC, we engaged local supply chain and our aligned supply chain partners early to review buildability and generate cost savings. This included a separate feasibility study by Byrne Looby (engineering consultants), Keller (foundations) and Woodmace (groundworks), to explore alternative foundation options with the aim of minimising money spent in the ground and managing the abnormal ground conditions cost effectively and safely. The study involved an initial options report, collaborative workshops, further site investigations organised and a period of dialogue with suppliers to answer DCC queries.

The Results

The outcome was that a Vibro Stone Column Piling solution, with a degree of lime stabilisation, was a feasible alternative to traditional CFA piling, which generated a saving against DCC’s Cost Plan of circa £100k. The information and outputs from the study were incorporated into an updated Site Investigation Report by DCC’s own engineer and issued as part of the tender pack to ensure a fair basis for tendering by all suppliers.

The project was delivered to budget and the largest package, mechanical and electrical was procured with a local supplier.  Just under £5m was spent with local SMEs.

7


Apprentices

97%


SME Spend

£1m


Added Value

8/10


Client Satisfaction

Client Testimonials

‘The building and grounds were fantastic’

Previous Previous Previous Next Next Next

Contractor Performance | Commitments


Sustainability

Passive mechanical and natural  ventilation systems contributed to low running costs. Trees were protected throughout the course of the project and the team regularly engaged with the Environment Agency about the ground water and ensured silt was well managed.


Fair

Payment periods were agreed at preconstruction and adhered to.


Safe

The client cited that the team’s management of safety was high and that site circulation and access was well controlled, giving a rating of 9. For CCS, they consistently scored an average 42.5 with the last one being 44.


Legacy

8 technical and work based experienced and was delivered and several site visits with the school children were organised and complimented with classroom projects.


Aftercare

Despite high number of school staff changes over the course of the project, the Project Manager held several collaborative handover and aftercare workshops with the school to ensure that messages were not lost. Galliford Try’s Facilities Management also attended these workshops to ensure continuity from project completion.

SCF Framework Manager

Kingsley Clarke

Email: kingsley.clarke@devon.gov.uk

Phone: : 07805760622

Contractor Framework Manager

Angela Purse

Email: Angela.Purse@gallifordtry.co.uk

Phone: 07593 561855

https://southernconstructionframework.gov.uk/wp-content/uploads/2023/01/Wimborne-030d-scaled.jpg 1385 2048 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2023-01-16 14:16:232023-01-16 14:16:23Wimborne First School

Kingston University

January 16, 2023/in Education: Further / Higher Refurbishment/by Gabby Stevens

Kingston University Knights Park Extension

  • Client

    Kingston University

  • Contractor

  • Value

    £24m

  • Completion Date

    November 2019

The refurbishment at Kingston University’s Knights Park Campus provides the Faculty of Art, Design and Architecture with 9500sqm of new and improved facilities that better reflect the school’s outstanding reputation and competitive edge. The new building provides more collaborative working space for staff and students.


The Challenge

The design and build project was undertaken in full occupation. The project required a significant decant schedule, and ongoing noise, dust and vibration monitoring.


The Solution

A phased approach to the works with a detailed decants schedule enabled activities to progress with minimal disruption to the campus. We provided a dedicated contact purely for any issues around noise, dust or vibration in order to address immediately. The phasing was undertaken floor by floor thus enabling containment as far as possible.


The Results

The final project delivered a 52% reduction in operational carbon emissions and also achieved BREEAM Excellent. Over 1,000sqm of flat roof has been put to work, providing outdoor teaching spaces, wildlife habitats and green roofs.

