Archives

Littlehampton Leisure Centre

Sussex

  • Client

    Arun District Council

  • Contractor

  • Value

    £17m

  • Completion Date

    March 2019

littlehampton wave

The Challenge

The replacement leisure centre was built on the same site as the existing leisure centre, which meant one of the biggest challenges was ensuring that there was minimal disruption to the leisure centres operations.


The Solution

To minimise disruption to leisure centre members, the construction was phased, and the new Leisure centre was constructed before the existing building was demolished.

The new leisure centre comprises wet & dry facilities including 8 lane 25m swimming pool, 4 court sports hall, 80-85 station gym, studio capacity of 50 with flexibility and a learner swimming pool.


The Results

Littlehampton was opened on time and to budget with a high standard of finish, exceeding expectations of customers and Freedom Leisure who are responsible for managing the leisure centre in partnership with Arun District Council.

The project was shortlisted for two LABC Regional Building Excellence Awards 2020

1) Best Public Service or Educational Building and

2) Best Large Commercial Project in the LABC Regional Building Excellence

Once opened to the public, membership applications increased c200% outperforming forecasted targets.

gym equipment

12


Apprentices

95.6%


SME Spend

22%


Added Value

9/10


Client Satisfaction

Contractor Performance | Commitments


Fair

99% of regular payment periods did not exceed 30 days


Sustainability

97% of waste was diverted from landfill


Safe

Zero harm


Legacy

Local work placements, trainee and graduate placements and apprenticeships, along with creating new jobs in the local area.


Aftercare

Handover & Aftercare Contractor Promise

Fulham College Boys’ School, London

  • Client

    Fulham College Boys’ School / Department for Education

  • Contractor

  • Value

    £13.75m

  • Completion Date

    May 2021

The Challenge

The scope included major renovation of a live secondary school, enhancing teaching provision for its transition to a STEM specialist Academy. The works were scheduled over three phases.

Phase 1: The transformation of Block L (the existing drama building) for use as the site team’s welfare and site offices; internal reconfiguration of the second floor of the Childerly Building providing an additional classroom; provision of 3 working labs and 2 standard classrooms.

Phase 2: Demolition and subsequent construction of a two-storey, steel framed science block providing six new teaching labs. The building includes a green roof, PV panels and attenuation tank.

Phase 3: The extensive refurbishment of the Grade II listed Kingwood Building including asbestos removal, MEPH systems, window replacement, decoration and carpentry works.

The Solution

It was recommended to the client that Block L (which was due to be demolished) be utilised as the site office and canteen space. This not only saved the project money in site setup costs and omission of the Block L demolition works from the scope of works, but furthermore, the making good of the building provided the school with a new space for music classes.

With three separate handovers, it was imperative that a good relationship was maintained with the school staff. Consideration and understanding were incorporated into the safe planning of works and scheduling of deliveries to allow the live school to continue to operate. The use of temporary modular classrooms accommodated students away from the works thereby ensuring minimal disruption to the overall learning environment.


The Results

Three successful handovers to a delighted client, helping to realise the school’s transition into a specialist STEM Academy. The first phase was completed on time, the second phase was handed over two weeks earlier than expected, and the third phase of works was also completed on time.

–


4


Apprentices

93.1%


SME Spend

£840k


Added Value

9/10


Client Satisfaction

Client Testimonials

“In my role as Trust Senior Site Manager, I led on behalf of liaison with the school and can happily report that Morgan Sindall have proven to be the most efficient, cooperative and enjoyable construction company I have had the pleasure to work with in my 20 years’ experience. From the early design stage right through to completion, communication between the school and Morgan Sindall has been second to none.”

