A bespoke ‘BREEAM Excellent’, 3-storey engineering and research building, housing the world-leading VSimulator facility, providing specialist engineering facilities and open-plan, flexible workspace. The facility will play a major role in spearheading Exeter Science Park’s aspirations and reputation for research and innovation, stimulating a knowledge-based economy, delivering jobs, higher productivity and economic growth.
Providing unique simulation capabilities far beyond anything available worldwide, the VSimulator facility will be used by academics and industry to support multi-disciplinary research factors. Helping to address critical issues of human engagement with the surrounding environment, it will present research, commercial and training opportunities within an endless range of disciplines.
Imperative to the successful project outcome, the Virtual Simulation Chamber had to be handed over to the specialist engineers on time to commence installation of the state-of-the-art motion platform and other equipment.
Additionally, the basement concrete floor had to be within a 2mm-tolerance level and strict water-proofing specifications had to be achieved prior to the VSimulator installation.
Further adding to the challenge were complex logistics and mechanical and electrical installations, and the involvement of multiple, including global, specialist installers.
Through sectional completion (in October 2019), we handed over the basement to the University for fitting-out of the simulator, whilst the remaining works continued. We worked closely with the University throughout the fit-out works, ensuring this was undertaken safely while the remaining works took place concurrently.
During early design collaboration, we were able to offer our experience with basement construction to align buildable-construction details with specialist tanking manufactured products. It was at this early stage when a significant change in tanking membrane manufacturers occurred and, with the help of our supply chain family, we were able to provide a quick solution to the benefit of the client.
Communication was critical to ensuring we kept to programme, and we successfully managed the co-ordination of overseas meetings, held virtually, regarding set-up, installation and delivery of equipment for the motion platform.
Drawing upon the expertise and skills of the project team, the challenging project objectives were all achieved, to the delight of the client.
100% payment within 30 days terms
BREEAM Excellent
99% waste diverted from landfill
100% timber responsibly sourced
Zero RIDDORs
CCS Score 43/45
38 No of SMEs
10 beneficiaries
4 jobs created
49 trainee weeks
Schools engagement: 28 students
£200 donations to charity
39 volunteer hours
88% social value created
Soft landings for handover
Dedicated Morgan Sindall point of contact
On-line portal for notifying any defects with 3 priority categories for response times
Email: kingsley.clarke@devon.gov.uk
Phone: 07805760622
Email: alan.smedley@morgansindall.com
Phone: 07967 686066
A new build four-storey steel frame building which includes two sports halls, three fitness studios, a health and well-being gym, a strength and conditioning high-performance gym and high-quality teaching facilities on a live university campus. The scheme also includes underground car parking.
The ambitious vision for the University was to create a new sports facility to improve and modernise the University’s offering and enable excellence in sport, health and fitness related degree programmes and associated teaching and research for staff, students and the local community.
The seminar and gym areas of the sports complex are fitted with 20mm soft joints between the room floor slabs. These help to isolate them and significantly reduce the vibration that passes through them. In the weight training area, they went a step further and introduced a cast in-situ reinforced concrete sprung floor. This innovation means that the sports hall can be enjoyed by everyone, no matter what activity they are involved in.
The iconic cladding system to the tower block represents the former use of the site with historical maps – a subtle presence in the perforation in the cladding system next to the standout face brickwork wrapping the sports halls. The building has provided a head turning modern build in Southampton’s old city centre.
The city centre project was constructed within a 86 week programme, delivering a four-storey sports complex with state-of-the-art gyms for both student and staff use. Along the stacked tower block of gyms and studios, the project had two full sized sports halls; one for multi-use catering for over 13 different sports, the other was dedicated to basketball, allowing Student Kestrels, the university’s leading sports team, a home court. Below the sports halls, basement parking was provided for staff, students and the public as well as accessible parking bays.
The project is a visually stunning, flagship sports facility which is enhancing Solent University’s offering in advanced sports degree courses, and it is already attracting more students to the local area and inspiring people to take part in sport.