16


Apprentices

£1,373,453


Added Value

Contractor Performance | Commitments


Fair

100% payment within 30 days terms


Safe

Zero RIDDORs


Aftercare

Soft landings for handover


Legacy

21 work experience placements

7 curriculum support activities

6 graduates

9 jobs created

15 NVQs

Community garden renovation


Sustainability

100% timber responsibly sourced

Over 100sqm of flat roof providing wildlife habitats and green roofs

BREEAM Excellent

52% reduction in carbon emissions

SCF Framework Manager

James Wright

Email: james.wright@hants.gov.uk

Phone: : 07761 330560

Contractor Framework Manager

Alan Smedley

Email: alan.smedley@morgansindall.com

Phone: 07967 686066

https://southernconstructionframework.gov.uk/wp-content/uploads/2021/02/Dawid-Patryk-helping-fisal-do-a-material-audit-3-scaled.jpg 1536 2048 Gabby Stevens https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Gabby Stevens2023-01-16 11:25:562023-01-16 11:25:56Kingston University

Extreme Photonics Applications Centre, Harwell Science and Innovation Campus

January 10, 2023/in Civic and Community/by Andrew Real

Extreme Photonics Applications Centre, Harwell Science and Innovation Campus

  • Client

    Science Technology Facilities Council (STFC)         

  • Contractor

  • Value

    £36m

  • Completion Date

    March 2022


The Extreme Photonics Applications Centre (EPAC) building is a new purpose-designed facility that will house cutting-edge equipment required for a unique, state-of-the-art high power / high repetition rate laser system.

The project is a partnership between UKRI, MoD, academia and industry. It brings together world-leading interdisciplinary expertise to develop and apply novel, laser based, non-conventional accelerators and particle sources which have unique properties. It is hoped to produce scientific breakthroughs and stimulate new solutions to challenging problems to help advance UK science and technology, helping to keep us safer, improve our healthcare and support a cleaner, more productive economy.


The Challenge

The science and technological application required us to place 7500cu metres of a specially designed low carbon concrete mix to create 3 reinforced concrete ‘laser target areas’ as a homogenous ‘crack-free’ structure.


The Solution

To achieve the ‘crack-free’ structure required the advice of one of the best structural minds in the world combined with technical expertise from renowned locally based ready mix concrete supplier. The structural solution was successfully delivered hailing it as one of the most important structures in Europe outside of the nuclear industry.

The Results

The project achieved a 48% (or 1372.5 tonnes) carbon reduction using structural concrete with a composition of 75% Ground Granulated Blast Furnace Slag (GGBS) and slag cement replacement (blast furnace bi-product) in place of 100% Portland Cement. The concrete design was based on its radiation shielding properties, high density aggregates and reduced cement content to reduce the risk of thermal cracks. Specifying this concrete mix enabled the site team to maintain control of the curing temperature to ensure minimal cracking and achieve the specified oven dry density for shielding purposes.

Redefining the Boundaries of Science and Discovery at Harwell Campus

450.8 weeks


Apprentices

£26.1m


SME Spend

£1.53m


Added Value

9/10


Client Satisfaction

10/10


Health & Safety

Client Testimonials

“As we said at the topping out, working with you has been an absolute pleasure…by continuously working very closely with Mace and the team in a flexible way rather than a traditional way.

If you get the partnership right and the people right, it works and takes years off the overall project delivery process. We have collectively managed to get that right.”

Professor John Collier Director, Central Laser Facility
Previous Previous Previous Next Next Next

Contractor Performance | Commitments


Fair

All payments in accordance with the fair payment charter.


Safe

Zero RIDDORs


Legacy

450.8 apprentice training weeks, 80 trainee weeks, 292.3 graduate trainee weeks.


Aftercare

Client provided an 8/10 score for the buildings building’s future maintenance and running costs, including energy efficiency.


Sustainability

By using 75% GGBS the project achieved a 48% carbon saving. This equates to 1372.5 tonnes of carbon (in comparison with using 100% Portland Cement).