Contractor Performance | Commitments


Fair

100% payment within 30 days terms


Sustainability

91% waste diverted from landfill

100% timber responsibly sourced

BREEAM Very Good


Safe

Zero RIDDORs

CCS Score 43/45 nominated for 2020 Award


Legacy

14 apprenticeships, 6 of which were new jobs created

7 work experience placements

272 Trainee weeks

Schools engagement: 361 pupils


Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times

Pembroke Road Waste Transfer Centre

  • Client

    Buckinghamshire Council

  • Contractor

  • Value

    £8.06

  • Completion Date

    October 2020


Project Background

Buckinghamshire Council’s existing waste and recycling services depot on Pembroke Road, Aylesbury has been expanded to cater for the local population growth. The local Council identified the need to plan for and accommodate growth within the Aylesbury Vale district over the next 10 years and relieve associated pressures on the existing waste and recycling services.

This has culminated in the Morgan Sindall team working closely with the Council to reconfigure the layout of the existing depot to optimise the site and to mitigate environmental impacts, the project was procured through the Southern Construction Framework.



The Challenge

Challenges of the redevelopment centred on the need to maintain the operation of the existing facility which entailed the works being undertaken over several phases and the fact that the site is bounded to the north and the south by two small rivers which have a history of flooding.

Towards completion of the project the Bear Brook river had already broke its north bank causing flooding across the site where defence measures were tested and successfully combined to prevent any flooding inside the new buildings.

The Solution

The contract works were divided into an initial demolition enabling works package followed by two sectional completions to accommodate the different phasing of the site works. The first being the construction of a new 699 sqm commercial vehicle MOT workshop with vehicle repair and service facilities for both local taxi drivers and the depot’s own Rigid Vehicles fleet which will bring about additional revenue for the depot.  The second phase provided a new 1825 sqm Waste Transfer and Recycling Station with a modern fire suppression canon system serviced by a 125,000-litre tank. The new buildings were supplemented with the upgrade of external slabs and wayfinding pedestrian routes with allocated fleet vehicle and staff parking areas. Specialist equipment provision included a new weighbridge, 2no industrial carwashes and a 45,000litre refuelling zone.

As part of the flood defences, we also provided a bespoke metal flood barrier system designed to be installed across each door and roller shutter opening.


The Results

The successful completion of the project culminated in the merging of the new and upgraded existing areas to provide a state-of-the-art depot ready to support the growing population needs of the Aylesbury Vale district.


3


Apprentices

58%


SME Spend

£655k


Added Value

10/10


Client Satisfaction

Client Testimonials

Having worked with Morgan Sindall on previous projects, I was pleased to be working with them again. In my experience, Morgan Sindall’s working ethos has ensured a well-presented safe site, with experienced personnel to deliver projects successfully. Pembroke Road depot is an operational site, with Morgan Sindall’s well-informed phasing and site constraint considerations, both the construction work and service delivery has been able to continue seamlessly. During the challenging and evolving Client Brief and timescale, Morgan Sindall have demonstrated an excellent collaborative approach. Honest and open dialogue and sharing respective points of view has allowed us to arrive at Contract Award with a positive team ethic.

You have all been agile in your approach to ensuring our onsite operational needs are considered and remain unaffected by the project. We often do not know you’re working on site – it can’t get much better than that!”

Contractor Performance | Commitments


Fair

100% payment within 30 days terms


Sustainability

99% waste diverted from landfill

100% timber responsibly sourced


Safe

Zero RIDDORs

CCS Score 41/45


Legacy

15 No of SMEs – 18 beneficiaries – 6 jobs created

154 apprentice trainee weeks, 16 Work Experience students, 130 students engaged

£300 donations to charity & £8,650 community investment project

£2.38 LM3 – 103% social value created


Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times

Any site specific process/initiatives

Amersham Secondary School

  • Client

    Buckinghamshire Council

  • Contractor

  • Value

    £6.4m

  • Completion Date

    August 2021


Project Background

The expansion of Amersham School was carried out within a live school campus, over three phases of works, and comprised: a new 27-space car park and landscaping works; the construction of a double-storey extension featuring a new dining hall, reception area, and eight classrooms forming a new maths block (Block N); extension of an existing science block to provide additional teaching space (Block E).

Although not an employer requirement for the scheme, our design team developed the design in BIM to provide a high degree of design co-ordination throughout the Stage 4 design development.