100% payment within 30 days terms
99% waste diverted from landfill
100% timber responsibly sourced
Zero RIDDORs
CCS Score 44/45
36 No of SMEs
59 beneficiaries
18 jobs created & 184 trainee weeks
Schools’ engagement: 577 students
£3,046 donations to charity & 1,845 volunteer hours
84% social value created
Soft landings for handover
Dedicated Morgan Sindall point of contact
On-line portal for notifying any defects with
3 priority categories for response times
Email: james.wright@hants.gov.uk
Phone: : 07761 330560
Email: alan.smedley@morgansindall.com
Phone: 07967 686066
Client
University of Exeter
Architect
Stride Treglown
Contractor
Kier Construction
Value
£8.2m
Contract Period
December 2017 – February 2019
Form of Contract
NEC Option A with design
The design and construction of two buildings for laboratories and research facilities to allow further growth of Exeter Business School, the College of Engineering, Mathematics and Physical Sciences and the College of Life and Environmental Services.
This new Science Engineering Research Support Facility (SERSF) building provides facilities for around 200 researchers and postgraduate students specialising in science and engineering.
The new facility accommodates many disciplines, including the newly established Business School, the Centre for Ecology and Conservation, Renewable Energy and Camborne School of Mines. It is also the new home for Law, Energy Policy and Mathematics
A large glazed atrium forms the main entrance and the vertical circulation route to all floors. The installation of a key operated lift allows lab users to access the autoclave area on the lower ground floor which creates a link for users to transport any contaminated waste, safely through the building.
A new seminar facility provides space to facilitate linkage with external agency researchers in marine science and wildlife research.
Previously constructed buildings.
The project consists of three linked buildings. The first phase of the project had already been constructed, which made the construction of the next two phases more complex as we were connecting and linking floor levels.
Existing services and diversions on main vehicular route.
The site was riddled with existing services and diversions impacted the main vehicular route into the campus. These works were brought forward in an enabling package at a more convenient, less disruptive time for the university.
Our Success
Our Learnings
Value Added
Client
Somerset County Council
Contractor
Morgan Sindall
Value
£736k
Contract Period
32 weeks
Expansion of the existing primary school with the addition of three new classrooms using the ‘Class Space’ standard design. The classroom extension included toilets and was situated on the old basketball court, north of the school’s sports hall.
The client wanted the classrooms to be flexible for potential future use and expansion. Therefore, the internal dividing walls were stud work and the school’s preferred option of radiators were used instead of underfloor heating. The position and orientation of the building on the basketball court area were carefully designed so the school could construct another block adjacent to this one in the future. Other considerations included design items, such as mains cable sizes.
The extension was constructed of steel frame, blockwork rendered externally, with a profiled metal roofing system.
Fair Payment Charter
Sustainable Development Charter
Health & Safety Charter
Legacy Charter
Handover & Aftercare Contractor Promise
Careers Opportunities
Maintaining the school’s curriculum while working in a live school environment
Ensuring business continued as normal while coordinating deliveries
Ensuring the design allowed for future use and expansion
Our Success
Our Learnings
Value Added
| Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
| Cost | £2,462k | £2,417k | -1/8% |
| Time | 32 weeks | 32 weeks | 0 |
Contact: Alan Smedley, Framework Manager
Email: alan.smedley@morgansindall.com
Client
Dorset County Council
Project Manager
Dorset County Council
Architect
Dorset County Council
Contractor
Morgan Sindall
Value
£2.7m
Contract Period
49 weeks
Procurement Type
Construction only
Form of Contract
JCT 2011 SFC
A new build two storey, separately annexed, classroom block extension to the existing school to increase capacity from 5 Form Entry (600 pupils) to 6 Form Entry (720 pupils). The new building, located to the eastern side of the existing school, provides four spacious classrooms, a multi-purpose resource teaching space, and a new dining hall and kitchen. The Multi Use Games Area (MUGA) was also replaced as the new building was located on the existing facilities.
