Dartington Primary School

Dartington Primary School

Dartington, Devon


Project Details



Client
Devon County Council

Contractor
Kier

Value
£6.9 million

Contract Period
17 weeks

Procurement Type
NEC3 Option A

Apprentices Employed
6 no. (2no with GT & Trac and 4 no. with supply chain – Roe, Halsion, PJE)

SME spend
85% and within LA catchment area 84%

Total added value benefits
£253,758

Following the completion of the demolition, the new build consisted of a new single storey building. The facility is completed with external landscaping and hard surfaces. The steel frame construction on a piled and concrete ground beamed foundation covers 2050m².

The external appearance consists of cladding and coloured rendered panels with the internals being constructed of metal stud partitioning and plasterboard to leave a decorative finish.



“One of the best projects we’ve ever received, if not, the best.”

Community Engagement

Events

  • CR Manager, Kate Ellis, worked with the Client team to organise numerous events at Dartington, including a mental health awareness workshop where Mates in Mind discussed the effects of stress in the workplace.

Learning Experiences

  • A time capsule was given to the school and a burial took place at the main entrance. The time capsule included hand print art work and poems about the pupils’ futures.
  • A local placement of two students were undertaken with a week’s work experience on site shadowing the site managers.
  • Two work experience places were provided on site with a female bricklaying apprentice and site engineer.
  • Sustainability was achieved on site through water butt harvesting rainwater for boot and tool cleaning purposes. Furthermore, a mock up spill incident was undertaken where students from Dartington were in.

Key Challenges

The logistics were carefully managed and planned due to the works taking place on a live primary school.

The vehicle access through the main gates were used by school users. To ensure that there was no disruption to the school or its users the access was carefully managed to ensure school users moved throughout the site safely by keeping it exclusive for school use between 8am and 9am and 3pm and 4pm.

Project Takeaways

Our Success

  • The heating strategy of the scheme is underfloor heating which is placed on insulation with a screed placed over the top. Despite the project being a traditionally procured scheme, the majority of the packages were CDPs therefore the site team and the supply chain worked over and above to deliver high-quality design solutions. The design was constantly monitored and reviewed, ensuring timely sign off was achieved. Good IRS and short-range design programmes kept the consultants and client informed of failings. The change control process was well managed by the team and they were able to make a good return on the changes.
  • The programme was driven by the client and the requirements of the school. For example, school opening dates were taken into consideration as well as the key milestone date of the removal of the temporary village – which Kier did and reinstated the ground back to existing / agreed levels.
  • £87,000 of VE was offered throughout the project, including the roof design and the attenuation tank construction, with a total of £72,000 being accepted by the client.

Our Learnings

  • The design for the roof changed due to value engineering from perforated liner construction to a solid roof sheet design. A man safe system is fixed to part of the roof allowing access to designated areas as per the Atkins design.

Value Added

KPI’s & Statistics

  • Contractor team performance: 10/10
  • Health and safety: 10/10
  • Quality of workmanship: 10/10
  • Progress in making good defects: 10/10
  • Collaborative approach: 10/10
  • Overall contractor performance: 10/10

Contact: James Parr
Email: james.parr@kier.co.uk

St Peter’s School RC Academy

St Peter’s School RC Academy

Bournemouth


Project Details



Client
Bournemouth Borough Council

Project Manager
Baqus

Architect
Cube Design

Contractor
Wates Construction

Value
£8.0 million

Contract Period
57 weeks

Procurement Type
Design & Build

Form of Contract
JCT 2011

Apprentices Employed
1 new start technical with SWSA

Project Brief

Phase 3C was part of an overall project that comprised 5 phases. St Peters School is a Roman Catholic Academy divided into 2 sites. The Iford site accommodates year 7&8 and the Southbourne accommodates the remainder of the school. The aim of the overall project was to merge year 7&8 into the Southbourne site so the overall secondary school is then located on one site.
Phase 3C New Build located in an existing school site, located on the schools existing sports field consisting of:

  • 3300sqm of teaching accommodation
  • 16 classrooms
  • Two art studios
  • Two science labs/classrooms
  • Dining hall and kitchen
  • Main hall
  • Changing facilities
  • Staff offices
  • Four multi use games area (MUGA) pitches
  • Associated landscaping
  • Staff car park


“The Wates team provided a superb service from start to completion of the project.”

Community Engagement

Education

  • Wates adopted St Peters School as part of Constructing Excellence Adopt a School initiative

Careers

  • Wates held a Building Futures employability programme
  • One new start technical apprentice with SWSA

Key Challenges

It was apparent at Mini Comp 2 that the budget was insufficient to meet the design aspiration so Wates carried out a full design review and redesigned the scheme to achieve the brief within budget. In addition, rationalisation of sport England requirements enabling significant savings.

The programme was extremely tight and was also dictated by school term times, therefore a clear schedule was planned and followed carefully.

Project Takeaways

Our Success

  • Works in existing school buildings were carried out outside school term to avoid disruption
  • Site logistics developed to ensure that the new construction works were completely isolated from the school operation and access to minimise disruption

Our Learnings

  • Cut and fill exercise carried out resulting in revised building levels minimising cart-away and omitted retaining wall by moving the building 3 metres.