–

The Challenge

Overcoming of a number of challenges was crucial to the successful outcome of the scheme. This included undertaking the works within a live school, restricted space to manoeuvre when completing areas of detail, working towards completing facilities to achieve critical phased handover dates whilst, additionally, the COVID-19 pandemic had swept its way through sites across the country.

Another was the discovery of unexpected urgent remedial works required to areas of masonry support on the existing building, which hindered and delayed progression of works. As it was unsafe to work underneath the concrete beams that supported the concrete blocks, the remediation works consumed many weeks of programming.

The Solution

Overcoming the various challenges on site required careful and considered planning, excellent communication, understanding and innovative methods of working.

Communication from all parties associated with the project was critical, particularly throughout term times, to ensure safety measures were in place to protect students, staff and members of the public.

Masonry remedial works were carefully considered, being struck down and re-built with engineering bricks and a concrete lintel to hold the structure of the loads, which provided its structural integrity.

Re-sequencing of work packages played an important factor to maintain progression to the job and was demonstrated by prioritising Block E works located in an existing block, which would continue to operate during school term whilst the refurbishment works continued. This strategy proved beneficial as, after Block E was handed over to the school, we were then able to prioritise works to the main Block N new build.


The Results

Successfully carried out within the live school environment, this much needed scheme saw the introduction of new and improved facilities, providing students and teachers with a first-class learning environment to serve future generations of learners.

At the Buckinghamshire College Group’s Student Awards Ceremony in June 2022, Morgan Sindall was awarded ‘Employer of the Year’. The nomination by Industry Placement Officer, Nicola Hieatt, was as follows:  ‘’Our partnership with this employer began late last year. During this academic year they have provided Buckinghamshire College Group construction students with over 500 work experience hours, careers sessions, help with CV writing, week-long virtual work experience projects, industry insight days not only for students but staff as well.

Their staff are always courteous and welcoming to students and regularly take time out of their working days to carry out safe site tours and offer advice. The construction students have been extremely lucky to have been given the opportunity to work alongside these professionals.  On a more personal note, our contact Norma Odain-Hines [Morgan Sindall Community Investment Manager, London & Home Counties] repeatedly goes out of her way to include the students in the site development in every possible way. We will certainly miss her dedication once the Buckinghamshire project is complete.

4


Apprentices

96.6%


SME Spend

£680k


Added Value

7/10


Client Satisfaction

Client Testimonials

“The MS site team have been very good to work with throughout the contract. Any issues that have arisen have been dealt with and we have not had any calls from the Principal”.

Contractor Performance | Commitments


Legacy

14 SMEs, 28 beneficiaries

6 jobs created, 172 trainee weeks and 277 students engaged

£11,750 donations to charity, 227 volunteer hours

78% social value created


Fair

100% payment within 30 days terms


Sustainability

100% waste diverted from landfill

100% timber responsibly sourced


Safe

Zero RIDDORs

CCS Score 43/45


Aftercare

Handover & Aftercare Contractor Promise

Harrison Building, University of Exeter

  • Client

    University of Exeter

  • Contractor

  • Value

    £14.23m

  • Completion Date

    January 2022


Project Background

The Harrison Building is located in the centre of the Streatham Campus, surrounded by several other University buildings, key facilities, roads and footpaths. The works to the operational building included the replacement of the roof, northlights and complex building services, whereby a scaffold birdcage and temporary roof were erected over the building to facilitate the removal of asbestos also involving a significant amount of temporary works.

Several interior refurbishment sub-projects were delivered concurrently including the new state-of-the-art ‘Curriculum 2020’ suite, comprising lab space, workshops, offices and open-plan workspaces.

A carefully planned logistics strategy was developed for each stage of the project, the planning of which began at the earliest possible stage.

–

The Challenge

The Harrison Building’s technical challenges and site constraints, combined with the requirement for the building to remain operational throughout, placed additional importance on the safe segregation of our works, stringent management of hazards and careful mitigation throughout in order to minimise the impact of works on the student experience and day-to-day campus operations.

Neighbouring campus buildings were occupied throughout the works and continuity of “business as usual” was vital for all campus users.