SCF Framework Manager

James Wright 

Email: james.wright@hantsgov.uk

Phone: 07761 330560

Contractor Framework Manager

David Chambers

Email: david.chambers@macegroup.com

Phone: 07789 514895

https://southernconstructionframework.gov.uk/wp-content/uploads/2023/01/Picture1.jpg 768 1024 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2023-01-10 11:55:242023-01-23 15:20:43Extreme Photonics Applications Centre, Harwell Science and Innovation Campus

Colindale HQ

December 9, 2022/in Civic and Community School/by Gabby Stevens

Colindale HQ

  • Client

    London Borough of Barnet  

  • Contractor

  • Value

    £36m

  • Completion Date

    April 2019

Construction of a new £36 million office building providing bespoke office accommodation for London Borough of Barnet. The project forms part of the Colindale regeneration programme. The new development is a nine-story building with a recreational terrace area on the 4th floor and provides a modern working environment for up to 1,400 people, including office spaces as well as a cafe on the ground floor. The new facility supports the London Borough of Barnet in working closer with the community.


The Challenge

Following PCSA appointment, London Borough of Barnet required to increase the use of the building to include additional community facilities like social services, business innovation hub, café and public conference suite – all whilst maintaining budget.

The Solution

Working with the architect, Hawkins Brown, we adapted the previous scheme design and incorporated an additional floor space to house the extra facilities. The redesign process required building shape and structural changes and extension of building services. The end users were consulted and engaged throughout the process to ensure group consensus. By working with Price & Myers, structural engineers, we redesigned the underground drainage connections which was tunnelled and avoided costly and disruptive above ground work. This removed the connection from the critical path and reduced programme risks considerably.



The Results

Despite having to extensively redesign, the preconstruction period was maintained and through early engagements with supply chain partners and through collaborative design and planning workshops, value engineering options were identified, resulting in a new enhanced scheme delivered within budget.

3


Apprentices

99%


SME Spend

2m


Added Value

910


Client Satisfaction

Contractor Performance | Commitments


Fair

Payment periods were agreed at preconstruction and adhered to.


Sustainability

Over 60% of supply chain were within 30 miles of the project, resulting in £18m spent locally. The project achieved BREEAM Very Good and incorporated energy saving design efficiencies, reducing running cost by £1m a year.


Aftercare

The Project Manager remained on site four weeks post completion and aftercare was managed in-house by our Facilities Management team.


Legacy

The team exceeded targets by 200% for work placements for under 16 years and through engagements with Barnet and Southgate College, 12 placements were given to their students. In addition, we also held bricklaying competition, enabling students from the college to learn new skills and gain support from site managers and supply chain directly.


Safe

The team held two Safety Stand Down days and 221 operatives  participated. The Intervention Workshop encouraged better communication and buy-in from our supply chain partners in the management of health and safety which helped the team achieve 43 on their last CCS visit.

SCF Framework Manager

James Wright

Email: james.wright@hants.gov.uk

Phone: : 07761 330560

Contractor Framework Manager

Angela Purse

Email: angela.purse@gallifordtry.co.uk

Phone: 07593 561855

https://southernconstructionframework.gov.uk/wp-content/uploads/2020/09/External.png 760 1280 Gabby Stevens https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Gabby Stevens2022-12-09 14:02:452023-02-01 13:59:23Colindale HQ

Belvedere Warehouse

December 9, 2022/in Civic and Community/by Andrew Real

Belvedere Warehouse

  • Client

    Mayors Office for Policing and Crime

  • Contractor

  • Value

    £42.2m

  • Completion Date

    January 2020

Construction of a new secure warehouse facility; comprising two separate building structures. Building one provides office accommodation facilities over three levels, a warehouse facility and two storey specialist storage facility encompassing double-volume intelligent storage equipment, as well as a number of cold hold refrigeration storage units. Building two is a standalone vehicle maintenance workshop, which contains specialist vehicle testing machinery and servicing equipment.


The Challenge

Following site surveys and results from investigative reports, the ground was found to be significantly contaminated from previous use of the site. Despite being a construct only contract, we helped the client through the design process, finding most cost efficient solutions that maximised reuse.

