Client
Somerset County Council
Project Manager
Somerset County Council
Architect
NVB Architects
Contractor
Midas Construction Ltd
Value
£2.9m
Contract Period
47 weeks
Procurement Type
Competitive tender – 2 stage
Form of Contract
NEC3 Option A
Size
830m²
Apprentices
6
Tor School is a Pupil Referral Unit (PRU) in Glastonbury, one of the first fully integrated PRUs in the UK, which brings together three streams of Somerset County Council’s educational facilities. The school offers alternative educational provision for vulnerable young people who struggle in a mainstream school environment and provides facilities for Key Stages 2, 3 and 4. The PRU includes a Learning Enhancement Centre with facilities for outreach staff. Designed with the needs of the young people in mind, the building’s layout enables direct access from each classroom to dedicated external spaces. The different year groups share specialist spaces, including a breakout room with low-level lighting.
Midas constructed this single-storey, 12 classroom educational building on a design and build contract. This well-insulated building features blockwork render on all elevations with a truss timber roof and robust internal fittings designed to accommodate the specialist needs of the pupils. Midas completed groundworks including drainage and service connections, with internal works including first fix M&E, dry lining, plastering and decorations.
The client scored the project 100% in the customer satisfaction survey at practical completion and the site received a CCS Bronze 2018 National Site Award.
Career Opportunities
The client had a restricted budget with which to meet their project requirements
This constrained site contained a party wall and was bounded by commercial and residential properties, including a live ambulance station to the south and an adjacent Learning Difficulties Day Centre that remained open throughout the project.
The site contained hazardous underground and overhead live services including a high voltage (HV) cable that served half of Glastonbury. The project also included creation of a substation requiring rerouting of existing services and removal of redundant services.
Our Successes
Our Learnings
Added Value
| Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
| Cost | £2,949,492 | £2,901,181 | -£48,311 (-0.3%) |
| Time | 34 weeks | 38 weeks | 4 weeks (11.8%) |
KPI Graphs
Apprentices 6
Graduates 1
Average AIR 0
Average CCS score 40.5
Waste diverted from landfill 92.1%
Cost/m2 £3,502m²
Cost/m2 excl abnormals £2,347m²
Client
South Somerset District Council
Project Manager
NPS South West Limited
Architect
NPS South West Limited
Contractor
Midas Construction Ltd
Value
£1.5m
Contract Period
40 weeks
Procurement Type
Competitive tender – 2 stage
Form of Contract
NEC3 Option A
Size
1,044m²
The Yeovil Innovation Centre is an evolving business community designed for small businesses and entrepreneurs that require high quality, low-cost and flexible work spaces with room for growth. Supported by funding from the Heart of the South West Local Enterprise Partnership, Midas constructed this two-storey extension for client South Somerset District Council to expand the capacity and update resources at this multi-office facility.Located on Lufton Trading Estate to the east of Yeovil’s town centre, the Innovation Centre provides reception and meeting areas for tenants and entrepreneurs looking for the flexibility of short term leases. This extension offers over 1,000m² office accommodation across two floors. The structure is strip footing foundations supporting a portal steel frame, with a block and beam ground floor and precast first floor and roof, and raised access flooring installed to both floors. It benefits from brise soleil solar shading, with internal plasterboard finish that allows for future reconfiguration of the ground floor to meet the changing needs of tenants. Midas’ works included a lift, shell and core finish to the first floor, a single ply roof and landscaping. The project received a score of 96% in the customer satisfaction survey at practical completion.
Career Development
Meeting the client’s design expectations within their budget
Budget: Early in the programme Midas’ market intelligence and cost benchmarking works identified a challenge, with the client’s design requirements exceeding their budget allowance. Midas’ commercial team worked closely with the client’s designers and our supply chain partners to deliver £550,000 of value engineering – including changing the structural frame, amending the window and natural ventilation configuration, amending hollow clay pot and lintel solution, and rationalising roof and gutter design – to make the project viable whilst achieving the client’s vision.
