Archives

Yeovil Innovation Centre

Yeovil Innovation Centre

Yeovil, Somerset

Project Details



Client
South Somerset District Council

Project Manager
NPS South West Limited

Architect
NPS South West Limited

Contractor
Midas Construction Ltd

Value
£1.5m

Contract Period
40 weeks

Procurement Type
Competitive tender – 2 stage

Form of Contract
NEC3 Option A

Size
1,044m²

Project summary

The Yeovil Innovation Centre is an evolving business community designed for small businesses and entrepreneurs that require high quality, low-cost and flexible work spaces with room for growth. Supported by funding from the Heart of the South West Local Enterprise Partnership, Midas constructed this two-storey extension for client South Somerset District Council to expand the capacity and update resources at this multi-office facility.Located on Lufton Trading Estate to the east of Yeovil’s town centre, the Innovation Centre provides reception and meeting areas for tenants and entrepreneurs looking for the flexibility of short term leases. This extension offers over 1,000m² office accommodation across two floors. The structure is strip footing foundations supporting a portal steel frame, with a block and beam ground floor and precast first floor and roof, and raised access flooring installed to both floors. It benefits from brise soleil solar shading, with internal plasterboard finish that allows for future reconfiguration of the ground floor to meet the changing needs of tenants. Midas’ works included a lift, shell and core finish to the first floor, a single ply roof and landscaping. The project received a score of 96% in the customer satisfaction survey at practical completion.



“The perfect location to nurture and grow your business.”

Community Engagement


Career Development

  • 8 Apprentices through the project

Key Challenges


Budget: Early in the programme Midas’ market intelligence and cost benchmarking works identified a challenge, with the client’s design requirements exceeding their budget allowance. Midas’ commercial team worked closely with the client’s designers and our supply chain partners to deliver £550,000 of value engineering – including changing the structural frame, amending the window and natural ventilation configuration, amending hollow clay pot and lintel solution, and rationalising roof and gutter design – to make the project viable whilst achieving the client’s vision.

Occupied building: Prior to commencement, Midas established a secure construction site perimeter to segregate live works from the Centre, and erected full perimeter Heras fencing with solid hoarding to the front elevation and post and rail fencing to pedestrian routes. Midas liaised with the client in advance of works and completed noisy works at agreed times. The team implemented acoustic protection measures including forming two baffle bunds from soils excavated on site. The team restricted and segregated noisy works, managed the movement of plant, and situated cement mixers on the opposite side of the site from neighbours. The team held regular consultation meetings to update neighbours on the project; allowing one to one discussions and providing advance notice of noisy works to Centre staff. The team monitored noise, dust and vibration levels through the works and across the site. Contractors completed cutting works in designated areas and made sparing use of damping down to manage dust whilst restricting the site’s water use.

Live services: The project included demolition works to form a link opening to the existing structure, and service and utilities connections between the original building and the extension. Midas engaged early with the Centre’s management team and planned works in consultation with them. Thanks to the good relations with the client, the site team developed a mutually agreed programme. This ensured Midas could complete demolition, connection and security works during daylight hours, allowing time to address any potential issues. Midas installed a lockable partition early in the programme to segregate works and mitigate disturbance from noise or dust. The team then installed temporary works prior to commencing demolition to support the structural integrity of the façade whilst forming the structural opening. Midas brought new services to the edge of the extension and existing services to the connection point in the original building, before completing service connections overnight. This simplified the connection process, ensured services were not in use during works and prevented disturbance of the Centre staff.

Project Takeaways

Our Successes

  • Upon review of the original design specification, Midas identified that the ties to secure the steel frame to the Porotherm structural block were unsuitable. Midas raised a technical query and provided an advance warning to the architect, requesting a replacement and utilising more traditional brick ties as a solution.
  • Midas requested the precast concrete stairs be delivered with pre-cut pockets on the horizontal treads, so that the team could fit scaffolding bars directly into them when placing the sections on site. Midas then used these upright bars to connect handrails, providing a time-effective safety solution that avoided noisy cutting works on site and simplified the scaffolding required.

Our Learnings

  • The site experienced several weeks of high winds, followed by weeks of extreme unseasonal snow during February and March 2018. The inclement weather hit as the team were preparing to install precast concrete planks and the block and beam using a crane. Midas successfully mitigated the impact of the weather and delivered the project on time.