The Solution

We had to raise the site ground level as a result of site investigation and thus required changes to the designs. Remediation works were needed to manage the contamination and included excavation of materials, mixing it with clean / inert materials to reduce contaminations levels and reusing on site. Under strict controls, the works were fully compliant to ensure safety of the workforce.

We adopted an early warning process using the NEC proforma and through working collaboratively with the Employers Agent and our groundworker and M&E supply chain partners, we managed to develop designs which saved the client money, like rationalising the pile and mat make-up and size and installation methodology, which avoided contamination arisings. Substantial earthworks movement were closely managed with commercial neighbours and residents nearby through daily liaison and by regular updates on our site information board.


The Results

The value engineering designs saved the client over £1.5m.  One of those included using a sleeved piling system with reduced pile diameters that avoided contaminated arisings saving both time and £540k in disposal costs.

£12.4m


SME Spend

£1.5m


Added Value

9/10


Client Satisfaction

Contractor Performance | Commitments


Sustainability

In addition to achieving 100% recycling during the groundworks phase, we also installed and maintained bird feeders and planters throughout the project to encourage biodiversity.


Fair

25% procurement was with small businesses and payment periods were kept to throughout the project.


Safe

Despite the groundwork and logistic challenges, there were zero complaints and through innovative ideas like using a ‘Thumbs Up’ sticker to denote plant safety, the team scored an average of 44 on their CCS visits.


Legacy

5 work experience placements were offered to students at London South East. Additionally, a graduate successfully completed her apprenticeship and is currently employed by GT as a Trainee Technician. In addition, the team donated 60 biscuit boxes to Queen Mary’s Hospital to thank the nurses, doctors and staff for their dedication, helping the community through the Covid pandemic.


Aftercare

An Operations Manager remained on site for six weeks post completion to ensure that end users were satisfied and looked after. Our Facilities Management team managed after care for 12 months.

SCF Framework Manager

James Wright

Email: james.wright@hants.gov.uk

Phone: : 07761 330560

Contractor Framework Manager

Angela Purse

Email: angela.purse@gallifordtry.co.uk

Phone: 07593 561855

https://southernconstructionframework.gov.uk/wp-content/uploads/2022/12/Aerial-2.1.jpg 664 1183 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2022-12-09 13:31:542022-12-09 13:31:54Belvedere Warehouse

Shoreditch Academy and Hackney Britannia Leisure Centre

November 29, 2022/in London Education: Further / Higher, Sports and Leisure Leisure, School/by Mel

City of London Shoreditch Academy and Hackney Britannia Leisure Centre

  • Client

    London Borough of Hackney

  • Contractor

  • Value

    £97.6m

  • Completion Date

    December 2021

New 6FE secondary school for 940 pupils and 200 6th form.  Roof top sports pitch and playground.  BREAAM Outstanding at design stage.  High environmental performance.

New 4-storey Britannia Leisure Centre with mix of single, double and triple height spaces.  Six-lane 25m main pool and 20m training both with moveable floors and leisure features including 3-storey flume.  Café and toilets.  Indoor 6 court sports hall.  Creche and soft play area.  Sauna and steam room.  Fitness suite (spin studio and 2 exercise studios).  Four squash courts.  Two rooftop 5-a-side pitches and 2 rooftop tennis courts.

The Challenge

Shoreditch Academy: As the existing Britannia Leisure Centre remained open throughout construction, customer access into the leisure centre needed to be modified to facilitate the COLASP building which was almost the footprint of the existing carpark and therefore logistically challenging.

Leisure Centre: Externally, we focused on a design solution to encourage the local community to participate in sports and lead a more active lifestyle. As such, the cellular changing accommodation was positioned in the centre of the building, with the pool-halls and other sports spaces wrapped around the perimeter. This produced an elevated, animated building that entices the public into the facility.