The Solution

Key to our successful relationship with the University was our established levels of communication, commitment, planning and understanding, coupled with the professional and considerate conduct of our site team at all times. Mitigation techniques included:

A carefully considered ‘birdcage’ scaffolding solution implemented due to standard temporary works scaffolding not being viable due to the constraints of the building;

Working concurrently, the team re-engineered the programme across two phases so that the building could remain operational, allowing the university time to safely decant between areas once handed over;

Recognising and ensuring all works were programmed with sufficient detail whilst maintaining the flexibility required for a live environment. Strong planning techniques were critical and all members of each site team were kept up-to-date on any issues relating to their particular element of works;

Works were suspended during exam periods and key events such as graduations, open days and the ‘Big Bang’ event.

The Results

In understanding and upholding the University’s commitment, core values, approach to sustainability and the Environmental Climate Emergency, we are proud to have now delivered 7 carbon reduction projects for the University within the past 5 years, including this project, through:

  • Upgrading the thermal insulation value of the roof to provide 0.18 W/m² K;
  • Upgrading the thermal insulation value of the Northlights to provide U-values of 2.0 W/m² K;
  • Upgrading building services to modern standards, rigorously commissioning to ensure the most efficient energy in use.

All of Morgan Sindall’s sites remained open throughout the initial Covid “lockdown” period including the Harrison Building. A visiting HSE inspector described our infection control measures as “above compliance”.

13


Apprentices

99.5%


SME Spend

£9,387


Added Value

9/10


Client Satisfaction

Client Testimonials

“I am very pleased with how Morgan Sindall have performed at Harrison Building, it is possibly the most challenging construction project the university has seen in many years and so credit should be given for the stringent management of safety, progress and quality on site.”

Contractor Performance | Commitments


Fair

100% payment within 30 days terms


Safe

Zero RIDDORs

CCS Score 43/45


Sustainability

96% waste diverted from landfill

100% timber responsibly sourced

159 tonnes carbon saving

12 SMEs

We have remained committed to provide a local workforce with the capability and capacity to deliver our clients’ requirements, whilst generating a positive impact on the communities and environments in which we work. At Harrison Building, an impressive 60% of our project spend was within the projects ‘catchment area’ (within 15 miles of site) and 75% within 30 miles.


Legacy

34 beneficiaries, 6 jobs created & 320 trainee weeks

£1,730 donations & 71 volunteer hours

82% social value created

We employed two construction management apprentices and supported our supply chain to recruit, train and retain local apprentice including MEP, where a further 2 apprentices were employed.

In recognising an opportunity to promote the varied and exciting careers available to the University’s College of Engineering, Mathematics and Physical Science (CEMPS) students, we helped in the organising of site visits and a ‘careers fair’, where students met members of our project team with engineering backgrounds and were also able to apply for work experience opportunities.

Throughout the project we have worked closely with local schools, Job Centre and Build Force, giving opportunities to those interested in careers within construction to gain practical, work-based experience in a range of areas, providing a total 14 week-long work experience placements.


Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times

On completion of the first phase, we dedicated a 3-week ‘post-contract’ period within our programme, giving our project management and MEP contractor the opportunity to provide any necessary training for building users, resolve concerns, and undertake ‘fine-tuning’ as required.

The Amelia Scott

Tunbridge Wells Learning and Cultural Hub

  • Client

    Tunbridge Wells Borough Council

  • Contractor

  • Value

    £14m

  • Completion Date

    April 2022

The Challenge

Regenerating a grade II listed building as Tunbridge Wells’ cultural and learning hub. The refurbishments caused complications due to the variety of the materials and construction methods used.

The works carried out were during the Covid-19 pandemic and included the demolition and removal of existing adult education outbuildings and the partial demolition of the existing library.

The budget and cost plan alignment was also a constant challenge, and the town centre location demanded considered planning of materials and plant.


The Solution

Multi-stakeholder engagement demanded communication clarity. The Willmott Dixon team introduced a stakeholder engagement and communication plan to provide clear communications, track and reocrd key decisions needed.