Value Added

  • Midas used a combination of best practice and added value solutions to deliver over £530k (35.5%) of client savings at practical completion Gateway 4. Midas worked with the client to complete a significant redesign of the superstructure at tender stage, including a reduction in floor area, to deliver £500k of savings. The team retained 1,800 tonnes of excavated soil on site, using it to form two acoustic baffle bunds and reusing the materials for base and landscaping for a saving of £22k.
  • The project supported the local economy with 96.2% of the total firms employed being SMEs, of which 40.7% were based within 30 miles of the site.
  • The team developed a Skills Plan for Yeovil college students, including a series of specific site visits and interactive events. The site employed apprentices from Yeovil College and supported two work experience placements through the site. The trainee site manager was a former Royal Marine, who Midas supported into a new career in construction. The team also developed local employment skills by advertising four jobs through local employment vehicles; delivering seven training plans, three supervisor training plans, one leadership and management training plan for subcontractors; and delivering four advanced health and safety training plans for subcontractors.

KPI’s & Statistics

ContractGateway 2 Planning Gateway 3 Contract Agreement Variation
Cost£2,117,646£1,474,292-£545,854 (-30.4%)
Time42 weeks36 weeks-6 weeks (-14.3%)

Apprentices: 8
Average AIR: 0
Average CCS score: 41
Waste diverted from landfill: 99.2%
Cost/m2: £1,574m²
Cost/m2: excl abnormals £1,453m²
Cost/m2: Industry average £ m

Loddiswell Primary School

Loddiswell Primary School

Loddiswell, Devon

Project Details



Client
Devon County Council

Project Manager
NPS South West Limited

Architect
NPS South West Limited

Contractor
Midas Construction Ltd

Value £2.4m

Contract Period
37 weeks

Procurement Type
Competitive tender – 2 stage

Form of Contract
NEC3 Option A

Size 890m²

Apprentices
3

Project summary

Situated in rural village surroundings, Loddiswell Primary School provides a welcoming and inclusive learning environment. The school is a 150-place, one form-entry single storey building with capacity to expand as the school grows. The school provides four classrooms, complete with interactive whiteboards and modern ICT equipment, a library, school hall and extensive outside space including a multi-use games area and playgrounds.

The building is timber frame with Structural Insulated Panels with a sectional roof, supported by glulam beams. The finished building features a 14kw PV array, larch weatherboarding and rubble stone walling, with an access road and car parking.Externally, Midas completed landscaping works and created a swale planted with wetland wildflowers as part of the Sustainable Urban Drainage Strategy, to help manage drainage, prevent flooding or run off, increase biodiversity and provide a source of natural interest for the pupils.The project scored 88% in the customer satisfaction survey at practical completion and received a CCS 2019 Bronze National Site Award.



“Our aim is to provide the best possible learning environment for all of the children in a caring supportive atmosphere.”

Community Engagement

Career Opportunities

  • Three apprenticeships provided through the project

Key Challenges

To address the power supply Midas installed air-source heat pumps, with a 14kw PV array on the roof. The building includes wind-catchers to increase natural ventilation, designed through the Building Physics strategy to meet requirements for natural ventilation, solar shading and natural daylight.

Midas implemented Structural Insulated Panel (SIPS) construction. This off site construction method is then fitted at the premises, enabling the team to make the building watertight sooner and resulting in a positive impact on the programme whilst also reducing waste, noise, dust and air pollution on site.

To manage the constrained access Midas restricted delivery vehicle size and scheduled deliveries to avoid rush hour and early mornings, directing site traffic to circumvent the village, and closely managed vehicle movements and timing to avoid disruption. The team reduced site movements by completing a cut and fill exercise, retaining 1,100m³ of excavated materials for the sports pitch and landscaping. The site team monitored the cleanliness of the access road, preempting the need for a road sweeper where necessary, and formed a tarmac car park within the site at the start of the project. Contractors used on-site parking to keep the residential roads clear and the vehicle controller monitored contractor parking to mitigate disturbance to the neighbours.

Project Takeaways

Our Success

  • The client requested several changes near the end of the project. Midas collaborated with them, the consultants and representatives from the school to adjust the programme to accommodate these works and still complete on the agreed date. Midas liaised frequently with these stakeholders to maintain a positive working relationship and accommodate the client’s requests.
  • The site team undertook extensive pre-start planning and consultation with NPS South West and the design team. The clients required the project to receive planning permission prior to them completing purchase of the land; Midas liaised with stakeholders at the preconstruction stage to collaboratively support the planning, in line with the philosophy of the SCF Framework, developing the design to maximise efficiency within the budget through an integrated team. Midas developed the cost plan and risk register with the client team to ensure a collaborative approach.
  • Midas invited representatives from the school to attend regular site meetings, keeping them informed on the progress of works. The team completed a sample room early in the programme, to use as a quality standard for subcontractors, to allow the client and end users to view the planned final standard and décor of the rooms

Our Learnings

  • The site experienced severe inclement weather during the winter and spring of 2017/18. To accommodate this, Midas liaised with the client and the school as a team to agree a solution. Midas completed works to the sports pitch, play area and gazebo at the end of the project during the school summer holidays, an adjustment that suited the school and enabled works to progress whilst mitigating the impact of the weather on the programme.