The Innovation Centre remained open and occupied throughout the works
Occupied building: Prior to commencement, Midas established a secure construction site perimeter to segregate live works from the Centre, and erected full perimeter Heras fencing with solid hoarding to the front elevation and post and rail fencing to pedestrian routes. Midas liaised with the client in advance of works and completed noisy works at agreed times. The team implemented acoustic protection measures including forming two baffle bunds from soils excavated on site. The team restricted and segregated noisy works, managed the movement of plant, and situated cement mixers on the opposite side of the site from neighbours. The team held regular consultation meetings to update neighbours on the project; allowing one to one discussions and providing advance notice of noisy works to Centre staff. The team monitored noise, dust and vibration levels through the works and across the site. Contractors completed cutting works in designated areas and made sparing use of damping down to manage dust whilst restricting the site’s water use.
The project involved connection of the extension to an operational building with live services
Live services: The project included demolition works to form a link opening to the existing structure, and service and utilities connections between the original building and the extension. Midas engaged early with the Centre’s management team and planned works in consultation with them. Thanks to the good relations with the client, the site team developed a mutually agreed programme. This ensured Midas could complete demolition, connection and security works during daylight hours, allowing time to address any potential issues. Midas installed a lockable partition early in the programme to segregate works and mitigate disturbance from noise or dust. The team then installed temporary works prior to commencing demolition to support the structural integrity of the façade whilst forming the structural opening. Midas brought new services to the edge of the extension and existing services to the connection point in the original building, before completing service connections overnight. This simplified the connection process, ensured services were not in use during works and prevented disturbance of the Centre staff.
| Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
| Cost | £2,117,646 | £1,474,292 | -£545,854 (-30.4%) |
| Time | 42 weeks | 36 weeks | -6 weeks (-14.3%) |
Apprentices: 8
Average AIR: 0
Average CCS score: 41
Waste diverted from landfill: 99.2%
Cost/m2: £1,574m²
Cost/m2: excl abnormals £1,453m²
Cost/m2: Industry average £ m
Client
Devon County Council
Project Manager
NPS South West Limited
Architect
NPS South West Limited
Contractor
Midas Construction Ltd
Value £2.4m
Contract Period
37 weeks
Procurement Type
Competitive tender – 2 stage
Form of Contract
NEC3 Option A
Size 890m²
Apprentices
3
Situated in rural village surroundings, Loddiswell Primary School provides a welcoming and inclusive learning environment. The school is a 150-place, one form-entry single storey building with capacity to expand as the school grows. The school provides four classrooms, complete with interactive whiteboards and modern ICT equipment, a library, school hall and extensive outside space including a multi-use games area and playgrounds.
The building is timber frame with Structural Insulated Panels with a sectional roof, supported by glulam beams. The finished building features a 14kw PV array, larch weatherboarding and rubble stone walling, with an access road and car parking.Externally, Midas completed landscaping works and created a swale planted with wetland wildflowers as part of the Sustainable Urban Drainage Strategy, to help manage drainage, prevent flooding or run off, increase biodiversity and provide a source of natural interest for the pupils.The project scored 88% in the customer satisfaction survey at practical completion and received a CCS 2019 Bronze National Site Award.
Career Opportunities
The village of Loddiswell is off the gas grid, meaning the building could not benefit from low carbon gas grids and hydrogen solutions, and had no direct access to the cheapest heating options
To address the power supply Midas installed air-source heat pumps, with a 14kw PV array on the roof. The building includes wind-catchers to increase natural ventilation, designed through the Building Physics strategy to meet requirements for natural ventilation, solar shading and natural daylight.
The building needed to be made watertight as early in the programme as possible, to ensure the client-design timber frame retained its integrity
Midas implemented Structural Insulated Panel (SIPS) construction. This off site construction method is then fitted at the premises, enabling the team to make the building watertight sooner and resulting in a positive impact on the programme whilst also reducing waste, noise, dust and air pollution on site.
The site was in proximity to new houses, with a large population of children, with access only available via narrow roads through the existing housing estate
To manage the constrained access Midas restricted delivery vehicle size and scheduled deliveries to avoid rush hour and early mornings, directing site traffic to circumvent the village, and closely managed vehicle movements and timing to avoid disruption. The team reduced site movements by completing a cut and fill exercise, retaining 1,100m³ of excavated materials for the sports pitch and landscaping. The site team monitored the cleanliness of the access road, preempting the need for a road sweeper where necessary, and formed a tarmac car park within the site at the start of the project. Contractors used on-site parking to keep the residential roads clear and the vehicle controller monitored contractor parking to mitigate disturbance to the neighbours.