Having a constant pro-active approach to reporting allowed design and specification decisions to be considered early, allowing the team to plan ahead and report against key milestone events.

The Willmott Dixon team also had to flexible in order to adapt to the ever evolving CLC working restrictions.

The Results

The Amelia Scott has been redeveloped as a major new cultural centre in Tunbridge Wells.

The centre is home to several attractions including a museum, art gallery, library, archives, Tunbridge Wells Borough Council’s Gateway, Kent County Council’s register office, the Tourist Information Centre and Kent Adult Education centre. It showcases rare paintings and artefacts, including a Gainsborough, as well as 10,000 books and 60,000 historical objects, twice as many that could be displayed in its forerunner.

There is also a new ground floor pottery studio, as well as textile and silversmithing facilities and a digital suite for the creation of short films, videos and other digital art.

4


Apprentices

87.2%


Achieved Local SME

2m


Added Value

9/10


Client Satisfaction

Contractor Performance | Commitments


Fair

99% of regular payments were made within the required period and did not exceed 30 days


Sustainability

Created learning opportunities leading to sustainable employment


Safe

Zero harm achieved


Legacy

Created distinctiveness of Tunbridge Well’s local economy


Aftercare

Applied aftercare and soft landing principles

Winchester Sport and Leisure Park

  • Client

    Winchester City Council

  • Contractor

  • Value

    £40m

  • Completion Date

    June 2021

The Challenge

A belated appointment at RIBA Stage 4 our newly formed integrated team worked well together to successfully resolve a number of key challenges:

Design Engagement: Current design consisted of two leading architects, drawn together via a local ‘Design Framework’

Facilitated Design: Introducing a Leisure design guide the client benefited input from Willmott Dixon’s ‘yellow book – a speciation application tool’. This improved design time and provided confidence with tried and tested leisure designed solutions. A project feature was the considered ground civil engineered solution, constructing the pools as the existing ground has a high ground water and located near a tributary feeding the river Itchen.

Constructing in a Global Pandemic – the construction period spanned the unprecedented Covid-19 Global Pandemic constantly adjusting adhering to the ever evolving CLC working guideline practices.

The Solution

A new facility comprises a 50m eight-lane swimming pool, 20m teaching pool including a water confidence area, a multi-use sports hall and a climbing facility, 4 squash courts with a movable wall to enable flexible use, treatment rooms, fitness suite (200 workout stations), two large studios, one spin studio and a café, a hydrotherapy suite to serve people in the local and wider community with disabilities.


The Results

Officially opened in May 2022 and membership has far exceeded any forecast. The centre pulled in more than 150,000 people in the first three months and is hailed a success despite constructing and completing throughout Covid-19.

5


Apprentices

100%


Achieved Local SME

15.7%


Added Value

9/10


Client Satisfaction

Contractor Performance | Commitments


Fair

99.9% of regular payments and have payment periods not exceeding 30 days


Safe

Zero Harm – extensive training delivered with updated Covid CLC awareness training provided


Legacy

SCF Legacy Hub created – Building Lives Academy delivered


Sustainability

£1.7m ADDED VALUE – Value gained from activities carried out with individuals, groups and communities where our construction projects are based.


Aftercare

Compliant with SCF Charter

RBC Office Rationalisation – 19 Bennet Road

  • Client

    Reading Borough Council

  • Contractor

  • Value

    £3.66m

  • Completion Date

    March 2020


Full Cat B fitout over two floors and mezzanine area for repeat client.  The newly modernised office space now houses the Council’s Parks, Highways and Housing Departments.  The works also included the creation of a storage facility for the museums and modern records division.