Live school environment
Phasing of the works, sectional handovers and decanting pupils as works completed
Our Success
Our Learnings
Value Added
Value engineering was carried out with the following outcomes:
| Contract | Gateway 3 Contract Agreement | Gateway 4 Practical Completion | Variation |
|---|---|---|---|
| Cost | £2,707,877 | £2,521,556 | -7.4% |
| Time | 45 weeks | 43 weeks | -2 weeks |
Client
Reading Borough Council
Project Manager
Hampshire County Council
Architect
Broadway Malyan
Contractor
Morgan Sindall (overbury)
Value
£3.6m
Contract Period
26 weeks
Procurement Type
Design & Build
Form of Contract
JCT D&B
Size
1,308 m2 GIFA
Trainees
5
Overbury successfully delivered a full Cat B fit out over two floors and a mezzanine area for repeat client, Reading Borough Council (RBC). Procured through the SCF Framework, the newly modernised office space will house the Council’s Parks, Highways and Housing departments. The works also included the creation of a storage facility for the museums and modern records division.
Works to the office space included the creation of a breakout area on the ground floor, new toilets, refurbishment of the showers, new tea points, installation of a new lift and redecoration throughout. Structural beams were moved and adapted to ensure that the lift could be appropriately supported. A new structural steel beam was installed under the mezzanine to support the new storage equipment that would be installed on this floor. New roller racking storage and close control air conditioning units and dehumidifiers were fitted in the document and artefact storage areas.
The security of the building was increased with specialist steel doors and updated security systems.
The building is located in the middle of a busy depot which was in constant use throughout the project. Logistics had to be carefully planned; and effective traffic and parking management was key. Maintaining a strong relationship with the client ensured successful and efficient use of a challenging site.
Throughout the project we had apprentices and trainees working on site; directly for Overbury and for our subcontractors.
Tight Programme to achieve Critical Path
The tight programme for the roller racking area presented a key challenge for the project. We had to ensure that this portion of works started as early as possible to meet the critical path. The programme was designed to progress these areas to mitigate the risk of not meeting the handover with the roller racking in place.
To ensure the smooth operation of the roller racking, the floor levels could only have a 5mm tolerance throughout the whole span of the warehouse. After the final stage of demolition was completed in the racking areas, we re-screeded the entire warehouse. This ensured the 5mm tolerance was met throughout the span which resulted in the perfect running of the racking system.
Plant Room Decommissioning
From the validation phases of the project it became apparent that there was an old mains electrical panel in a plant room in the centre of the building that was still live, this was due to be demolished to be used for racking areas. Requests to the electrical board were made immediately for them to disconnect and remove, however there was still to be a delay for these works. To ensure that this did not delay the overall programme we progressed with all other surrounding works, whilst keeping this plant room out of bounds to mitigate any health and safety risk. The sequencing of the roller racking was swapped to ensure the programme stayed on schedule.
Once the electrical panel was safely disconnected and removed, works to remove the old plant room and progress works for roller racking installation was accelerated so that the end handover date was met.
Deliveries Logistics
The office block was at the centre of a live and busy council depot. We had to balance deliveries and a shared car park with the council contractors and the challenging location also meant that large vehicles and deliveries could not access the site.
Collaboration, communication and organisation were key to maintaining a good relationship with the client while being efficient with deliveries and subcontractors.
Our Success
Our Learnings
Value Added
Client
Department of Education
Contractor
Morgan Sindall
Value
£7.5m
Contract Period
80 weeks
At Fulham Cross Girls’ School, the works comprised the demolition of an old 1970’s science block and delivery of a state-of-the-art science building and gymnasium with bespoke science labs, staff rooms, offices and a double-height gym. The new steel frame building with precast concrete planks on the first floor and roof and external brick and clad facade provides 5 new laboratories, preparation room, sports hall, changing rooms, toilets and staff room. The building includes PV panels and attenuation tank.
The main gym complements the all-weather outdoor facilities with associated changing rooms, storage facilities and offices, and capacity for a variety of indoor sports including hockey, netball, dance, and rowing machine activity.
Fulham Cross Girls’ School new block was handed over successfully on budget in March 2020, safely and without delay following the government guidelines during the COVID-19 pandemic.
Fair Payment Charter
Sustainable Development Charter
Health & Safety Charter
Legacy Charter
Handover & Aftercare Contractor Promise
Career Opportunities
Outreach Programmes
Minimising disruption
The project saw the use of temporary modular classrooms to house students away from the works in order to minimise disruption as much as possible to the overall learning environment.