Value Added

  • Midas delivered over £90k (3.7%) of savings to the client by project completion Gateway 4, with a combination of best practice and added value reviews including: saving £15k through programme mitigation; and saving £56k through early contribution to the risk register and managing potential issues.
  • The project worked to the Employment Skills Plan, providing seven work placements for persons aged 16 or over; supported seven curriculum activities; advertised four jobs through local employment vehicles; supported three NVQ starters through subcontractors; completed seven training plans for subcontractors and supervisor training for one subcontractor; and provided advanced health and safety training for 21 subcontractors. The site provided four of the work experience placements through the ‘Step In Step Up’ careers campaign and subsequently made an offer of employment, with the candidate accepting a job with the site team.
  • The site employed 100% SMEs, with 61% of firms based within 30 miles of the project

KPI’s & Statistics

ContractGateway 2 Planning Gateway 3 Contract Agreement Variation
Cost£2,238,653£2,420,067-£40,300 (8.1%)
Time37 weeks37 weeks0 weeks

KPI Graphs

Apprentices 3
Average AIR 0
Average CCS score 41
Waste diverted from landfill 41%
Cost/m2 £2,793m²
Cost/m2 excl abnormals £1,948m²
Cost/m2 Industry average £ m

Contact:

Email:

Wincanton Primary School

Wincanton Primary School

Wincanton, Somerset

Project Details



Client
Somerset County Council

Project Manager
Faithful & Gould

Architect
Atkins Ltd

Contractor
Midas Construction Ltd

Value
£3.3m

Contract Period
43 weeks

Procurement Type
Competitive tender – 2 stage

Form of Contract
NEC3 Option A

Size 1,020m²

Apprentices
4

Project Summary

The client commissioned Midas to construct a two-storey, eight classroom teaching facility at a primary school in Wincanton to increase the school’s capacity and meet the growing needs of the community. The school’s ethos is to deliver high standards of education within a supportive and stimulating environment. The bright and colourful design of the new building provides a visually striking building with extensive play facilities.

The project team delivered inclusive activities to engage pupils and the community with the project. Events included hosting a time capsule and beam-signing ceremony; having twice monthly site visits from Wincanton Primary and local schools; and hosting students from the local college. The school invited the Midas team to judge their ‘Best Digger’ competition and Midas donated £150 as prize money to the school raffle. The project also won a CCS Silver 2018 National Site Award.

The finished building features educational, administration and associated spaces. Midas’ works included partial demolition of a shelter, fit out of the finished building and all associated utilities connections. The structure is steel frame with block and beam flooring, precast concrete staircases and a lift. Midas created gardens and a play area, completed soft landscaping and provided car parking facilities.



“Children will have had individual Learning Experiences throughout the year that will focus on the build and the construction, as well as having opportunities to make time capsules and be part of momentous ceremonies such as ”Ground Breaking” and ”Bolt Tightening” to mark the end of the project. “

Community Engagement

Career Opportunities

  • Four apprenticeships provided through the project

Key Challenges

The team managed the live educational site through effective collaboration with the school to coordinate the programme of works and schedule external and noisy works around lesson times and exams, timing significant works to occur during school holidays to mitigate disruption. Midas maintained close communication through weekly and ad hoc meetings with the school as required, and detailed restrictions in contractor toolbox talks and during site inductions, with daily monitoring to ensure workers complied with restrictions. The Midas team clearly set out site rules and requirements to all members of the supply chain, confirming site standards and providing recognition and rewards for good performance, and providing copies of the traffic management plan and logistics plan to all operatives. The site scheduled deliveries to avoid busy periods, with no deliveries permitted before 9am and avoiding the end of the school day, and noisy works restricted to the afternoon (3.15pm to 5.00pm) to avoid disturbing lessons.

To incorporate the request for additional works, Midas liaised with the school to agree a revised programme. The team implemented a countdown programme, completed additional hours and carried out quality checks during the works. The Midas team closely monitored contractors during the final stages of the project to ensure workers maintained safety standards during the busiest phase of the works, and maintained careful coordination of subcontractors. The team completed the total project, including additional works, to a high standard of quality and to programme.

To ensure safe installation of the mains electrical substation, Midas completed a ground penetrating radar survey, identifying routes of new and existing services, before compiling a Risk Schedule/ Register. Midas collaborated with SSE (the services supplier who relocated services and removed redundant cables) ensuring the project benefitted from early risk identification. The team encouraged stakeholder input during regular risk meetings, established “no dig” zones along known service routes to reduce risk, used trial pits and hand excavation and completed groundworks under permits to excavate. The team secured Heras panels around the works, with clear signage, and installed protective barriers within public highways during utility connections. At the start of the programme, the site’s power supply ran from generators (with back-up) before connecting into the new mains following installation of the substation. Following this, Midas worked around live services, identifying and removing redundant services in association with SSE.