–

The Challenge

  1. Tight programme for roller racking area to achieve critical path
  2. Old mains electrical panel in plant room required decommissioning as part of the demolition works to the racking areas
  3. Deliveries logistics to an office block in the centre of a live and busy council depot

The Solution

  1. We ensured the roller racking area works started as early as possible to meet the critical path. The programme was designed to progress these areas to mitigate the risk of not meeting the handover with the roller racking in place.
  2. Requests made to the electrical board immediately for them to disconnect and remove the mains electrical panel but still meant some delay to works. To ensure this did not delay the overall programme, we progressed with other surrounding works whilst keeping the plant room out of bounds also mitigating any H&S risks.  The sequencing of the roller racking was swapped to ensure the programme stayed on schedule.
  3. We had to balance deliveries and a shared car park with the Council contractors with the use of a dedicated banksman and one way system. The challenging location meant that large vehicles could not always access the site.

The Results

  1. After the final demolition, the entire warehouse was re-screeded to ensure the smooth operation of the roller racking and the floor levels only have 5mm tolerance throughout the whole span of the warehouse.
  2. Once the old mains electrical panel had been safely disconnected and removed in the plant rook, the roller racking installation was accelerated so that the end handover date was met.
  3. Collaboration, communication and organisation with the Council were key to maintaining a good relationship whilst being efficient with deliveries and subcontractors.

5


Apprentices

94.5%


SME Spend

£147k


Added Value

10/10


Client Satisfaction

Client Testimonials

 “I would like to take this opportunity to thank you and your team for all of your efforts in bringing this project to a very successful conclusion.  Your pro-active ‘can do’ approach has made it a real pleasure to work with you all.  You collaborate more than other contractors. I find with Overbury nothing is ever a problem and we work together. You get on and deal with things, and there is a lot of trust.”

“On overall delivery you have strengths in all areas.  You have no weaknesses – from the day to day on site right through to finances.  You are the complete package.”

Contractor Performance | Commitments


Fair

100% payment within 30 days terms


Sustainability

8% waste diverted from landfill

Use of local subcontractors and materials had a positive impact on the local economy


Safe

Zero RIDDORs


Legacy

20 SMEs

5 beneficiaries

2 jobs created

152 trainee weeks

£500 donations to charity


Aftercare

Soft landings for handover

Dedicated Morgan Sindall point of contact

On-line portal for notifying any defects with 3 priority categories for response times

SCF Framework Manager

James Wright

Email: james.wright@hants.gov.uk

Phone: 07761 330560

Contractor Framework Manager

Alan Smedley

Email: alan.smedley@morgandsindall.com

Phone: 07967 686066

Friars House Re-Cladding

  • Client

    Friars House Aylesbury Ltd

  • Contractor

  • Value

    £4.4m

  • Completion Date

    March 2022


The Challenge

first Recladding Project Undertaken: Friars House is a office block that was converted into a Residential building in 2015, with one additional floor added. The building totals 5 storey’s (8 storey’s including the shopping centre) and is constructed over an existing shopping centre and now contains 71 residential apartments. When the Building was converted from Offices to Residential the building was over-clad with ACM and a EPS render system. Whilst occupied, this project undertook works to replace the potential combustible cladding on the external elevations with materials in line with Approved Document B December 2018 Revision, post-Grenfell.


The Solution

Undertook extensive cross checking with physical inspections. Understand how the occupiers use and plot trends whilst planning operational delivery around these patterns. Plan ahead with extensive logistical solutions in place and test these prior to undertaking any works.


The Results

Adapted to ever evolving Covid CLC working practices – worked closely with the client to ensure minium disruption experienced. Customer stated: Excellent communication all through the design and construction phases

1


Apprentices

73.3%


SME Spend

£662k


Added Value

10/10


Client Satisfaction

Contractor Performance | Commitments


Fair

99.8% payment periods not exceeding 30 days


Sustainability

Undertook social legacy work-streams and compliance with the Social Legacy Policy


Safe

Zero Harm


Aftercare

Handover & Aftercare Contractor Promise

University of London, Sebastian Street Law School

  • Client

    City, University of London

  • Contractor

  • Value

    £49.5m

  • Completion Date

    September 2020 

Procurement Type: Two stage
Form of Contract: JCT 2016 Design and Build
Contract Period: 161 weeks
Size: 7,267m2

BAM has developed a landmark property for City University, which incorporates a striking combination of new and existing structures. The project was procured through SCF Construct and consists of a tower block with an innovative twin screen printed façade, new attached blocks and existing structures incorporated into a single building. Scope includes a double basement, ground and six upper floors, including the extension and refurbishment of the existing Goswell and Myddleton buildings.