Thames Water sewer: Construction of the leisure centre was complicated by the presence of an existing large diameter Thames Water storm relief sewer that runs diagonally across the site at a depth of 14m. This sewer has an exclusion zone of 3m either side and above it where no new construction is allowed. The building is on a tight footprint and the leisure activity zones are ‘stacked’ vertically which created some interesting challenges in structural stability and vibration control. Spanning 9m over the sewer and due to the diagonal alignment, equates to some 14m on grid, this alone brings significant construction challenges. The site also directly sits on the position of a vertical access shaft which gave access to the sewer for maintenance and emergency escape purposes.

The Solution

Shoreditch Academy: We designed an innovative ramped solution into the top floor of the Leisure Centre building to allow it to remain open while the new school was built.  We fixed transport routes around the whole site to manage traffic and deliveries. There was a cycle superhighway adjacent to our site, which required collaboration with the highways team. The proposed route for Crossrail 2 was also located directly underneath the new Academy, so the building design needed to be considered due to strict loading restrictions imposed by Crossrail.

We designed a unique groundworks solution to incorporate the temporary sheet piling into the permanent structure at basement level, creating an extremely cost-effective solution for the project. The precast cladding was then selected as it required no scaffolding and cut down on noise and vibration on vehicle deliveries to the site.

The façade was also load-bearing and allowed the design of the concrete framed structure to be simplified and fast erection on site while minimising construction site area. We even designed the City of London logo onto the facades via a patterned concrete finish which was then installed along with all other panels. The future Crossrail tunnels, size of the building and constrained nature of the site required an innovative approach. The building footprint was kept as small as possible to maximise the playground areas, taking advantage of the existing topography to create an amphitheatre playground.

Leisure Centre: Due to the complexity of the stacked leisure centre we had to keep the sports hall free of columns, and to bridge over the pool areas a complicated steel truss arrangement was needed. Spanning over 10m in height and 50m in length, the spine of the building spans 3 floors. Due to these structural intricacies, this was built on-site then lifted into place with two 500 tonne cranes in a tandem crane lift. This was an innovative and important project milestone for the build, which was completed safely and successfully.

We developed a team of specialist engineers whose knowledge and input enabled us to create a safe, on time and to budget build. As an example, the main 25m swimming-pool hall is double-height, and the leisure pool hall is triple height. Each of these pool spaces contains warm, moist air which is under positive pressure. Cooler spaces such as the sports hall and fitness gym are positioned over the pool-halls therefore the environmental separation between each of these spaces was a key construction challenge. To help deliver this environmental control we involved a specialist mechanical engineer with a focus on finite engineering. This ensured we maintained the continuity and integrity of the vapour control layer both vertically and horizontally within the building, preventing pool-hall air migrating through the building envelope, preventing it condensing on any cooler surfaces or spaces. Maintaining the continuity of the vapour control layer and insulation performance was particularly important for our roof-top pitches. We knew the importance of having an air-tight vapour control layer that was chlorine resistant for the longevity and overall safety of the build.

Thames Water sewer: We worked with Buro Happold and Thames Water to overcome the main risks of working over the sewer. This involved developing a working / construction methodology of preventing the sewer from trying to pop out of the ground due to buoyancy when it was empty or bursting under 14m head of water pressure when it became full. One of the main the concerns was that by excavating over the sewer to form the basement areas and pool shells, we would be effectively reducing the weight of the soil over the pipe, increasing the risks associated with buoyancy or bursting. Early involvement commissioned a detailed line and level survey to ascertain the precise depth and alignment of the sewer pipe, this led to greater confidence and understanding of design parameters and restrictions.

The Results

Shoreditch Academy: The school was originally due to open in September 2021; however, we were able to hand over the building for the school to occupy earlier than planned in June 2021 to use for their final school term and allow the year 11 pupils to carry out their final exams in their new school.

Leisure Centre: With our attention to detail and meticulous checking systems we are set to achieve BREEAM Excellent. The building’s energy design philosophy was to connect into the future district heating system which was being provided as part of the redevelopment of the Colville Estate.