Project Takeaways

Our Success

  • The school is situated halfway around a one-way system, with a bus stop directly outside and residential premises and commercial businesses in proximity. The school remained live during periods of the project, presenting a significant logistical challenge. Midas created a detailed, bespoke traffic management plan to avoid adversely affecting the neighbours and the local industry, and employed a full-time traffic marshal to supervise site access, ensuring site traffic and parking did not block buses or local access, and managing deliveries. The team installed airlock-type inner Heras gates, to allow delivery vehicles to pull off the public highway into a holding area, performed vehicle safety checks on arrival and departure from site, considered vulnerable road users in the logistics plan, and planned delivery routes to reduce left-hand turns in accordance with Construction Logistics and Community Safety (CLOCS) initiative requirements.
  • The project manager issued weekly ‘Look Ahead’ newsletters for the school, providing details of works completed in the previous week and works planned for the forthcoming week, including warnings regarding potentially noisy works. These regular communications engaged the pupils and local community in the project and contributed to site safety.

Our Learnings

  • The client’s representative raised a concern regarding the fitting of the rainscreen cladding. To assure them that the cladding had been installed safely and correctly, Midas organised a site inspection with a meeting between the representative and the cladding manufacturer. This inspection confirmed the cladding had been safely and correctly installed.

Value Added

  • Midas delivered over £164k of savings for the client by practical completion Gateway 4, through a combination of best practice and added value solutions including drawing on specialist contractors to provide £125k of savings through design advice and alternative products.
  • The site employed 100% SMEs including seven local firms that formed 36.3% of the workforce on the project.
  • The team held regular site visits for the school pupils, providing updates on the site progress to the children, with weekly ‘Look Ahead’ newsletters and progress photos provided for the school’s website. The site manager organised hand-delivered copies of the monthly newsletter to 50 residences and businesses in the local area, and the site held weekly ‘Through the Fence’ presentations for up to 70 pupils at a time, with Wincanton Primary and other local schools. These presentations included safety awareness and progress updates. Midas made presentations to parents during a school fete; donated £150 as prize money for a school raffle; and judged the school’s ‘Best Digger’ competition

KPI’s & Statistics

ContractGateway 2 Planning Gateway 3 Contract Agreement Variation
Cost£3,229,311£3,250,840£21,529 (0.7%)
Time37 weeks37 weeks0 weeks

KPI Graphs

Apprentices 4
Average AIR 0
Average CCS score 42
Waste diverted from landfi ll 93.7%
Cost/m2 £2,995m²
Cost/m2 excl abnormals £2,342m²
Cost/m2 Industry average £ m²

Ashmole Primary School

  • Client

    ESFA

  • Contractor

  • Value

    £7.5m

  • Completion Date

    November 2018


A new-build 2FE school to provide a permanent new home for Ashmole Primary School. The school  created 420 places for pupils aged four to 11 and provides teaching space for KS1 and KS2 along with offices, a sports hall, a community room and a canteen.


The Challenge

The school was built on a land-filled site with debris built up from previous excavations in the local area. The ground was found to contain asbestos and obstructions. The risk was quantified and a management strategy was put in place to remove the asbestos and obstructions from the site. This put significant pressure on the project programme.

The Solution

The use of SIPs achieved a 10 week programme saving during the pre-construction phase and a five week programme saving during the construction phase of the project. This has led to SIPs being used on subsequent SCF and Morgan Sindall projects. The frame, including the roof, floor and walls, was installed in 13 weeks, which is a significant saving compared to traditional construction methods.

The Results

The use of SIPs achieved a 10 week programme saving during the pre-construction phase and a five week programme saving during the construction phase of the project. This has led to SIPs being used on subsequent SCF and Morgan Sindall projects. The frame, including the roof, floor and walls, was installed in 13 weeks, which is a significant saving compared to traditional construction methods.

91.5%


SME Spend

£252k


Added Value

9/10


Client Satisfaction

Client Testimonials

The on-site management team’s highly professional and collaborative approach enabled the new building to be completed on a demanding programme to a high standard of quality ready for the school to occupy

Contractor Performance | Commitments


Fair

100% payment within 30 days terms


Sustainability

98% waste diverted from landfill

100% timber responsibly sourced


Safe

Zero RIDDORs

CCS Score 39/45


Legacy

7 work experience placements

94 apprenticeship weeks

£5k charitable donations

23 SMEs


Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times

SCF Framework Manager

James Wright

Email: james.wright@hants.gov.uk

Phone: : 07761 330560

Contractor Framework Manager

Alan Smedley

Email: alan.smedley@morgansindall.com

Phone: 07967 686066

Polden Bower School

Somerset

  • Client

    Somerset County Council

  • Contractor

  • Value

    £16m

  • Completion Date

    May 2021

Project Manager
Aecom

Architect
AWW

Civil Engineer
Services Design Solution

The Challenge

A challenging site that had to battle flooding after a string of winter storms, the team involved have overcome numerous obstacles to deliver the school successfully to Somerset County Council.