Our Success
Our Learnings
Value Added
| Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
| Cost | £2,238,653 | £2,420,067 | -£40,300 (8.1%) |
| Time | 37 weeks | 37 weeks | 0 weeks |
KPI Graphs
Apprentices 3
Average AIR 0
Average CCS score 41
Waste diverted from landfill 41%
Cost/m2 £2,793m²
Cost/m2 excl abnormals £1,948m²
Cost/m2 Industry average £ m
Contact:
Email:
Client
Somerset County Council
Project Manager
Faithful & Gould
Architect
Atkins Ltd
Contractor
Midas Construction Ltd
Value
£3.3m
Contract Period
43 weeks
Procurement Type
Competitive tender – 2 stage
Form of Contract
NEC3 Option A
Size 1,020m²
Apprentices
4
The client commissioned Midas to construct a two-storey, eight classroom teaching facility at a primary school in Wincanton to increase the school’s capacity and meet the growing needs of the community. The school’s ethos is to deliver high standards of education within a supportive and stimulating environment. The bright and colourful design of the new building provides a visually striking building with extensive play facilities.
The project team delivered inclusive activities to engage pupils and the community with the project. Events included hosting a time capsule and beam-signing ceremony; having twice monthly site visits from Wincanton Primary and local schools; and hosting students from the local college. The school invited the Midas team to judge their ‘Best Digger’ competition and Midas donated £150 as prize money to the school raffle. The project also won a CCS Silver 2018 National Site Award.
The finished building features educational, administration and associated spaces. Midas’ works included partial demolition of a shelter, fit out of the finished building and all associated utilities connections. The structure is steel frame with block and beam flooring, precast concrete staircases and a lift. Midas created gardens and a play area, completed soft landscaping and provided car parking facilities.
Career Opportunities
In proximity to a live school site with challenging logistics
The team managed the live educational site through effective collaboration with the school to coordinate the programme of works and schedule external and noisy works around lesson times and exams, timing significant works to occur during school holidays to mitigate disruption. Midas maintained close communication through weekly and ad hoc meetings with the school as required, and detailed restrictions in contractor toolbox talks and during site inductions, with daily monitoring to ensure workers complied with restrictions. The Midas team clearly set out site rules and requirements to all members of the supply chain, confirming site standards and providing recognition and rewards for good performance, and providing copies of the traffic management plan and logistics plan to all operatives. The site scheduled deliveries to avoid busy periods, with no deliveries permitted before 9am and avoiding the end of the school day, and noisy works restricted to the afternoon (3.15pm to 5.00pm) to avoid disturbing lessons.
The school requested additional works late in the programme
To incorporate the request for additional works, Midas liaised with the school to agree a revised programme. The team implemented a countdown programme, completed additional hours and carried out quality checks during the works. The Midas team closely monitored contractors during the final stages of the project to ensure workers maintained safety standards during the busiest phase of the works, and maintained careful coordination of subcontractors. The team completed the total project, including additional works, to a high standard of quality and to programme.
The project included installation of a mains electrical substation
To ensure safe installation of the mains electrical substation, Midas completed a ground penetrating radar survey, identifying routes of new and existing services, before compiling a Risk Schedule/ Register. Midas collaborated with SSE (the services supplier who relocated services and removed redundant cables) ensuring the project benefitted from early risk identification. The team encouraged stakeholder input during regular risk meetings, established “no dig” zones along known service routes to reduce risk, used trial pits and hand excavation and completed groundworks under permits to excavate. The team secured Heras panels around the works, with clear signage, and installed protective barriers within public highways during utility connections. At the start of the programme, the site’s power supply ran from generators (with back-up) before connecting into the new mains following installation of the substation. Following this, Midas worked around live services, identifying and removing redundant services in association with SSE.
Our Success
Our Learnings
Value Added
| Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
| Cost | £3,229,311 | £3,250,840 | £21,529 (0.7%) |
| Time | 37 weeks | 37 weeks | 0 weeks |
KPI Graphs
Apprentices 4
Average AIR 0
Average CCS score 42
Waste diverted from landfi ll 93.7%
Cost/m2 £2,995m²
Cost/m2 excl abnormals £2,342m²
Cost/m2 Industry average £ m²
A new-build 2FE school to provide a permanent new home for Ashmole Primary School. The school created 420 places for pupils aged four to 11 and provides teaching space for KS1 and KS2 along with offices, a sports hall, a community room and a canteen.