Value Added

  • £8 million value building
  • Teaching facilities to accommodate 480 secondary school pupils

KPI’s & Statistics

Contact: Neil Channon, Framework Manager

Email: neil.channon@wates.co.uk

Thorn Turn Highways Depot

Thorn Turn Highways Depot

Houghton Regis, Bedfordshire


Project Details



Client
Central Bedfordshire Council

Project Manager
Central Bedfordshire Council

Architect
Atkins

Contractor
Morgan Sindall

Value
£18.7million

Contract Period
71 weeks

Procurement Type
Traditional

Form of Contract
JCT 2011 SFC / CDP

Size
2,795 square meters

Apprentices Employed
Two

Project Brief

The project consisted of the construction of a highways and waste disposal depot to service the maintenance requirements across the council’s highways whilst relieving pressure on the existing household waste and recycling centre (HWRC) nearby.

A new modular office was built to accommodate approx. 100 highways staff, a large tension fabric salt barn, a Highways Maintenance Dry store warehouse which enables the ongoing maintenance of fleet vehicles, whilst providing a suitable storage area for high value materials. The building was also fitted out with a small office provision for up to 10 staff. A refuelling area was also provided on the site.



“I am delighted that this ambitious project continues to progress so positively. We went through a highly competitive exercise to appoint them [Morgan Sindall] and were impressed with their ambitious vision for the new highways depot and household waste recycling centre.”

Community Engagement

Careers

  •  Two apprentices employed through the project

Key Challenges

  • At Gateway 2, we presented a very open and honest cost plan to give CBC sight of the initial deficiencies. We then worked closely with CBC on an extensive Value Engineering exercise, resulting in all four main buildings being taken on as CDP’s. By doing so, we were able to deliver the project in line with the Employers Requirements whilst offering considerable savings on the initial design. The VE exercise resulted in a saving of nearly £2m.
  • We provided accurate forecast figures for the main contract sum, which gave CBC confidence to issue a notice to commence for £3m to undertake initial earthworks ahead of bird nesting season – without this, the project start date would have slipped by six months.
  • Early engagement and involvement with CBC and Ringway Jacobs throughout the design phase of the S278 works enabled the programmes to run concurrently without causing delay to the programme.

Project Takeaways

Our Success

  • Employment and skills plan targets were exceeded
  • Full team collaboration from appointment to completion
  • Early and continued engagement with CBC fostering a good relationship with the client

Our Learnings

  • Interpretation of the end user requirements has meant that some areas of the site are not being utilised to their full extent, e.g. the vehicle wash bays and the vehicle maintenance store.
  • The project would have benefited from buildability input from Morgan Sindall during the design stage.

Value Added

KPI’s & Statistics

Contract
Gateway 2 PlanningGateway 3
Contract Agreement
Gateway 4 Completion
Cost£24,284,755£16,952,854£18,714,980
Time63 weeks63 weeks71 weeks
Value Engineering
Saving
Change construction of Salt Barn£300,000
Use alternative supply chain partner for Highways Depot£500,000
Change construction of Maintenance Shed£450,000

Apprentices: 2

Average AIR: 0

Average CCS score: 46 (out of 50)

Waste diverted from landfill: 99.95%

Contact: Tom Martin, MS Project Manager
Email: Thomas.Martin@morgansindall.com

Woodmansterne Secondary School

Woodmansterne Secondary School

Streatham, Lambeth

Project Details


Client
Lambeth London Borough Council

Project Manager
Faithful and Gould

Architect
Peter Taylor Associates Limited

Contractor
Willmott Dixon

Value
£21.3 million

Contract Period
48 weeks

Procurement Type
Two Stage Open Book Design and Build

Form of Contract
Jct 2011 Minor Works

Apprentices Engaged
5

BIM
Level 2 Construct

New 5 full education secondary school with 150 pupil sixth form. Works to be undertaken within the demolition area and consist of an RC Frame / Gebrik Cladding system and Glazing to the envelope, associated MUGA Pitches and external works and include the installation and removal of temporary classrooms.

Urban Beach Programme for Inner City Schools

Due to the temporary loss of access to the schools’ ecological area, the site team have developed an Urban Beach Programme to bring the coast to city pupils, raising their awareness of the coastal environment and the need to protect it. Woodmansterne school is the pilot for the Urban Beach Programme, and is partnered with the Marine Conservation Society, with Willmott Dixon fully funding the pilot programme by providing resources, staff and funding the coach trip to the Grain Coastal Park.

It is based on the Wildbeach programme developed by the wildlife Trusts and has been fully adapted to be delivered in inner city schools with the aim to get the children to the beach by the end of the programme. A new topic is introduced each week covering areas such as species ID, tides, human impact, food webs, marine processes and more.

The programme began with two year 3 classes of 30 and ran for 6 weeks, culminating in a field trip to the beach. The majority of the sessions are delivered in the school field to promote outdoor learning.

Local volunteers were sought through the Marine Conservation Society, providing an opportunity for anyone looking for a career in marine education.

The programme will continue with one of the volunteers taking over the project to deliver to the next year group selected by the school. The Marine Conservation Society is also looking out for the right candidate so this can be rolled out to other schools.

ContractGateway 2 PlanningGateway 3 Contract AgreementVariation
Cost£2,5532,4122 (£141.00)
Time48 weeks48 weeks0

KPI Graphs

Apprentices 5

Average AIR NIL

Average CCS score 47(out of 50)

Waste diverted from landfill 99%

Cost/m2 £3,1K/m2

Collaborative KPI 10/10


Contacts:

Guy Dawes
Framework Manager
Email: Guy.dawes@Willmottdixon.co.uk

Erika Buckenham
Framework Coordinator
Email: Erika.buckenham@Willmottdixon.co.uk