The team had to undertake a major value engineering process, which led to a substantial redesign to bring the project in to budget, as well as building on a site with significant drainage issues.

The team designed a bund to provide acoustic protection for the school from the neighbouring motorway (M5), all while maintaining strong and collaborative working relationships between all parties.

However, Willmott Dixon are experts in navigating complex and challenging builds, finding solutions and making sure the works carried out meet expected requirements, so we were able to successfully deliver the project to a high standard.

The Solution

Construction of a new 160 Place All-Through Special Educational Needs School (SEN) with administration facilities, hydrotherapy pool, sensory areas, carparking and other required facilitating and external works on greenfield land. Also include the construction of a spine road to facilitate access to the new school.

The Results

Willmott Dixon’s team of education specialists have constructed a state of the art, new two-storey SEN School in Bridgwater creating 160 school places, bringing pupils from two existing sites under one roof.

The new all-age school includes accessible classrooms, dining hall, sports hall, sensory and therapy rooms and a hydrotherapy pool. Outside a sensory garden, multi-use games area and adventure playground will provide lots of spaces to support the pupils’ physical and sensory needs.

5


Apprentices

95.7% were local


SME Spend

£3.8m


Added Value

9/10


Client Satisfaction

Client Testimonials

“ These are the next steps in ensuring we have the right provision in the right places for Somerset’s children.  We always do all we can to support children with SEND to attend mainstream school where this is appropriate and also make sure that those with the highest level of need have the right provision. These projects will ensure that children with all levels of need can be educated close to home in their own communities.”

Contractor Performance | Commitments


Fair

99% prompt and fair payments


Legacy

  • 20 work experience placements
  • 12 local jobs created
  • 19 construction careers information, advice and guidance events
  • 4396 hours spent dedicated to construction support, mentoring and training for both under 24s and over 24s
  • Apprentices spending 585 training weeks on site
  • 30 construction qualifications gained
  • 21 hours in school doing H&S assemblies and site visits
  • 658 hours spent on other initiatives across the community (legacy projects, support with qualifications, community engagement)


Safe

Zero Harm


Sustainability

97% waste diverted from landfill


Aftercare

Handover & Aftercare Contractor Promise

SCF Framework Manager

Kingsley Clarke

Email: kingsley.clarke@devon.gov.uk

Phone: 07805760622

Contractor Framework Manager

Guy Dawes

Email: guy.dawes@willmottdixon.co.uk

Phone: 07989 179444

St Michael’s Catholic School

St Michael’s Catholic Secondary School

Aylesbury, Buckinghamshire

Project Details



Client
Buckinghamshire County Council

Project Manager
WYG

Architect
BAM Design

Contractor
BAM Construction

Value
£24.6 million

Contract Period
68 weeks

Procurement Type
Design & Build

Form of Contract
JCT 2017

Apprentices
9

Project Summary

BAM built Buckinghamshire’s first ‘satellite’ school in Aylesbury – an extension of St Michael’s Catholic Secondary School, High Wycombe, which opened in September 2019. 

The satellite plan, a partnership between the county council, St Michael’s governors and trustees, and the Diocese of Northampton, caters for 900 students aged between 11 and 19. The new school is based on the former Quarrendon School site, where there is a Bucks CC Adult Education Centre, a pre-school and youth club. There is also a Multi-Use Games Area (MUGA), a grass pitch and 3G all-weather pitch. The new building and grounds will be available for community use outside school hours. This includes main assembly hall and sports facilities. 



“I have been in this job with building schools and refurbishing for nearly 30 years and this was both the most impressive site I’ve seen.”

“BAM have been proactive in progressing the design. They have fully understood the project brief and the vision for the school. They have worked well with the end user and have managed their expectations throughout the design development stage.”

Community Engagement

Career Opportunities

  • Five apprentices came through the project. One was direct for BAM as a QS, two from the Cotrain, and two other apprentices from the electricians and plumbers
  • Short term work placements were provided as part of Getting into Construction Programme with the Prince’s Trust.
  • Two presentations were given to careers leaders in conjunction with Bucks Skills Hub and Amazing Apprenticeships.

Educational Aspects

  • School visits were arranged for Year 7 pupils currently attending the school.
  • There were site visits for Bucks UTC and West Herts College as part of Open Doors 2019.

Community & Residence

  • Regular meetings were held with the local resident’s association.
  • The site team attended the Bucks County Council Apprentice Roadshow, Bucks skills Show and Big Bang @ Bucks.