Last minute programme changes
As of March 2020 and amidst the COVID-19 pandemic, Fulham Cross Girls’ School new block was handed over successfully on budget and safely following the government guidelines. Last minute programme changes were made to suit the school amidst the COVID-19 outbreak. Morgan Sindall utilised their labour to help move the school in/out for handover 2-weeks early.
Noisy works
The school remained fully operational throughout the works which required Morgan Sindall to work closely with the school throughout to minimise the impact on teaching and learning. They re-programmed works to avoid noisy works during busy school time/utilising school holidays where possible.
Our Success
Our Learnings
Value Added
| Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
|---|---|---|---|
| Time | 71.7 weeks | 63.6 weeks | -11.4% |
Contact: Alan Smedley, Framework Manager
Email: alan.smedley@morgansindall.com
Client
Dorset County Council
Project Manager
Dorset County Council
Architect
Dorset County Council
Contractor
Morgan Sindall
Value
£1.46m
Contract Period
43 weeks
Procurement Type
Traditional
Form of Contract
JCT 2011 SFC/CDP/Q
GIFA
180m2
Apprentices
4
Sherborne Abbey CE Primary School is located on the western edge of Sherborne. The existing 1.5 form entry (FE) school was constructed in 1999 but due to an increase in the population of the school aged children in the area, the school needed to expand in size from 1.5FE (315 pupils) to 2FE (420 pupils).
A new single storey extension to the western elevation of the existing school was constructed. The new accommodation comprised of three new class bases, food technology room, two group rooms, toilets and associated ancillary spaces, landscape and drainage works. The existing reception area was also extended and internally re-modelled to provide adequate space.
To enable the construction works to progress whilst the school remained operational, temporary modular accommodation was installed and remained on site for 12 months during the course of the works.
The design of the new extension followed the style and rhythm of the existing traditionally constructed school, being a masonry walling envelope under a pitched tiled roof covering. This retained the established strong sense of identity and consistency. The landscape works included new footpaths to link all new external door entrances to existing paths, hard and soft play areas providing fully accessible circulation routes for disabled users.
Career Development
School remained fully operational throughout works
The school remained fully operational throughout the works and with shared site access the contractors worked closely with the school throughout to minimise the impact on teaching and learning.
Site access
Access to the site was via a bridleway that had to be maintained. Prior to works commencing, the bridleway was upgraded up to the temporary site access to avoid damage and mud onto the public highway. Works were agreed in advance with the Local Authority.
Out of hours work
Elements of the project required localised works within the existing school including classroom refurbishment, a new entrance canopy and reception area, service connections and switchovers. These works were carefully planned prior to commencement on site to be undertaken out of school term and at weekends/out of hours to avoid disruption to the school. Weekly discussions with the school took place on the planned works for the work to avoid impact to the day to day operations of the school.
Our Success
Throughout the project we engaged well with the school, coordinating the works around their requirements to ensure that the safety of pupils was the upmost priority. Consistently maintaining our relationships with local residents with our just in time deliveries and avoiding peak times with school drop off and pick up times. Communication and training with the school as part of the handover process was well received and resulted in the staff feeling confident and competent with their new teaching facility. Following on from a project review, the team received a 10/10 recommendation score from the client after handover.
Our Learnings
The project was fully detailed and specified with limited CDP elements to the works. Notably one challenge arose surrounding the subcontract complex cut roof design which was to interlink to the existing building causing significant delay to the project. We worked with the client team and subcontractors to find a solution as quickly and efficiently as possible through collaborative meetings to resolve the complex design coordination that worked for all parties.