An atrium connects the collection of buildings, containing a cafe and circulation space. A new external courtyard has been created between the building and adjacent residential properties. BAM extended the existing basement to provide lecture/ conference space.

The Challenge

Site Constraints / Logistics This was a logistically challenging project, situated on a restricted site and bounded by residential properties, including Grade II listed buildings. Sebastian Street also lies within the Northampton Square Conservation area.

Cladding design – The concept design comprised a twin walled flue design to achieve the desired architectural look. Technically this presented a challenge as it did not align with the M&E strategy, this issue required quick resolution to maintain programme.

Archaeology – archaeological dig required to ensure the preservation of the rich local history.

The Solution

Site Constraints / Logistics – Bounded by residential neighbours and building within a conservation area required sensitively managing in order to maintain good relations and minimise the impacts of construction works. We achieved exactly this through regular resident forums and good communication. CCS score of 42/50.

With regards to site and design complexities, the use of digital technologies / BIM aided design coordination, spatial fit of retained structures and condition / cloud surveys.

Cladding design – To overcome the technical issues and align with the buildings M&E strategy we collaborated with specialist supply chain partners Skonto and Schuco to design an alternative cladding solution based on a twin walled unitised system.

Archaeology– Prior to construction starting, City collaborated with Museum of London Archaeology. During the excavation, artefacts dating back to the pre-Bronze Age era were found, in addition to remnants of a Civil War fort, trenches, glazed pottery and tokens from the 1640s.

–

The Results

The final results are outstanding, Clients expectations exceeded is testament to the teams unified approach to managing the many complex and unforeseen challenges, in particular delivering this facility in London during the height of the pandemic.


13


Apprentices

£36m


SME Spend

£1.98m


Added Value

9/10


Client Satisfaction

Client Testimonials

‘I cannot thank you all enough for what you have done …to deliver such a fantastic building that we are so proud to call ours. Every one of you, both on site and behind the scenes, have been a pleasure to work with for the past 3 years. Without your commitment and hard work it wouldn’t be the building it is, exceeding my expectations. Thank you all so much’

‘BAM, our principle contractor, has brought our vision for the building to reality by transforming the old site and two existing historic buildings. They have worked excellently throughout the construction phase and I am looking forward to the building coming to life.’ [Feb 2020]

Contractor Performance | Commitments


Sustainability

The project achieved a BREEAM Excellent rating attributable to the low carbon design and sustainable services installations all contributing to a reduction in City’s carbon emissions.

Sustainable features:

Photovoltaic system on roof areas

Centralised lighting control system throughout the law school

Primary ground source heat pump system

Energy Efficient lighting

Rainwater harvesting

98% Waste diverted from landfill –

100% timber sustainably sourced

56 Environmental Toolbox Talks

Contaminated ground was remediated


Legacy

493 apprenticeship weeks

Work experience placements and volunteering

5 local apprentices from Islington

8 apprentices not local

57 hours volunteered by project team

2 work experience placements

Charities supported: CLIC Sargent and Alzheimer’s Society both charity partners and CRASH

Employment of local site management trainee: We had 6 local apprentices on site, 1 non- local management trainee.

Sponsorship of college/university students: 1 x quantity surveyor


Fair

100% payment within 30 days terms


Aftercare

As part of our commitment to aftercare, key BAM personnel remained on site following completion to facilitate smooth occupation for both the university staff and students. We worked with the Clients FM team to ensure they were fully familiar with the operation and maintenance requirements, providing additional training sessions where required.


Safe

Zero RIDDORs

CCS Score 42/50

SCF Framework Manager

Alex Nelhams

Email: alex.nelhams@hants.gov.uk

Phone: 07717 003869

Contractor Framework Manager

Darren Birch

Email: dbirch@bam.com

Phone: 07920 134843