Local Supplies

  • Timber was separated and collected by RAW Workshop based in Oxford. The timber was either sold, made into products or chipped for use. The initiative employs those that are furthest from the job market. The spend on this social enterprise was £6840 – 379 cubic yards of waste timber of which 77% was recycled, 23% was reused.

Key Challenges

The project had a tight programme, with completion in 68 weeks. Working with our in-house disciplines BAM Design, BAM Plant and BAM Services Engineering, allowed us to improve the speed and efficiency of how the project was managed and delivered on site. The project was designed in a 3D environment under BIM level 2 requirements. The BIM execution plan was discussed in detail with the client upfront to understand exactly what the client wanted, and to minimise costs.

Extensive groundworks were required at the start of the project due to heavy clay. A decision to use piled foundations and ground remediation reduced the construction risk on site.

Project Takeaways

Our Success

  • Lessons learned workshop early within design process to iron out potential design, buildability and operational issues.
  • Early contractor appointment essential to ensure robust affordable design prior to planning submission. The team worked hard to achieve this ahead of planning.
  • Fully transparent cost management built trust and confidence early on.
  • Complex highways / utilities works outside the red line to have dedicated management to ensure timely close out of issues.

Our Learnings

Value Added

  • BAM delivered £290K of added value benefits during the design development process.
  • 100% of waste was diverted from landfill i.e. through segregation of waste on site and recycling. Eco cabins used onsite to reduce power usage on site.
  • Sustainable design using PV panels, natural ventilation and LED lighting saving energy and running costs.
  • Fully federated digital models saved time and cost. We integrated our supply chain design models; used clash detection software to iron out issues prior to manufacture. This reduced any potential down time / abortive works providing programme certainty.

KPI’s & Statistics

ContractGateway 3 Contract FormationGateway 4 Final AccountVariation
Cost£24,642,019£24,613,801£28,218 (saving)
Time68 weeks68 weeksNil

Contact: Darren Birch, Framework Manager

Email: dbirch@bam.co.uk

Oakmoor School

  • Client

    Hampshire County Council

  • Contractor

  • Value

    £23m

  • Completion Date

    November 2019

The Challenge

The school, previously known as Bordon Secondary School needed to meet the requirements of 900 school places and relocate from the eastern side of town to a more central location for children in both Bordon and neighbouring Whitehill. In 2015, Bordon and Whitehill were selected by the NHS’s Healthy New Towns scheme in hopes to develop a healthier environment, a strong sense of community and better care services within the local area. It was therefore imperative that the new school included facilities that would boost the children’s well-being.

Due to constricting budget restraints, it was crucial that Kier worked closely with Hampshire County Council’s team and maintained consistent communication throughout the project to help bring their dream school to life.

The Solution

In order to create a modern and cohesive learning environment that satisfies the councils’ design, a proposal was approved for a collegiate style campus with four separate buildings connected by a central courtyard. This courtyard was intended to be a social and teaching hub, therefore encouraging a positive and well-connected community.

As part of the town’s Healthy Living Masterplan, extensive consultation with Sport England was carried out to devise a diverse range of facilities that could be used by the children all year round, therefore encouraging activity. The school was built in an area easily accessible for residents of Bordon and Whitehill, acting as a gateway to intertwine the communities.

To prioritise sustainability, the project adopted a low-energy, fabric-first strategy by making the most of the surrounding and historical Woolmer Forest. This resulted in the school possessing beautiful views of nature, boosting student and faculty morale. Additionally, a large expanse of PV panels on the southern teaching wing’s roof provides 10% of the school’s energy requirements.

The Results

The new Oakmoor School is a modern building with two-storey teaching wings spanning from the central courtyard, with school halls and sports halls at either end. The covered courtyard effectively reduces internal floor area and prevents the corridors from becoming overcrowded. Additionally, entrances to teaching wings are defined by staircases, once again minimising the volume of students within corridors. Passing through the courtyard promotes a healthier lifestyle as students and teachers will get a breath of fresh air while traveling easily between classes.


86.4%


SME Spend

£362,000


Added Value

8.6


Client Satisfaction

Contractor Performance | Commitments


Fair


Sustainability

10% energy requirements from green energy


Safe

Zero RIDDORs


Legacy

900 academy places


Aftercare

Handover & Aftercare Contractor Promise

SCF Framework Manager

James Wright

Email: james.wright@hants.gov.uk

Phone: 07761 330560

Contractor Framework Manager

James Parr

Email: james.parr@kier.co.uk

Phone: 07794218011

Oceansgate

Oceansgate

Plymouth, Devon

Project Details



Client
Plymouth City Council

Project Manager
AECOM

Architect
Form Design Group

Contractor
Midas Construction Ltd

Value £6.1m

Contract Period
63 weeks

Procurement Type
Competitive tender – 2 stage

Form of Contract
JCT Design & Build 2011

Size 3,000m²

Apprentices
13

Project Summary

Oceansgate is the UK’s first marine enterprise zone, occupying a 35 hectare site on the southern edge of Devonport Dockyard, one of the largest naval dockyards in Europe. Delivering new opportunities and economic regeneration to a deprived area of Plymouth, Oceansgate has transformed derelict land into a site that aims to bring together marine-based businesses to create a world-class hub for industry. The development, designed by local architects, uses a layout and materials that
reflect the area’s naval history.