Value Added
Early engagement with the supply chain particularly with the roof design solution resulted in an overall saving for the client.
| Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Gateway 4 Contract Handover | Variation |
|---|---|---|---|---|
| Cost | £1,682,019 | £1,682,019 | £1,460,147 | -15.2% |
| Time | 38 weeks | 38 weeks | 43 weeks | +5 weeks |
Client
University of Exeter
Project Manager
Faithful + Gould
Architect
Faithful + Gould
Contractor
Morgan Sindall
Value
£1.06m
Contract Period
25 weeks
Procurement Type
Traditional
Form of Contract
JCT 2011 SFC
The works involved removing and replacing all existing external windows and external doors, providing a new fire alarm and emergency lighting system, new sub-main power installation and new heating distribution pipework and radiators. Due to the pre-construction stage being very short, our team had to ensure a speedy and accurate order for new windows which were manufactured by Nordic and immediately delivered to site for just in time arrival for fitting.
The works were completed within an occupied building out of hours ie all works carried out overnight from 6pm – 7am leaving the areas in a suitable condition for re-use by the building users the following day which included the relocation of furniture and all associated equipment. The works also included floor slab concrete repairs acting as lintels. The works were completed within an occupied building over a series of 24 weekly phases.
These phases were programmed in detail with the stakeholders to incorporate each of their requirements ie to take into account their busy times; for example there was a 3 week period within the central block when it operated as a 24 hour call centre for a telethon. Within the programme, consideration was also given for graduation weeks, exam periods and open days. Each phase was vacated at the end of each working day and all works delivered out of hours. Works also included the erection and dismantling the scaffold around the live building, campus and the car park for Northcote House.
Senior management occupation of building
The building is the main HQ of the University which is occupied by all of the senior management team at the University including the Vice Chancellor.
The window installation around the Vice Chancellor’s office (Executive Suite) needed to be within strict timescales to be “seen and not heard”. We created a scheduled timetable with the building occupants so they were all aware of busy and noisy periods enabling them to plan their meetings accordingly.
Exam period
There were to be exams held within the building throughout the duration of our works therefore a schedule was worked out around timetables. Works were then planned to commence out of hours and at weekends to hand back the offices on the Monday.
Building remained fully occupied and operational throughout works
To enable the building to remain fully operational without disruption and accommodating the out of hours working, we photographed each room prior to the shift starting, moved all furniture away from the windows ready to remove and replace and then put the room back to how it was in the morning ready for staff to use the office space. The building was a large building and the works as such were done under multiple phases with each requiring very close liaison with the building users within each office area.
Our Success
Our Learnings
Value Added
| Contract | Gateway 3 Contract Agreement | Gateway 4 Contract Completion | Variation |
|---|---|---|---|
| Time | 24 weeks | 24 weeks | 0 weeks |
Client
Devon County Council
Project Manager
NPS Group
Architect
NPS Group
Contractor
Morgan Sindall
Value
£1.6m
Contract Period
59 weeks
Procurement Type
Traditional
Form of Contract
NEC ECC Option A
Size
382 m2
Trainees
10
Works at Totnes St Johns CoE Primary School comprised the demolition of the existing temporary classroom and construction of a large two storey steel frame extension to the existing school. The new extension provided five new classrooms, group rooms, new toilet facilities, extension to existing hall and reshaping of the external footprint. The building was heated with underfloor heating and all classrooms had breathing systems installed, drawing fresh air in to the rooms, creating good working environments for the pupils.
The works all linked in to the existing school and required new openings and access ways formed to enable smooth passage from the existing school to the new extension.
Career Development
Working in a live school environment
The school remained fully operational throughout the works and with shared site access and segregation requirements required the contractors worked closely with the school throughout to minimise the impact on teaching and learning. Weekly meetings were held with the head teacher to plan works, ensuring they were planned carefully, enabling all users to maintain a high quality of safety throughout the contract.
High risk activities
Works were sequenced so that the high risk demolition and steel lifting activities were undertaken during the school holidays. We had to keep in regular contact with the school and would speak with the headteacher most days. These were highlighted as key objectives in our customer charter. All possible access points to the construction site were secured with solid hoardings / secured gates.
Detailed client co-ordination
The existing hall was extended to meet the requirements for the number of pupils currently at the school, requiring detailed client co-ordination and relocation of the school front entrance.
Our Success
Our Learnings
Value Added
| Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
|---|---|---|---|
| Cost | £1,304,215 | £1,304,215 | 0% |
| Time | 45.3 weeks | 45.3 week | 0 weeks |