The school was built on a land-filled site with debris built up from previous excavations in the local area. The ground was found to contain asbestos and obstructions. The risk was quantified and a management strategy was put in place to remove the asbestos and obstructions from the site. This put significant pressure on the project programme.
The use of SIPs achieved a 10 week programme saving during the pre-construction phase and a five week programme saving during the construction phase of the project. This has led to SIPs being used on subsequent SCF and Morgan Sindall projects. The frame, including the roof, floor and walls, was installed in 13 weeks, which is a significant saving compared to traditional construction methods.
The use of SIPs achieved a 10 week programme saving during the pre-construction phase and a five week programme saving during the construction phase of the project. This has led to SIPs being used on subsequent SCF and Morgan Sindall projects. The frame, including the roof, floor and walls, was installed in 13 weeks, which is a significant saving compared to traditional construction methods.
100% payment within 30 days terms
98% waste diverted from landfill
100% timber responsibly sourced
Zero RIDDORs
CCS Score 39/45
7 work experience placements
94 apprenticeship weeks
£5k charitable donations
23 SMEs
Soft landings for handover
Dedicated Morgan Sindall point of contact
On-line portal for notifying any defects with 3 priority categories for response times
Email: james.wright@hants.gov.uk
Phone: : 07761 330560
Email: alan.smedley@morgansindall.com
Phone: 07967 686066
Somerset
Project Team
Project Manager
Aecom
Architect
AWW
Civil Engineer
Services Design Solution
A challenging site that had to battle flooding after a string of winter storms, the team involved have overcome numerous obstacles to deliver the school successfully to Somerset County Council.
The team had to undertake a major value engineering process, which led to a substantial redesign to bring the project in to budget, as well as building on a site with significant drainage issues.
The team designed a bund to provide acoustic protection for the school from the neighbouring motorway (M5), all while maintaining strong and collaborative working relationships between all parties.
However, Willmott Dixon are experts in navigating complex and challenging builds, finding solutions and making sure the works carried out meet expected requirements, so we were able to successfully deliver the project to a high standard.
Construction of a new 160 Place All-Through Special Educational Needs School (SEN) with administration facilities, hydrotherapy pool, sensory areas, carparking and other required facilitating and external works on greenfield land. Also include the construction of a spine road to facilitate access to the new school.
Willmott Dixon’s team of education specialists have constructed a state of the art, new two-storey SEN School in Bridgwater creating 160 school places, bringing pupils from two existing sites under one roof.
The new all-age school includes accessible classrooms, dining hall, sports hall, sensory and therapy rooms and a hydrotherapy pool. Outside a sensory garden, multi-use games area and adventure playground will provide lots of spaces to support the pupils’ physical and sensory needs.
99% prompt and fair payments
Zero Harm
97% waste diverted from landfill
Handover & Aftercare Contractor Promise
Email: kingsley.clarke@devon.gov.uk
Phone: 07805760622
Email: guy.dawes@willmottdixon.co.uk
Phone: 07989 179444
Client
Buckinghamshire County Council
Project Manager
WYG
Architect
BAM Design
Contractor
BAM Construction
Value
£24.6 million
Contract Period
68 weeks
Procurement Type
Design & Build
Form of Contract
JCT 2017
Apprentices
9
BAM built Buckinghamshire’s first ‘satellite’ school in Aylesbury – an extension of St Michael’s Catholic Secondary School, High Wycombe, which opened in September 2019.
The satellite plan, a partnership between the county council, St Michael’s governors and trustees, and the Diocese of Northampton, caters for 900 students aged between 11 and 19. The new school is based on the former Quarrendon School site, where there is a Bucks CC Adult Education Centre, a pre-school and youth club. There is also a Multi-Use Games Area (MUGA), a grass pitch and 3G all-weather pitch. The new building and grounds will be available for community use outside school hours. This includes main assembly hall and sports facilities.