The project features a three-storey office and two single-storey industrial terraces, arranged in parallel rows and offering nearly 3,000m² of office and industrial space with provision for up to 21 businesses. Completed to a high standard, the finished buildings are steel portal frame with brickwork and blockwork, curtain walling and power floated concrete slabs; they feature fibre connectivity and internal floor layouts that can be subdivided to suit tenant requirements. Externally, Midas completed car parking, access roads and planting to improve the site’s appearance and ecology.

The development has been shortlisted in the ‘Regeneration’ category of the 2019 South West RICS awards and was shortlisted for ‘John Bracey Building of the Year’ in the 2018 The Building Forum Awards.



“Oceansgate occupies a 35 hectare site on the southern edge of Devonport Dockyard, one of the largest naval dockyards in Europe.”

Community Engagement

Career Opportunities

  • Thirteen apprenticeships provided through the project

Key Challenges

Prior to commencement of works, Midas reviewed all Ordnance Survey maps of the area and commissioned a ground penetrating radar scan of the site for unexploded ordnance, as Devonport Dockyard was heavily targeted for bombing during World War Two. During excavation works the team discovered several voids including basements, bank vaults and foundations of buildings destroyed during the Blitz. Midas pumped 400 tonnes of Type 1 granular fill compactable material into the holes, solid enough for the 55-tonne crane to sit on, and filled other excavations with concrete. The site fenced off excavations, with a vehicle controller in place to guide operations of plant and excavation machinery, and tested the ground for stability before each stage of the works. The team completed excavations under close, careful management, utilising remote compactors over the arches and basements to avoid risk to operators.

Midas joined this design and build project at RIBA Stage 2. The innovative design included use of a kinetic wall to reflect light and move with the wind, and random rubble stone cladding to some elevations. Midas constructed the kinetic wall, which is nearly six metres wide and over seven metres high, with 1,786 aluminium shingles affixed to steel wires attached to a full-height screen over the main entrance. It is the first of its kind in the west country and provides a distinctive feature of the development. Midas completed and connected the gable ends of the buildings early in the project, adjusting the programme to mitigate this requirement and completing the gable ends as soon as possible to make the buildings watertight and enable progression of interior works. Internally, the structural grid and division walls were designed to be easily combined to provide larger floor plates to respond to market interest.

Midas successfully achieved BREEAM Excellent through provision of bicycle storage; attaining a lower Building Emission Rate than the Target Emission Rate; and installation of one bat box, one bird box and one bee brick on each building. Midas fitted a PV array to the roof of the office, with an estimated annual generation of 19,616.00kWh and a declared net capacity of 20.00kWh. The team also planted verges and trees, improving the site’s ecology, and achieved a 98% recycling figure, with demolition waste sent for reprocessing and reuse.

Project Takeaways

Our Success

  • Midas liaised with the neighbouring Ministry of Defence (MOD) site in advance of commencing works to coordinate logistics and ensure the site kept MOD access clear at all times. The site employed several gate controllers and traffic managers to ensure safe site access, with radio-linked site management teams.
  • The site contained multiple underground services, including a gas governor and electrical transformer. During excavation works the site team uncovered more than 130 services, not included on any plans or surveys, including underground external drainage. The team hand dug excavations to expose cables and arranged for the isolation of services, with utilities proved dead before works proceeded. Midas included a service grid system over the site survey, overlaid on a plan of the new buildings.
  • The project had restricted site access that presented challenging logistics, which had a significant impact on the construction programme. Midas mitigated this by utilising weekend working and employing a high volume of staff, including increasing the number of managers on site.

Our Learnings

Value Added

KPI’s & Statistics

ContractGateway 2 Planning Gateway 3 Contract Agreement Variation
Cost£5,809,000£5,425,000-£384,000
(-6.6%)
Time48 weeks48 weeks0 weeks

KPI Graphs

KPI Graphs Apprentices 13
Average AIR 0
Average CCS score 40
Waste diverted from landfi ll 98.9%
Cost/m2 £3,837m²
Cost/m2 excl abnormals £3,017m²
Cost/m2 Industry average £ m²

Nexus Training and Production

Surrey County Council

  • Client

    Surrey County Council

  • Contractor

  • Value

    £40m

  • Completion Date

    February 2019

Architect
HGP Architects

Civil Engineer
Lyons O’Neill

The Challenge

As part of its global expansion, L3 commissioned a new £40m training and production facility on a site owned by Surrey County Council just a few miles from Gatwick Airport. The Nexus Training and Production Facility is critical for the UK’s aviation industry, as it will attract huge amounts of inward investment.