To enable this to occur a temporary energy centre serving both the leisure centre and school, was installed and removed once the permanent connection to the energy centre was installed. Our district heating system and the overall design compliments the energy targets established in the New London Plan, so all equipment installed is energy efficient.

As an example, we use low energy fans to minimise energy consumption and have PV panels on the roof that supports our on-site sustainability strategy. Supporting our sustainability goals, we took advantage of the TfL CS1 main cycle superhighway which was adjacent to the project and were the first contractor to adopt a carbon neutral innovation of using Cargo Bikes for plant hire and small deliveries. Almost 500 residents can see the site, so we looked for innovative solutions to flood lighting and became the first constriction company to use hydrogen flood lights which helps reduce excessive noise.

Thames Water sewer: Once we knew the exact positioning of the sewer we developed a detailed construction methodology, working with Thames Water to agree how the works would be constructed. This led to greater cost and programme certainty and the removal of the substantial provisional sums associated with the identified risks.

45


Apprentices

54%


SME Spend

£26.8m


Added Value

9/10


Client Satisfaction

Client Testimonials

From the start, working with Morgan Sindall has been different. It has been a true collaboration and team effort to deliver this incredible new leisure centre and secondary school during a pandemic. Morgan Sindall have added real value at every stage of the project and their forward planning, focus on delivery, supply chain and genuine interest in minimising the impact of the construction process on the local community has been exemplary. This has included great local communication and building strong local partnerships from mobilisation through construction and into the final handover. After a very difficult year, I am so proud of what we have achieved with Morgan Sindall in delivering the biggest public sector investment in Shoreditch and Hackney in a generation.

A critical part of the Britannia Development for the Council has always been the social value that could also be delivered as part of the project. This has always felt like a key focus for Morgan Sindall as well – they have delivered excellent outcomes on apprenticeships, mentoring and work placements. However, they have also gone further, working hard on sustainability through initiatives like the use of cargo bikes and developing important links with local charities, community groups and schools throughout the project. Morgan Sindall are certainly one of the best contractors we have worked in partnership with in terms of delivering social value outcomes.

Philip GlanvilleElected Mayor of Hackney

Simply one of the finest schools & educational environments, not just in Hackney, but in the country. State of the art, spacious, designed with the community in mind and ready to serve Hoxton, Shoreditch & Hackney.

Philip Glanville Elected Mayor of Hackney
Previous Previous Previous Next Next Next

Contractor Performance | Commitments


Legacy

Winner of Building’s Award for Delivering Social Value

Hackney’s Apprentice Employer of the Year

Hosted a Wheels for Wellbeing best practice site visit as part of ongoing commitment with TfL and Streetscene to ensure the site boundary was easily accessible for all pedestrian users. Wheels for Wellbeing focus is wheelchair cycling and ensuring cycle lanes are adequate to allow inclusion for all.

Project team hosted local forums and drop-in sessions at 5 local schools in advance of works starting so they could understand the logistics and opportunities for schools engagement as well as local residents’ forum.

Partnership created with Shoreditch Trust addressing inequality and supporting people who are facing life and health problems. This included sponsorship of an Elders Feast.

Hosted CIOB virtual site tours during Covid 19 pandemic to inspire more people into construction

Sponsored Hackney Council’s virtual quiz night raising money for Hackney Foodbank

Hosted two visits from 9 SEND students to aid their transition from their old school site to the new constructed school

Hosted two site visits for K10 (local shared apprenticeship provider) for 27 students to give them much needed experience resulting in 6 work experience placements

Attended Women in Construction career seminar, speed interviews and mentoring programme

Attended a number of Hackney Works initiatives supporting local residents finding work

Created two “Paws Stations” for local daily dog walkers against the site hoarding

161 beneficiaries

64 new jobs created (39 previously unemployed and 19 live in Borough of Hackney)

34 Apprentices – 8 lived in Hackney, 18 enrolled in new apprenticeships on this project and 9 now directly employed by the company they worked for

1,096 trainee weeks

1001+ student engagement events

Schools engagement: xx students

£48,500 donations to charity

822 volunteer hours

47 No of SMEs

£2.11 average LM3

£78m social value created


Sustainability

97% waste diverted from landfill

100% timber responsibly sourced

BREEAM Outstanding

Natural ventilation and user controls maximisedTrialled cargo bike deliveries on the project making full use of TfL’s Cycle Super Highway adjacent to the project to capture industry best practice of zero emissions method of transport and resulting in 17.1kg CO2/km saving per week. We are one of the only construction sites using this type of delivery and installed a cargo bikes loading area – the first in the country!