Career Opportunities
Educational Aspects
Community & Residence
Local Supplies
Tight deadline
The project had a tight programme, with completion in 68 weeks. Working with our in-house disciplines BAM Design, BAM Plant and BAM Services Engineering, allowed us to improve the speed and efficiency of how the project was managed and delivered on site. The project was designed in a 3D environment under BIM level 2 requirements. The BIM execution plan was discussed in detail with the client upfront to understand exactly what the client wanted, and to minimise costs.
Heavy Clay Ground Conditions
Extensive groundworks were required at the start of the project due to heavy clay. A decision to use piled foundations and ground remediation reduced the construction risk on site.
Our Success
Our Learnings
Value Added
| Contract | Gateway 3 Contract Formation | Gateway 4 Final Account | Variation |
| Cost | £24,642,019 | £24,613,801 | £28,218 (saving) |
| Time | 68 weeks | 68 weeks | Nil |
Contact: Darren Birch, Framework Manager
Email: dbirch@bam.co.uk
The school, previously known as Bordon Secondary School needed to meet the requirements of 900 school places and relocate from the eastern side of town to a more central location for children in both Bordon and neighbouring Whitehill. In 2015, Bordon and Whitehill were selected by the NHS’s Healthy New Towns scheme in hopes to develop a healthier environment, a strong sense of community and better care services within the local area. It was therefore imperative that the new school included facilities that would boost the children’s well-being.
Due to constricting budget restraints, it was crucial that Kier worked closely with Hampshire County Council’s team and maintained consistent communication throughout the project to help bring their dream school to life.
In order to create a modern and cohesive learning environment that satisfies the councils’ design, a proposal was approved for a collegiate style campus with four separate buildings connected by a central courtyard. This courtyard was intended to be a social and teaching hub, therefore encouraging a positive and well-connected community.
As part of the town’s Healthy Living Masterplan, extensive consultation with Sport England was carried out to devise a diverse range of facilities that could be used by the children all year round, therefore encouraging activity. The school was built in an area easily accessible for residents of Bordon and Whitehill, acting as a gateway to intertwine the communities.
To prioritise sustainability, the project adopted a low-energy, fabric-first strategy by making the most of the surrounding and historical Woolmer Forest. This resulted in the school possessing beautiful views of nature, boosting student and faculty morale. Additionally, a large expanse of PV panels on the southern teaching wing’s roof provides 10% of the school’s energy requirements.
The new Oakmoor School is a modern building with two-storey teaching wings spanning from the central courtyard, with school halls and sports halls at either end. The covered courtyard effectively reduces internal floor area and prevents the corridors from becoming overcrowded. Additionally, entrances to teaching wings are defined by staircases, once again minimising the volume of students within corridors. Passing through the courtyard promotes a healthier lifestyle as students and teachers will get a breath of fresh air while traveling easily between classes.
10% energy requirements from green energy
Zero RIDDORs
900 academy places
Handover & Aftercare Contractor Promise
Email: james.wright@hants.gov.uk
Phone: 07761 330560
Email: james.parr@kier.co.uk
Phone: 07794218011
Client
Plymouth City Council
Project Manager
AECOM
Architect
Form Design Group
Contractor
Midas Construction Ltd
Value £6.1m
Contract Period
63 weeks
Procurement Type
Competitive tender – 2 stage
Form of Contract
JCT Design & Build 2011
Size 3,000m²
Apprentices
13
Oceansgate is the UK’s first marine enterprise zone, occupying a 35 hectare site on the southern edge of Devonport Dockyard, one of the largest naval dockyards in Europe. Delivering new opportunities and economic regeneration to a deprived area of Plymouth, Oceansgate has transformed derelict land into a site that aims to bring together marine-based businesses to create a world-class hub for industry. The development, designed by local architects, uses a layout and materials that
reflect the area’s naval history.
The project features a three-storey office and two single-storey industrial terraces, arranged in parallel rows and offering nearly 3,000m² of office and industrial space with provision for up to 21 businesses. Completed to a high standard, the finished buildings are steel portal frame with brickwork and blockwork, curtain walling and power floated concrete slabs; they feature fibre connectivity and internal floor layouts that can be subdivided to suit tenant requirements. Externally, Midas completed car parking, access roads and planting to improve the site’s appearance and ecology.
The development has been shortlisted in the ‘Regeneration’ category of the 2019 South West RICS awards and was shortlisted for ‘John Bracey Building of the Year’ in the 2018 The Building Forum Awards.