Engineering solutions were required due to the ground contamination and temporary works were needed on the existing retaining wall which made meeting the programme end date a challenge.

The Solution

Willmott Dixon deployed a team of commercial building specialists to create the exact conditions needed for the fixed-based simulators as well as briefing rooms, classrooms, meeting rooms and a restaurant.

To meet the challenge of having a fully operational facility by summer 2019 an experienced management team were on hand to ensure any requests for changes were accommodated and fitted into a complex building schedule, making sure the 60,000 square foot facility came in on schedule.

The Results

The project involves creating two rather special buildings. The first is a global centre for excellence in airline training and houses eight flight simulators, each costing £12m. It also includes a number of fixed-based simulators plus briefing rooms, classrooms, meeting rooms and a restaurant.

The second building, opposite, is a similarly sized facility to manufacture 30 simulators a year and be a base for more than 300 employees.

6


Apprentices

96.8


SME Spend

£5.6m


Added Value

9/10


Client Satisfaction

Client Testimonials

“We’re proud of our legacy  in Sussex with completing Nexus on time and on budget helping L3 realise its growth in the Gatwick area, as well as provide opportunities to help attract and retain the next generation of workers in the county.”

Contractor Performance | Commitments


Fair

99%


Sustainability

Waste diverted from landfill: 99%

Solar power was used to power temporary site accommodation


Safe

Zero Harm


Legacy

Shortlisted for LABC awards 2020

Safety tours undertaken on for local school children


Aftercare

Handover and aftercare process followed

SCF Framework Manager

Kingsley Clarke

Email: kingsley.clarke@devon.gov.uk

Phone: 07805760622

Contractor Framework Manager

Guy Dawes

Email: guy.dawes@willmottdixon.co.uk

Phone: 07989179444

New Addington Leisure Centre

London Borough of Croydon

  • Client

    London Borough of Croydon

  • Contractor

  • Value

    £33.7m

  • Completion Date

    March 2020

Civil Engineer: Enginuiti

Architect: GT3

Project Manager: Gleeds

The Challenge

The new multi-level site was designed to transform the western side of Central Parade in New Addington, Croydon to provide community spaces, state of the art sports facilities and eight new family homes running parallel with the swimming pool, separated only by a considered designed structural wall.

Local businesses needed to maintain ‘business as usual’ so Willmott Dixon undertook and deployed a extremely detailed logics phased plan.

The Solution

The new flexible space features two multi-purpose halls, a cafe, meeting rooms, offices and dressing rooms, with an option of licence applications for booked events.

The facility provides:

  • Community Halls
  • Community Cafe
  • Six lane 25 m pool with spectator seating for up to 150 people
  • Learner pool
  • Wet changing village
  • Large fitness gym incorporating a spin studio
  • Dry change facilities
  • Multipurpose studios (Fitness and community)
  • Indoor four court sports hall with associated changing facilities
  • Public realm upgrades

The Results

Overall, the project helped create over 75 jobs for local Croydon residents and was where Willmott Dixon held their first Building Lives Academy. This was an initiative to upskill young people in Croydon and provide them with valuable construction experience and gain qualifications within the industry.

The development has provided high quality leisure and community facilities which is a significant improvement on the previous facilities in the area.

The project won the RICS Social Impact 2020 award in recognition of the positive impact Building Lives has made on the community.

The team also helped facilitate the Christmas lights switch on in New Addington, not only donating funds to the charity but helped create their own Santa’s Grotto in the local community.


4


Apprentices

96.2%


SME Spend

17.7%


Added Value

9


Client Satisfaction

Client Testimonials

This is a stunning new centre with first-class facilities for everyone in New Addington to enjoy and be proud of. It will make a huge difference to our local community, helping them to keep fit and stay healthy while giving them a new venue to enjoy with family and friends.

Contractor Performance | Commitments


Fair

Regular payments and have payment periods not exceeding 30 days


Sustainability

99% of waste diverted


Safe

CCS Score 40


Legacy

RICS Social Impact 2020 award won in recognition of the positive impact Building Lives has made on the community.

Helped facilitate the Christmas lights switch on in New Addington. The team not only donated funds to the charity but helped create their own Santa’s Grotto in the local community.


Aftercare

Handover & Aftercare Contractor Promise

SCF Framework Manager

James Wright

Email: james.wright@hants.gov.uk

Phone: 07761 330560

Contractor Framework Manager

Guy Dawes

Email: Guy.Dawes@Willmottdixon.co.uk

Phone: 07989179444