First use of hydrogen flood lights in construction

110 trees planted doubling the previous number

Wood chippings from removed trees retained by Hackney Council’s ground maintenance team and felled trees donated to Shoreditch Adventure Playground as climbing frames and seating

Reusable water bottles which can be clipped to a belt issued to all site operatives


Safe

CCS Score 45/45

Collaborated with TfL’s Cycle Super Highway and Hackney Council Street scene by taking part in an environmental walk to agree construction logistics, review traffic routes and ensure cyclists enjoyed passing the project throughout construction. All traffic Marshalls completed TfL’s Elite Marshal training.

Nominated for TfL Transport Awards through collaboration with TfL and Hackney Highways team


Aftercare

Soft landings for handover
Dedicated Morgan Sindall point of contact
On-line portal for notifying any defects with 3 priority categories for response times


Fair

100% payment within 30 days terms

SCF Framework Manager

James Wright 

Email: james.wright@hants.gov.uk

Phone: 07761 330560

Contractor Framework Manager

Alan Smedley

Email: alan.smedley@morgansindall.com

Phone: 07967 686066

https://southernconstructionframework.gov.uk/wp-content/uploads/2022/11/Shoreditch-Academy-and-Hackney-Britannia-Leisure-Centre-3.jpg 286 550 Mel https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Mel2022-11-29 12:31:532026-02-18 10:20:28Shoreditch Academy and Hackney Britannia Leisure Centre
littlehampton wave

Littlehampton Leisure Centre

October 31, 2022/in Sports and Leisure Leisure/by Andrew Real

Littlehampton Leisure Centre

Sussex

  • Client

    Arun District Council

  • Contractor

  • Value

    £17m

  • Completion Date

    March 2019

littlehampton wave

The Challenge

The replacement leisure centre was built on the same site as the existing leisure centre, which meant one of the biggest challenges was ensuring that there was minimal disruption to the leisure centres operations.

The Solution

To minimise disruption to leisure centre members, the construction was phased, and the new Leisure centre was constructed before the existing building was demolished.

The new leisure centre comprises wet & dry facilities including 8 lane 25m swimming pool, 4 court sports hall, 80-85 station gym, studio capacity of 50 with flexibility and a learner swimming pool.


gym equipment

The Results

Littlehampton was opened on time and to budget with a high standard of finish, exceeding expectations of customers and Freedom Leisure who are responsible for managing the leisure centre in partnership with Arun District Council.

The project was shortlisted for two LABC Regional Building Excellence Awards 2020

1) Best Public Service or Educational Building and

2) Best Large Commercial Project in the LABC Regional Building Excellence

Once opened to the public, membership applications increased c200% outperforming forecasted targets.


12


Apprentices

95.6%


SME Spend

22%


Added Value

9/10


Client Satisfaction

Contractor Performance | Commitments


Fair

99% of regular payment periods did not exceed 30 days


Sustainability

97% of waste was diverted from landfill


Safe

Zero harm


Legacy

Local work placements, trainee and graduate placements and apprenticeships, along with creating new jobs in the local area.