Career Opportunities
The project had demanding site conditions, including the discovery of underground wells, basements, oil and asbestos
Prior to commencement of works, Midas reviewed all Ordnance Survey maps of the area and commissioned a ground penetrating radar scan of the site for unexploded ordnance, as Devonport Dockyard was heavily targeted for bombing during World War Two. During excavation works the team discovered several voids including basements, bank vaults and foundations of buildings destroyed during the Blitz. Midas pumped 400 tonnes of Type 1 granular fill compactable material into the holes, solid enough for the 55-tonne crane to sit on, and filled other excavations with concrete. The site fenced off excavations, with a vehicle controller in place to guide operations of plant and excavation machinery, and tested the ground for stability before each stage of the works. The team completed excavations under close, careful management, utilising remote compactors over the arches and basements to avoid risk to operators.
The development had a challenging, innovative design that included a kinetic wall, the first of its kind in the West Country
Midas joined this design and build project at RIBA Stage 2. The innovative design included use of a kinetic wall to reflect light and move with the wind, and random rubble stone cladding to some elevations. Midas constructed the kinetic wall, which is nearly six metres wide and over seven metres high, with 1,786 aluminium shingles affixed to steel wires attached to a full-height screen over the main entrance. It is the first of its kind in the west country and provides a distinctive feature of the development. Midas completed and connected the gable ends of the buildings early in the project, adjusting the programme to mitigate this requirement and completing the gable ends as soon as possible to make the buildings watertight and enable progression of interior works. Internally, the structural grid and division walls were designed to be easily combined to provide larger floor plates to respond to market interest.
The client required achievement of BREEAM Excellent
Midas successfully achieved BREEAM Excellent through provision of bicycle storage; attaining a lower Building Emission Rate than the Target Emission Rate; and installation of one bat box, one bird box and one bee brick on each building. Midas fitted a PV array to the roof of the office, with an estimated annual generation of 19,616.00kWh and a declared net capacity of 20.00kWh. The team also planted verges and trees, improving the site’s ecology, and achieved a 98% recycling figure, with demolition waste sent for reprocessing and reuse.
Our Success
Our Learnings
Value Added
| Contract | Gateway 2 Planning | Gateway 3 Contract Agreement | Variation |
| Cost | £5,809,000 | £5,425,000 | -£384,000 (-6.6%) |
| Time | 48 weeks | 48 weeks | 0 weeks |
KPI Graphs
KPI Graphs Apprentices 13
Average AIR 0
Average CCS score 40
Waste diverted from landfi ll 98.9%
Cost/m2 £3,837m²
Cost/m2 excl abnormals £3,017m²
Cost/m2 Industry average £ m²
Surrey County Council
Project Team
Architect
HGP Architects
Civil Engineer
Lyons O’Neill
As part of its global expansion, L3 commissioned a new £40m training and production facility on a site owned by Surrey County Council just a few miles from Gatwick Airport. The Nexus Training and Production Facility is critical for the UK’s aviation industry, as it will attract huge amounts of inward investment.
Engineering solutions were required due to the ground contamination and temporary works were needed on the existing retaining wall which made meeting the programme end date a challenge.
Willmott Dixon deployed a team of commercial building specialists to create the exact conditions needed for the fixed-based simulators as well as briefing rooms, classrooms, meeting rooms and a restaurant.
To meet the challenge of having a fully operational facility by summer 2019 an experienced management team were on hand to ensure any requests for changes were accommodated and fitted into a complex building schedule, making sure the 60,000 square foot facility came in on schedule.
The project involves creating two rather special buildings. The first is a global centre for excellence in airline training and houses eight flight simulators, each costing £12m. It also includes a number of fixed-based simulators plus briefing rooms, classrooms, meeting rooms and a restaurant.
The second building, opposite, is a similarly sized facility to manufacture 30 simulators a year and be a base for more than 300 employees.
99%
Waste diverted from landfill: 99%
Solar power was used to power temporary site accommodation
Zero Harm
Shortlisted for LABC awards 2020
Safety tours undertaken on for local school children
Handover and aftercare process followed
Email: kingsley.clarke@devon.gov.uk
Phone: 07805760622
Email: guy.dawes@willmottdixon.co.uk
Phone: 07989179444