Aftercare

Handover & Aftercare Contractor Promise

SCF Framework Manager

James Wright

Email: james.wright@hants.gov.uk

Phone: 07761 330560

Contractor Framework Manager

Guy Dawes

Email: guy.dawes@willmottdixon.co.uk

Phone: 07989179444

https://southernconstructionframework.gov.uk/wp-content/uploads/2018/05/Littlehampton-Wave-scaled.jpg 1363 2048 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2022-10-31 14:14:022023-08-18 11:05:02Littlehampton Leisure Centre

Fulham College Boys’ School, London

October 25, 2022/in Education: Further / Higher College/by Andrew Real

Fulham College Boys’ School, London

  • Client

    Fulham College Boys’ School / Department for Education

  • Contractor

  • Value

    £13.75m

  • Completion Date

    May 2021

Major renovation of a live secondary school, enhancing teaching provision for its transition to a Science, Technology, Engineering and Mathematics (STEM) specialist Academy.

The Challenge

Undertaking major renovation works within a live secondary school, scheduled over three phases of works.

Phase 1: The transformation of Block L (the existing drama building) for use as the site team’s welfare and site offices; internal reconfiguration of the second floor of the Childerly Building providing an additional classroom; provision of 3 working labs and 2 standard classrooms.

Phase 2: Demolition and subsequent construction of a two-storey, steel framed science block providing six new teaching labs. The building includes a green roof, PV panels and attenuation tank.

Phase 3: The extensive refurbishment of the Grade II listed Kingwood Building including asbestos removal, MEPH systems, window replacement, decoration and carpentry works.

The Solution

It was recommended to the client that Block L (which was due to be demolished) be utilised as the site office and canteen space. This not only saved the project money in site setup costs and omission of the Block L demolition works from the scope of works, but furthermore, the making good of the building provided the school with a new space for music classes.

With three separate handovers, it was imperative that a good relationship was maintained with the school staff. Consideration and understanding were incorporated into the safe planning of works and scheduling of deliveries to allow the live school to continue to operate. The use of temporary modular classrooms accommodated students away from the works thereby ensuring minimal disruption to the overall learning environment.

–

The Results

Three successful handovers to a delighted client, helping to realise the school’s transition into a specialist STEM Academy. The first phase was completed on time, the second phase was handed over two weeks earlier than expected, and the third phase of works was also completed on time.


4


Apprentices

93.1%


SME Spend

£840k


Added Value

9/10


Client Satisfaction

Client Testimonials

“In my role as Trust Senior Site Manager, I led on behalf of liaison with the school and can happily report that Morgan Sindall have proven to be the most efficient, cooperative and enjoyable construction company I have had the pleasure to work with in my 20 years’ experience. From the early design stage right through to completion, communication between the school and Morgan Sindall has been second to none.”

Terry Barrett Fulham College Boys’ School’s Senior Site Manager.
Previous Previous Previous Next Next Next

Contractor Performance | Commitments


Fair

100% payment within 30 days terms


Sustainability

91% waste diverted from landfill

100% timber responsibly sourced

BREEAM Very Good


Safe

Zero RIDDORs

CCS Score 43/45 nominated for 2020 Award


Legacy

14 apprenticeships, 6 of which were new jobs created

7 work experience placements

272 Trainee weeks

Schools engagement: 361 pupils


Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times

SCF Framework Manager

James Wright

Email: james.wright@hants.gov.uk

Phone: 07761 330560

Contractor Framework Manager

Alan Smedley

Email: alan.smedley@morgansindall.com

Phone: 07967 686066

https://southernconstructionframework.gov.uk/wp-content/uploads/2022/10/54V003-scaled.jpg 1365 2048 Andrew Real https://southernconstructionframework.gov.uk/wp-content/uploads/2018/07/Logo.svg Andrew Real2022-10-25 16:11:542022-10-25 16:11:54Fulham College Boys’ School, London
Page 3 of 14‹12345›»
SCF Logo White

Two Stage Open Book Procurement delivered by the public sector, for the public sector.

  • Cookie Policy
SCF is a member of NACF, a national collective of regional frameworks which shares best practice expertise and experience.
© 2026 - Website by Blaze Concepts
Scroll to top Scroll to top Scroll to top